L.J. Vontz Construction Co. v. Department of Roads

440 N.W.2d 664, 232 Neb. 241, 1989 Neb. LEXIS 234
CourtNebraska Supreme Court
DecidedMay 19, 1989
Docket88-925
StatusPublished
Cited by50 cases

This text of 440 N.W.2d 664 (L.J. Vontz Construction Co. v. Department of Roads) is published on Counsel Stack Legal Research, covering Nebraska Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
L.J. Vontz Construction Co. v. Department of Roads, 440 N.W.2d 664, 232 Neb. 241, 1989 Neb. LEXIS 234 (Neb. 1989).

Opinion

Shanahan, J.

L. J. Vontz Construction Co., Inc. (Vontz), appeals from the judgment of the district court for Lancaster County, which affirmed the order of the Department of Administrative Services (DAS), dismissing Vontz’ contract claim barred by the statute of limitations.

FACTS

On September 27,1983, Vontz and the Department of Roads (DOR) of the State of Nebraska entered a written contract whereby Vontz was the contractor on construction Project No. OM-AD-36(9) Div. II in Cheyenne County, Nebraska. Vontz commenced work on the project on May 9, 1984. In a letter dated July 23, 1984, DOR declared Vontz in default under the contract and ordered Vontz to remove its personnel and equipment from the project sites. In April of 1985, DOR made its last payment to Vontz for its work done before ouster of Vontz from the construction sites.

On February 3, 1987, Vontz filed its claim with DAS and alleged that DOR had breached the construction contract with Vontz. See Neb. Rev. Stat. § 77-2406 (Reissue 1986) (DAS examination of contract claims against the state). All the conduct of DOR alleged as a basis for the Vontz claim occurred on or before July 23, 1984. DOR filed a motion to dismiss Vontz’ claim, asserting that the claim was barred by the statute of limitations contained in Neb. Rev. Stat. § 25-218 (Reissue 1985), which in pertinent part provides: “Every claim and demand against the state shall be forever barred, unless the action be brought thereon within two years after the claim arose.” In response to the DOR motion, Vontz contended that its contract claim or cause of action did not accrue until DOR *243 made its final payment in April 1985.

DAS found that Vontz’ right to claim a breach of the construction contract accrued on July 23, 1984, when DOR declared Vontz in default and prevented further performance of the contract. Because Vontz did not file its claim with DAS until February 3,1987, DAS found the claim was barred by § 25-218 and, pursuant to DOR’s motion, denied Vontz’ claim.

Vontz appealed to the district court. See Neb. Rev. Stat. § 77-2407 (Reissue 1986) (appeal to the district court in the manner provided by Neb. Rev. Stat. §§ 84-917 to 84-919 (Reissue 1987) of the Administrative Procedure Act). The district court affirmed DAS’ denial of the Vontz claim.

The issue, one of first impression before this court, is whether an administrative agency, charged with examining and approving contract claims for payment by the state, is empowered to dismiss a claim which is barred by the statute of limitations.

We realize that, during the pendency of Vontz’ appeal, the Legislature repealed § 77-2407 and enacted the State Miscellaneous Claims Act, Neb. Rev. Stat. §§ 81-8,294 to 81-8,301 (Cum. Supp. 1988), and the State Contract Claims Act, Neb. Rev. Stat. §§ 81-8,302 to 81-8,306 (Cum. Supp. 1988). The State Miscellaneous Claims Act and the State Contract Claims Act altered the procedure for payment of a claim against the state which existed when Vontz filed its claim, and now provide for possible original judicial determination of contract claims against the state. However, the procedures under the claims acts, enacted after the disposition of Vontz’ claim, are irrelevant to Vontz’ appeal.

LIMITATION OF ACTIONS

“Statutes of limitations have an important role in disposition of claims between individuals, because such statutes promote and produce finality and thereby stability in human affairs. In this manner statutes of limitations stimulate activity and punish unreasonable delay in prosecuting claims.” Rosnick v. Marks, 218 Neb. 499, 501, 357 N.W.2d 186, 188 (1984).

