Hawkins Construction Co. v. Matthews Co., Inc.

209 N.W.2d 643, 190 Neb. 546, 12 U.C.C. Rep. Serv. (West) 1013, 1973 Neb. LEXIS 748
CourtNebraska Supreme Court
DecidedJuly 27, 1973
Docket38627
StatusPublished
Cited by109 cases

This text of 209 N.W.2d 643 (Hawkins Construction Co. v. Matthews Co., Inc.) is published on Counsel Stack Legal Research, covering Nebraska Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Hawkins Construction Co. v. Matthews Co., Inc., 209 N.W.2d 643, 190 Neb. 546, 12 U.C.C. Rep. Serv. (West) 1013, 1973 Neb. LEXIS 748 (Neb. 1973).

Opinions

White, C. J.

This is an action for property damage sustained by plaintiff Hawkins Construction Company as a result of the collapse of a scaffold manufactured by the defendant Waco Scaffold and Shoring Company and leased to the plaintiff by the defendant Matthews Company, Inc. The jury returned a verdict for the plaintiff and against both defendants in the amount of $32,635.48. We affirm the judgment of the District Court.

Because of the complex nature of this case, a careful review of the facts is necessary. In May of 1968, the plaintiff Hawkins Construction Company entered into a contract with Swift and Company of Chicago under the terms of which plaintiff was to construct a ham canning facility for Swift at 94th and J Streets in Omaha, Nebraska. A substantial amount of scaffolding equipment was needed for the job, and the plaintiff made an investigation as to availability, cost, and similar factors. Because of the frequent need which companies like the plaintiff have for scaffolding equipment, manufacturers and suppliers periodically send it advertising brochures, and the plaintiff had a complete set of the latest brochures [549]*549in its office. Among the pamphlets was one published by the defendant Waco, which the plaintiff had received from Mr. William Matthews of the defendant Matthews Company, Inc. The back cover was rubber-stamped with one of the Matthews Company’s trade names, “Scaffold Rental & Sales Co.,” together with its address and phone number.

The Waco pamphlet described the various types of scaffold components manufactured by the company, and provided pictorial representations of suggested applications of the equipment. In addition, the pamphlet contained the following statement: “Waco HI-LOAD shoring equipment is designed to safely carry working loads up to 20,000 pounds per panel. This is twice the load capacity of conventional steel scaffolding.” The pamphlet later reiterated the claim in the following manner: “HI-LOAD panels will safely carry individual concentric loads up to 10,000 pounds per leg as illustrated. These loads were established following test procedures recommended by the Steel Scaffolding and Shoring Institute.” Accompanying this text was a drawing of a scaffold panel with the number “10,000” above each of its two legs.

Thomas Lang, plaintiff’s job sponsor on the Swift project, testified that he relied on statements made in the brochure in entering the lease arrangement for Waco equipment with the defendant Matthews Company. Fred Hawkins, president and majority stockholder of the plaintiff, testified at trial that he also relied on the brochure in helping to make the decision to use Waco scaffolding, but in a deposition prior to the trial he had testified that there was “no particular thing” he read or saw that influenced his thinking, and that price was an important factor as well.

In any case, the decision was made to use Waco scaffolding, and to lease it from the defendant Matthews Company. Lang, the job sponsor,^went to William Matthews, described the project and the purposes for which [550]*550the equipment was to be used, and provided him with blueprints of the job. In time, the plaintiff received back from Matthews a series of drawings prepared by-Waco showing the recommended scaffolding configuration for the plant’s construction, and work on the project began.

The purpose of the scaffolding involved in the collapse was the support of the roof deck cement pour. The plaintiff’s men first consulted soil compact tests made by a local laboratory in an effort to determine whether the foundation upon which the scaffold would be erected was firm. Under the supervision of Thomas Flynn, the plaintiff’s carpenter foreman, “mud sills” were then placed on the ground to support the structure. These sills consisted of 2 x 12 inch boards laid flat on the ground, and their purpose was to prevent sinkage by distributing the weight of the scaffold and its load more evenly over the base soil. Screw jack base plates, permitting vertical adjustment of the panels, were then nailed to the mud sills, and levels were taken at each stage of this assembly to insure that the base scaffold structure was perfectly horizontal. The tubular frame panels forming the bottom section of the structure were then fitted into the base plates.

