Hancock v. Parks

110 N.W.2d 69, 172 Neb. 442, 1961 Neb. LEXIS 98
CourtNebraska Supreme Court
DecidedJune 30, 1961
Docket34952
StatusPublished
Cited by10 cases

This text of 110 N.W.2d 69 (Hancock v. Parks) is published on Counsel Stack Legal Research, covering Nebraska Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Hancock v. Parks, 110 N.W.2d 69, 172 Neb. 442, 1961 Neb. LEXIS 98 (Neb. 1961).

Opinion

Messmore, J.

The plaintiff, John V. Hancock, doing business as John Hancock Construction Company, brought this action at law in the district court for Dodge County against Leslie Parks, defendant, seeking to recover on quantum meruit for the reasonable value of services rendered to the defendant. The jury returned a verdict finding in favor of the plaintiff and against the defendant, and assessed the amount of plaintiff’s recovery in the sum of $1,000. Judgment was rendered on the verdict. The defendant filed a motion for judgment notwithstanding the verdict or in the alternative for a new trial. This motion was overruled.. Defendant perfected appeal to this court.

The plaintiff’s petition, insofar as necessary to consider, alleged that at the special instance and request of the defendant, the plaintiff furnished services for the defendant commencing on August 26, 1958, using a caterpillar tractor and operator through September 4, 1958, a motor patrol and operator on September 12 and 13, 1958, and a caterpillar tractor and operator on October 17 and 18, and November 21, 1958; that the total *444 amount of services rendered, amounted to $1,179; that this sum represented the reasonable and agreed value of the said services; that despite repeated demands for payment thereof more than 90 days prior to the institution of this action, no part of said sum had been paid except the sum of $100 on January 12, 1959, leaving a balance due of $1,079 which the plaintiff voluntarily reduced to $1,000; and that the plaintiff sought to recover no more than $1,000 with interest at 6 percent from February 22, 1959. The plaintiff also asked for attorney’s fee to be-taxed as costs by virtue of section 25-1801, R. R. S. 1943, and costs of suit.

The defendant, in his answer, alleged that he entered into a written contract with the plaintiff on June 16, 1958; that on June 28, 1958, he paid the plaintiff $1,000 on the contract; that on July 25, 1958, he paid the plaintiff $1,000 on the contract; that on January 12, 1959, he paid the plaintiff $500; that the items of work alleged to have been performed by the plaintiff relate to work to be performed under the written contract dated June 16, 1958; that the plaintiff failed to carry out the terms of the written contract and the plaintiff’s neglect in doing so caused the defendant to employ other persons to complete the work as provided for in the contract; that nevertheless on January 12, 1959, defendant delivered to plaintiff his check in the sum of $500, mentioned above, which the plaintiff accepted and cashed; and that the plaintiff accepted and received said check in full satisfaction and discharge of any and all liability of the defendant to the plaintiff. The defendant’s answer denied all allegations of the plaintiff’s petition not admitted.

The plaintiff’s reply admitted the written contract dated June 16, 1958, and the payments made thereunder; and denied that the work done by the plaintiff' related to work under the written contract. The plaintiff denied that he failed to carry out the terms of the written contract, and denied that the check for $500 dated Janu *445 ary 12, 1959, was in full satisfaction of the defendant’s liability to the plaintiff. Other allegations of the defendant’s answer were denied generally.

The record discloses that the plaintiff is in the contracting business; that between August 10 and 15, 1958, at the defendant’s request, he went to see the defendant; and that the defendant wanted the plaintiff to do some work for him to make the water on the defendant’s land go to the north before it went east, and to put in more dirt. The evidence further discloses that starting on August 26, 1958, to and including November 21, 1958, the plaintiff furnished a caterpillar tractor and operator, and a motor patrol and operator, working for the defendant a designated number of hours for a total amount of $1,179. The plaintiff testified that he was paid $100; and that he was reducing the balance of $1,079 to $1,000. The plaintiff further testified that he obtained dirt from a new cut-off ditch on the north side of the defendant’s property, and hauled the dirt 3,000 to 4,000 feet; that there were between 1,500 and 2,000 cubic yards of dirt hauled; that he did other work for the defendant under a contract; that the defendant was going to build a trailer court on his land; that the plaintiff did the work called for under that written contract and was paid for it; and that this work was completed sometime in the first 10 days of July 1958.

On cross-examination the plaintiff testified that the job which was commenced in August was a “fill” job, to fill the area so the water would run to the western slope, to make it go west; that the dirt was put on the east side of the defendant’s property line, which made the water flow west and north to the cut-off ditch; and that there was no discussion as to how long the job would take or what the cost would be.

A written contract dated June 16, 1958, which was admitted and designated exhibit No. 3, reads in part as follows: “John Hancock Const. Co. agrees to do the following work for the sum total of $2400.00. Dirt to be *446 hauled from the new ditch North l/4th mile and East only. 1. Fill old creek bed with a slope to East of approx. 2' from West rock road to East side of creek bed. 2. Fill front of building site .8 below pavement with slope of V east and slope of 3' North on West of East property line. 3. Grade to North property line from county road to approx. 250' East. 4. Grade to be on person property only. 5. Finish fill areas. Payment to be made on day of completion.” This contract was signed by the plaintiff and defendant.

The plaintiff further testified on cross-examination that he submitted the first bill to the defendant September 19, 1958, by handing it to him; that the defendant said that he did not have the money at that time; that he asked the defendant several times to pay the bill; and that he delivered a bill to the defendant around November 5, 1958, and asked the defendant if he could pay the bill. The defendant told the plaintiff that he did not have his Standard Oil loan through, and that when he got $500' for the old house he sold he would give that amount to> the plaintiff.

The plaintiff’s wife testified that she assisted the plaintiff in his business by taking care of the books and preparing the bills for the jobs the plaintiff was doing. She prepared the bills covering the period from August 26, 1958, until the completion of the work. This witness further testified that the timesheets of their employees are turned over to her, and show the work done for the defendant.

The testimony of a witness for the plaintiff who operates the machinery necessary to do the work corroborated the plaintiff’s evidence relating to the work done by him from August 26, 1958, to and including the date of finishing the work.

The defendant testified to the physical characteristics of his property in June 1958; that at that time old Rawhide Creek was blocked off west of his property to the road, and new Rawhide Creek was built to bring fill *447

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Vistar Bank v. Thompson
530 N.W.2d 910 (Nebraska Supreme Court, 1995)
Lanphier v. Omaha Public Power District
417 N.W.2d 17 (Nebraska Supreme Court, 1987)
Hawkins Construction Co. v. Matthews Co., Inc.
209 N.W.2d 643 (Nebraska Supreme Court, 1973)
Halbert v. Food Host U.S.A., Inc.
202 N.W.2d 735 (Nebraska Supreme Court, 1972)
Lucht v. American Propane Gas Co.
162 N.W.2d 891 (Nebraska Supreme Court, 1968)
In Re Crusinberry's Estate
126 N.W.2d 481 (Nebraska Supreme Court, 1964)
Sterner v. Lehmanowsky
113 N.W.2d 588 (Nebraska Supreme Court, 1962)

Cite This Page — Counsel Stack

Bluebook (online)
110 N.W.2d 69, 172 Neb. 442, 1961 Neb. LEXIS 98, Counsel Stack Legal Research, https://law.counselstack.com/opinion/hancock-v-parks-neb-1961.