Irving F. Jensen Co. v. State

719 N.W.2d 716, 272 Neb. 162, 2006 Neb. LEXIS 126
CourtNebraska Supreme Court
DecidedAugust 11, 2006
DocketS-04-1315
StatusPublished
Cited by51 cases

This text of 719 N.W.2d 716 (Irving F. Jensen Co. v. State) is published on Counsel Stack Legal Research, covering Nebraska Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Irving F. Jensen Co. v. State, 719 N.W.2d 716, 272 Neb. 162, 2006 Neb. LEXIS 126 (Neb. 2006).

Opinion

*163 McCormack, J.

NATURE OF CASE

Irving F. Jensen Company, Inc. (Jensen), appeals the decision of the district court which found that Jensen’s petition against the State of Nebraska, Department of Roads (DOR), was time barred.

BACKGROUND

In April 1998, Jensen and the DOR entered into a written contract whereby Jensen was the contractor on two construction projects commonly known as the Tarnov Wetland Site and US-81 South of Tarnov projects. The Tarnov Wetland Site, which is the subject of this action, involved the excavation and construction of a wetlands mitigation site.

With regard to the construction of the wetlands mitigation site, the contract provided:

The contractor will be required to remove 300,000 cubic meters of material from the wetland bank as “Excavation, Borrow” for [the US-81 South of Tarnov project]. The remainder of the material will be removed and paid for as “Excavation” for [the Tarnov Wetland Site],
The bottom one-half meter of the mitigation site and the 3 pond areas will be at or near the water table. This material will be wet and may be wasted at the site shown in the plans, not to exceed elevation 465.0, as directed by the engineer. This material would be suitable for use in the embankment, but will be slow to dry.

The contract also included by reference the “1996 Metric Supplemental Specifications to the Standard Specifications for Highway Construction Series 1985” (the Specifications), published by the DOR. Section 102.08 of the Specifications required in pertinent part that the bidder carefully examine the site of proposed work before submitting a proposal. Section 102.08 further provided that the submission of the bid was considered conclusive evidence that the bidder examined the site and was satisfied with and understood the conditions to be encountered in performing the work and other requirements of the contract.

Before commencing construction of the wetlands mitigation site, Jensen and its subcontractor for excavation of the site, J.R Theisen & Sons, Inc. (Theisen), determined that the soil conditions were wetter than anticipated at the time of bidding. As a *164 result of the wetter conditions, Jensen and Theisen determined that excavation measures different from those anticipated at the time of bidding would need to be employed and that the excavation of the site would be more costly than originally anticipated.

Section 104.02 of the Specifications provided as follows:

(1) Differing site conditions:
a. The Contractor shall notify the Department in writing of the specific differing conditions before they are disturbed, before any additional work is performed, and as soon as the condition is discovered.
(1) This includes subsurface or latent physical conditions which differ materially from those indicated in the contract.
(2) It also includes unknown physical conditions of an unusual nature and differing materially from those ordinarily encountered and generally recognized as inherent in the work provided in the contract.
b. Before the site is disturbed or the affected work is performed, the Engineer shall be given an opportunity to investigate.
c. Upon written notification, the Engineer will investigate the differing conditions. If the Engineer determines that they do materially differ and will result in an increase or decrease in the cost or time required for the performance of any work under the contract, a cost (excluding loss of anticipated profits) or time allowance adjustment will be made. The Engineer will make a written determination, and the contract will be modified in writing if a change is warranted.
d. No contract adjustment which results in a benefit to the Contractor will be allowed unless the Contractor has provided the required written notice.

Section 109.05(9)(a) of the Specifications provided:

In any case where the Contractor feels that extra compensation is due for “extra work” or material neither clearly covered in the contract nor ordered in writing by the Engineer, the Contractor shall give written notice of his/her intention to make a claim for such extra compensation before the work begins.

In the spring of 1998, Jensen and Theisen notified the DOR that conditions were wetter than anticipated at the time of bidding *165 and requested additional payment. Jensen and Theisen also notified the DOR that it intended to seek damages for the “extra work” not included in its original bid.

In May and July 1998, the DOR conducted two meetings regarding the wetlands mitigation site project. An engineer for the DOR testified that at the May meeting, the president of Theisen inquired into how the DOR had determined the volume of material to be removed from the wetlands mitigation site and the water table information. The engineer testified that he advised Jensen and Theisen that the DOR had estimated this information based on soil borings that the DOR had taken. The engineer testified that Jensen and Theisen did not request the information from the soil borings at that time. At the July meeting, Jensen again informed the DOR that it believed the water table was higher than stated in the contract and that in order to complete the project, it would have to proceed differently at an additional cost.

On July 29, 1998, the DOR informed Jensen that site conditions were not different from those indicated in the contract, and it denied in writing Jensen’s claim for additional compensation. Thereafter, rather than suffer liquidated damages, which Jensen faced under the terms of the contract if it did not complete the project within the authorized timeframe, Theisen began the excavation of the wetlands mitigation site. Following the completion of the excavation, Jensen calculated the extra costs it incurred as a result of the alleged differing site conditions and on September 7, 2000, made a claim for payment in the amount in excess of that allowed under the contract. On May 22, 2001, the DOR denied Jensen’s claim. Thereafter, the DOR issued its final acceptance of the work and completion of the project. Under the terms of the contract, the DOR reserved the right to make changes to the contract or changes to the estimated compensation until final acceptance.

On August 29, 2001, Jensen filed a claim against the DOR under the State Contract Claims Act, Neb. Rev. Stat. § 81-8,302 et seq. (Reissue 2003), with the State Claims Board. The DOR objected to the submission of Jensen’s claim to the State Claims Board, and the claim was withdrawn from consideration, allowing for the filing of a claim with the district court pursuant to *166 § 81-8,305(3).

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Susman v. Kearney Towing & Repair Ctr.
310 Neb. 910 (Nebraska Supreme Court, 2022)
Weyh v. Gottsch
303 Neb. 280 (Nebraska Supreme Court, 2019)
Keith v. Data Enters.
27 Neb. Ct. App. 23 (Nebraska Court of Appeals, 2019)
Keith v. Data Enterprises, Inc.
27 Neb. Ct. App. 23 (Nebraska Court of Appeals, 2019)
Sampson Construction Co. v. Martin
Nebraska Court of Appeals, 2018
SFI LTD. Partnership 53 v. Ray Anderson, Inc.
Nebraska Court of Appeals, 2017
Steen v. Murray
955 F. Supp. 2d 1030 (D. Nebraska, 2013)

Cite This Page — Counsel Stack

Bluebook (online)
719 N.W.2d 716, 272 Neb. 162, 2006 Neb. LEXIS 126, Counsel Stack Legal Research, https://law.counselstack.com/opinion/irving-f-jensen-co-v-state-neb-2006.