The roof deck construction required the scaffolding to reach to a height of 20 feet and, since each scaffold panel is only 6 feet high, the job thus required panels to be stacked on top of each other until the desired height was reached. In order to accomplish this, the plaintiff had ordered tubular connectors, manufactured by the defendant Waco, from the defendant Matthews Company. These connectors are merely hollow tubes with an interior diameter slightly larger than the tubular-feet of a scaffold panel. Connectors are fitted over the tubular supports of the bottom panel, and the upper panel is then stacked on top by fitting its feet into the connectors.

Originally, these connectors were manufactured by [551]*551simply welding a reinforcing ring washer to the outside center of a solid length of pipe. More recently, however, the connectors have been formed by hydraulically pressing two smaller lengths of pipe together with an amount of pressure greater than their yield value, so that the two pieces deform at the center to form an exterior ridge as they join. All this is accomplished without heating the connector components, and the procedure is correspondingly known as a “cold form process.” It was the latter type of connector which Matthews Company provided for the plaintiff’s use on the Swift job, and the effect of the cold form process on the stability of these connectors is actively disputed.

Once the panels have been stacked to reach the desired height they are topped off with “shore heads,” U-shaped holders designed to cradle some of the supportive lumber bracing which will underly the plywood pour base. More specifically, the short heads cradle the “ledgers,” which consist of a minimum of three and sometimes four 2 x 12’s nailed together front to back and fitted into the shore heads on edge. That is, if three 2 x 12’s are used, the ledger when installed would be 6 inches wide in the shore head and would stand 12 inches above it. The ledgers, in turn, support the “joists.” Joists are lengths of lumber placed on edge on top of the ledgers and at right angles to them. It is the joists which provide direct structural support to the plywood pour base above, and, in this case, they were placed 16 inches apart on center.

In the construction of these joists the plaintiff departed from the plans supplied to it. The variances involved the size of lumber used for joists and the type of structural bracing supporting them. It is undisputed that the Waco plans called for the joists to be made from 2 x 10’s and that the plaintiff used 2 x 12’s instead; thus the joists supporting the plywood pour base stood 12 inches off the ledgers rather than the recommended 10 inches. The plaintiff’s job sponsor admitted that one of the reasons 2 x 12’s were used was that they [552]*552are more versatile, and could be reused, either as joists or as ledgers, on other jobs.

The Waco plans also called for the joists to be supported by cross-bracing, and the plaintiff used horizontal bracing.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Tuscumbia City School System v. Pharmacia Corp.
871 F. Supp. 2d 1241 (N.D. Alabama, 2012)
Banks v. International Rental & Leasing Corp.
55 V.I. 967 (Supreme Court of The Virgin Islands, 2011)
Shipler v. General Motors Corp.
710 N.W.2d 807 (Nebraska Court of Appeals, 2006)
Bell Sports, Inc. v. Yarusso
759 A.2d 582 (Supreme Court of Delaware, 2000)
Trgo v. Chrysler Corp.
34 F. Supp. 2d 581 (N.D. Ohio, 1998)
Steele v. Encore Manufacturing Co.
579 N.W.2d 563 (Nebraska Court of Appeals, 1998)
Lutz Farms v. Asgrow Seed Company
948 F.2d 638 (Tenth Circuit, 1991)
Lutz Farms v. Asgrow Seed Co.
948 F.2d 638 (Tenth Circuit, 1991)
Meisner v. Patton Elec. Co., Inc.
781 F. Supp. 1432 (D. Nebraska, 1990)
Wheeler v. Sunbelt Tool Co.
537 N.E.2d 1332 (Appellate Court of Illinois, 1989)
Delgado v. Inryco, Inc.
433 N.W.2d 179 (Nebraska Supreme Court, 1988)
Forker Solar, Inc. v. Knoblauch
396 N.W.2d 273 (Nebraska Supreme Court, 1986)
Peterson v. North American Plant Breeders
354 N.W.2d 625 (Nebraska Supreme Court, 1984)
Erickson v. Monarch Industries, Inc.
347 N.W.2d 99 (Nebraska Supreme Court, 1984)
Nerud v. Haybuster Manufacturing, Inc.
340 N.W.2d 369 (Nebraska Supreme Court, 1983)
Brookins v. Sargent Industries, Inc.
717 F.2d 1201 (Eighth Circuit, 1983)

Cite This Page — Counsel Stack

Bluebook (online)
209 N.W.2d 643, 190 Neb. 546, 12 U.C.C. Rep. Serv. (West) 1013, 1973 Neb. LEXIS 748, Counsel Stack Legal Research, https://law.counselstack.com/opinion/hawkins-construction-co-v-matthews-co-inc-neb-1973.