Our law is clear regarding the operation of a statute of limitations in a civil action. “If a petition alleges a cause of action ostensively barred by the statute of limitations, such *244 petition, in order to state a cause of action, must show some excuse tolling the operation and bar of the statute.” Rosnick, supra at 501-02, 357 N.W.2d at 188; S.I.D. No. 145 v. Nye, 216 Neb. 354, 343 N.W.2d 753 (1984). When it is apparent from the face of the petition that the action is barred by a statute of limitations, the petition fails to state a cause of action and is subject to a general demurrer. Vielehr v. Malone, 158 Neb. 436, 63 N.W.2d 497 (1954). See Neb. Rev. Stat. §§ 25-806 and 25-807 (Reissue 1985). When it is not apparent from the face of the petition that the action is barred by the statute of limitations, the affirmative defense of the statute of limitations must be raised in the answer. Vielehr, supra. Since a defendant cannot raise the statute of limitations for the first time on appeal, a defendant waives the statute of limitations by failure to raise the issue in a demurrer or the defendant’s answer. Vielehr, supra.

The foregoing observations concerning a petition in a civil action are analogously applicable to a contract claim against the state, that is, a claimant’s contract demand for money from the state.

We also recognize that Nebraska civil procedure does not authorize a pretrial motion to dismiss, or, as expressed in Voyles v. DeBrown Leasing, Inc., 222 Neb. 250, 256, 383 N.W.2d 36, 40 (1986): “A pretrial motion to dismiss is not permissible as a pretrial pleading but may sometimes be recognized as a demurrer on stipulation of the parties or by rule of court.”

Although we have noted general rules of procedure pertaining to the statute of limitations in pleadings applicable to civil actions, we realize that the rules which we have mentioned are part of a procedure which is inapplicable to actions before an administrative agency. Thus, we are confronted by the contract claims act under which Vontz filed its claim, a legislative provision which contains no procedural mechanism for raising the statute of limitations as an issue concerning a contract claim against the state. Without a means to raise the statute of limitations at the level of the administrative hearing before DAS, the State (DOR) could not raise the statute of limitations for the first time on appeal to the district court. See Vielehr v. Malone, supra.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Susman v. Kearney Towing & Repair Ctr.
310 Neb. 910 (Nebraska Supreme Court, 2022)
Custom Hair Designs by Sandy v. Central Payment Co.
984 F.3d 595 (Eighth Circuit, 2020)
Steen v. Murray
955 F. Supp. 2d 1030 (D. Nebraska, 2013)
Irving F. Jensen Co. v. State
719 N.W.2d 716 (Nebraska Supreme Court, 2006)
Weeder v. Central Community College
691 N.W.2d 508 (Nebraska Supreme Court, 2005)
Snyder v. Case
611 N.W.2d 409 (Nebraska Supreme Court, 2000)
Welsch v. Graves
582 N.W.2d 312 (Nebraska Supreme Court, 1998)
Crown Products Co. v. City of Ralston
567 N.W.2d 294 (Nebraska Supreme Court, 1997)
MOTOR CLUD INS. ASS'N v. Fillman
568 N.W.2d 259 (Nebraska Court of Appeals, 1997)
Cavenaugh v. City of Omaha
567 N.W.2d 592 (Nebraska Court of Appeals, 1997)
Hroch v. Farmland Industries, Inc.
548 N.W.2d 367 (Nebraska Court of Appeals, 1996)
Emerson v. Zagurski
531 N.W.2d 237 (Nebraska Court of Appeals, 1995)
Baldwin Carpet Linoleum & Carpet, Inc. v. Builders, Inc.
523 N.W.2d 33 (Nebraska Court of Appeals, 1994)
Upah v. Ancona Bros. Co.
521 N.W.2d 895 (Nebraska Supreme Court, 1994)
Rosberg v. Lingenfelter
516 N.W.2d 625 (Nebraska Supreme Court, 1994)
Association of Commonwealth v. Moylan
517 N.W.2d 94 (Nebraska Supreme Court, 1994)

Cite This Page — Counsel Stack

Bluebook (online)
440 N.W.2d 664, 232 Neb. 241, 1989 Neb. LEXIS 234, Counsel Stack Legal Research, https://law.counselstack.com/opinion/lj-vontz-construction-co-v-department-of-roads-neb-1989.