Lucht v. American Propane Gas Co.

162 N.W.2d 891, 183 Neb. 583, 1968 Neb. LEXIS 593
CourtNebraska Supreme Court
DecidedDecember 6, 1968
Docket36728
StatusPublished
Cited by8 cases

This text of 162 N.W.2d 891 (Lucht v. American Propane Gas Co.) is published on Counsel Stack Legal Research, covering Nebraska Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Lucht v. American Propane Gas Co., 162 N.W.2d 891, 183 Neb. 583, 1968 Neb. LEXIS 593 (Neb. 1968).

Opinion

Spencer, J.

This is an action for damages sustained to property of the plaintiff in an explosion and fire, which occurred November 11, 1963, on the premises of the plaintiff when plaintiff subjected a propane tank truck, delivered to him for painting, to intense heat in a bake oven as part of the painting and drying process. A jury returned a verdict against all defendants in the sum of $86,200. Defendants perfected appeals to this court.

In determining the sufficiency of evidence to sustain a judgment, it must be considered in the light most favorable to the successful party. Every controverted fact must be resolved in his favor and he is entitled to the benefit of every inference that can reasonably be de *585 duced from the evidence,. Thompsen v. Miller, 177 Neb. 530, 129 N. W. 2d 498.

Applying the criterion above, we determine the facts to be as set out herein: American Propane Gas Company, a corporation, hereinafter referred to as American, delivered the truck, which was propelled by propane gas, to Phillips Petroleum Company, a corporation, hereinafter referred to as Phillips, for repair and painting. The truck in question carried liquid propane gas in two side-by-side cargo tanks, with a smaller supply tank on top which was used to propel it. After Phillips had completed the repair work, McCord, the district maintenance supervisor for Phillips, had the truck delivered to plaintiff to be painted because Phillips did not have the facilities to do the work.

Before it delivered the truck to Phillips, American pumped out all of the liquid gas in the two cargo tanks on the truck but, having no facilities to do so, did not steam clean or purge them. After Phillips’ employees delivered the truck to plaintiff’s premises, the plaintiff observed that one of the petcocks on the truck was frosted, which indicated to him that the tank still had some gas in it. Plaintiff then called McCord, told him about the petcock, and advised him that he would not paint the truck unless it was purged. He also told McCord that since the exterior of the truck was rough it should be sandblasted. Neither plaintiff nor Phillips had the facilities to sandblast or purge the vehicle. It is plaintiff’s testimony that McCord instructed him to send the truck to Transport Repair Service, a corporation, hereinafter referred to as Transport. It is McCord’s testimony that he instructed plaintiff to obtain a bid on the sandblasting and purging.

Exhibit 67 is an invoice furnished by plaintiff, dated November 7, 1963. This invoice indicates that plaintiff was to bill Phillips for the sandblasting and purging as well as for the painting. Plaintiff delivered the truck to Transport. Subsequently, Transport’s foreman called *586 plaintiff and. told him they would not sandblast the truck unless it was purged. Plaintiff told him that was what it was sent down for, and asked the cost. The foreman could not give plaintiff an estimate. Later, plaintiff obtained a bid by telephone from Reuben Johnson, Transport’s president. Plaintiff communicated this bid to McCord, who thought it was too high. McCord told plaintiff he would have to check it out with his employers, which he did. In the interim, McCord happened to see Johnson at a restaurant, and asked him about the bid and was told he could take it or leave it. On this occasion, Johnson told McCord that Transport would not sandblast the truck without purging it. Subsequently, McCord received authority to accept the bid. He attempted to contact the plaintiff, who was out of the city. When he could not do so, he called Transport’s foreman by telephone and told him to go ahead with the job. The next day McCord told plaintiff he had instructed Transport to go ahead with the job.

McCord did not have possession of the truck after it was delivered to plaintiff. McCord had no contact with Transport after he told Transport’s foreman to go ahead with the job, or with plaintiff after he relayed this information to him, until after the explosion. He did not see the truck after plaintiff delivered it to Transport. When he told Transport’s foreman to go ahead with the job, it was his understanding the truck would be purged, because he had been told Transport would not sandblast the truck without purging it and that plaintiff would not paint it unless it was purged. The bid which he had submitted to his superiors was for both jobs.

After Transport sandblasted the truck, its foreman called plaintiff and told him the truck was ready. Plaintiff sent an employee to bring the truck back to his shop, but did not receive a work order or ascertain what work Transport had done. This was sometime Friday afternoon, November 8, 1963. The employee who painted the *587 truck testified that when he began work that afternoon, he detected the odor of gas, It smelled like rotten eggs. He could smell gas even when the truck was not running. Neither this employee nor the plaintiff checked to see if the truck had actually been purged. The evidence is undisputed that this fact could have been readily determined by turning a petcock.

The lower portion of the truck was painted on Saturday and driven into the bake oven for a period of 15 minutes to dry the paint. This bake oven is heated to 180 degrees for the drying process. Monday, November 11, 1963, the painting on the truck was completed and it was backed into the bake oven about 11:15 a.m. When the painter returned from lunch, about 1 pan., he heard a hissing noise coming from the furnace room. He ran to that room and turned the switch which controlled the flame of the furnace. He then said to his foreman, “I think there’s something wrong,” and the explosion occurred. Less than a minute elapsed between the time the painter heard the hissing noise and the explosion. It was this employee’s testimony that at the time he drove the truck into the bake oven he knew it contained some form of gas.

After the explosion, in the presence of plaintiff, Johnson, Transport’s president, told the fire captain that the truck had been purged. It is undisputed that the truck had not been purged, and that Transport did not inform plaintiff or his employees of this fact.

American and Phillips moved for directed verdicts at the close of the evidence, and after the verdict, for judgments notwithstanding the verdict. These motions were overruled. It is apparent that the trial court believed that these defendants had a nondelegable duty to furnish plaintiff with a truck which had been purged in a proper manner for painting. We do not question the duty in the usual situation to furnish a truck which had been purged in a proper manner for painting of to direct attention to the fact that the truck had not been purged. *588 The general rule where a party is responsible for a dangerous instrumentality is that he is charged with the duty to take suitable precautions to avoid injury or damage to persons or property rights in its proximity, and his failure to do so is negligence. Adapted from Rose v. Buffalo Air Service, 170 Neb. 806, 104 N. W. 2d 431. That is not the situation we have in the present case.

Granting that a propane transport is a dangerous instrumentality, this case is readily distinguishable from those where a duty may be nondelegable.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

State v. Penas
263 N.W.2d 835 (Nebraska Supreme Court, 1978)
Daniels Ex Rel. Jones v. Andersen
237 N.W.2d 397 (Nebraska Supreme Court, 1975)
Halbert v. Food Host U.S.A., Inc.
202 N.W.2d 735 (Nebraska Supreme Court, 1972)
Sacco v. Gau
199 N.W.2d 605 (Nebraska Supreme Court, 1972)
McBride Ex Rel. Last Will of McBride v. Fort Kearney Hotel, Inc.
176 N.W.2d 911 (Nebraska Supreme Court, 1970)
Gillotte v. Omaha Public Power District
176 N.W.2d 24 (Nebraska Supreme Court, 1970)

Cite This Page — Counsel Stack

Bluebook (online)
162 N.W.2d 891, 183 Neb. 583, 1968 Neb. LEXIS 593, Counsel Stack Legal Research, https://law.counselstack.com/opinion/lucht-v-american-propane-gas-co-neb-1968.