A.M. Cohron & Son, Inc. v. City of Columbus, Nebraska

CourtDistrict Court, D. Nebraska
DecidedJuly 7, 2021
Docket4:21-cv-03066
StatusUnknown

This text of A.M. Cohron & Son, Inc. v. City of Columbus, Nebraska (A.M. Cohron & Son, Inc. v. City of Columbus, Nebraska) is published on Counsel Stack Legal Research, covering District Court, D. Nebraska primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
A.M. Cohron & Son, Inc. v. City of Columbus, Nebraska, (D. Neb. 2021).

Opinion

IN THE UNITED STATES DISTRICT COURT FOR THE DISTRICT OF NEBRASKA

A.M. COHRON & SON, INC.,

Plaintiff, 4:21CV3066

vs. MEMORANDUM AND ORDER CITY OF COLUMBUS, NEBRASKA,

Defendant.

This matter is before the court on Defendant City of Columbus’ (“the City”) motion to dismiss pursuant to Fed. R. Civ. P. 12(b)(6). The City asserts the complaint fails to state a claim upon which relief can be granted because Plaintiff A.M. Cohron & Son, Inc. (“AMC”) failed to perform the conditions precedent required under Neb. Rev. Stat. § 16-726 and its complaint for breach of contract is time-barred. AMC requests oral argument because the parties disagree as to which statutes apply. For the reasons stated below, the motion to dismiss will be granted (Filing No. 10), and the motion for hearing (Filing No. 15) will be denied.

STATEMENT OF FACTS

Plaintiff AMC’s complaint alleges:

AMC, an Iowa Corporation and the City, a political subdivision of the State of Nebraska, entered into a construction contract for a project in Platte County, Nebraska in December 2016. (Filing No. 1 at CM/ECF pp. 1-2). The project involved construction of grade-separated crossings of the Union Pacific Railroad Corridor at two locations in the city; one was a pedestrian overpass, the other a vehicular viaduct. (Filing No. 1 at CM/ECF p. 5). During its work on the viaduct, AMC encountered issues with rebar clearance and was unable to achieve the clearance specified in the contract. AMC consulted with the Project Engineer and ultimately performed “extra work” to pour the bridge deck thicker than the contract specifications. (Filing No. 1 at CM/ECF pp. 5-6). AMC submitted a change order request to the Project Engineer on or about May 22, 2018. The Project Engineer denied AMC’s change order request on or about June 4, 2018, and the City did not pay additional compensation or extend the time allotted under the contract for completion of the project. (Filing No. 1 at CM/ECF p. 6). AMC alleges it is entitled to additional time and compensation for the “clearance issues” it encountered.

Under the contract, the project was to be completed within 587 calendar days, with terms allowing liquidated damages if AMC failed to complete the project within the specified time frame. (Filing No. 1 at CM/ECF p. 6). The City assessed $394,179.00 in liquidated damages against AMC because of the delayed completion of the project. AMC asserts the City’s damages are significantly less than the liquidated damages assessed. (Filing No. 1 at CM/ECF p. 8). AMC alleges that as a direct and proximate cause of the City’s breaches of the Contract, AMC has been damaged in an amount exceeding $456,762.45. (Filing No. 1 at CM/ECF p. 9).

The project was a federal-aid project. The Nebraska Department of Roads (“NDOR”) made payments to AMC on behalf of the City, and NDOR delegated to the City as Local Public Agency Owner under 23 CFR 635.105. (Filing No. 1 at CM/ECF p. 2) AMC filed this action on March 18, 2021, alleging the City breached its contract by: (a) failing to provide AMC with additional time and compensation as a result of the clearance issues it encountered on the Project; (b) failing to grant a time extension for delays caused by conditions beyond AMC’s control; and, (c) withholding sums owed to AMC as a result of an unenforceable liquidated damages provision. (Filing No. 1 at CM/ECF p. 9). STANDARD OF REVIEW

To survive a Rule 12(b)(6) motion to dismiss, a complaint must set forth a short and plain statement of the claim showing that the pleader is entitled to relief. Fed. R. Civ. P. 8(a)(2). This standard does not require detailed factual allegations, but it demands more than an unadorned accusation. Ashcroft v. Iqbal, 556 U.S. 662, 678 (2009). The standard requires a complaint to contain sufficient factual matter which, accepted as true, states a claim for relief that is plausible on its face. Ashcroft, 556 U.S. at 678; Corrado v. Life Inv'rs Ins. Co. of Am., 804 F.3d 915, 917 (8th Cir. 2015) (quoting Bell Atlantic Corp. v. Twombly, 550 U.S. 544, 570 (2007)).

Generally, a motion to dismiss may be granted when a claim is barred under a statute of limitations. Varner v. Peterson Farms, 371 F.3d 1011, 1016 (8th Cir.2004). If a defendant raises a statute of limitations defense and the face of the complaint indicates that the limitations period has expired, the plaintiff can survive a 12(b)(6) motion to dismiss only upon a showing that the statute of limitations was tolled. Schmidt v. Newland, 927 F.3d 1038, 1041 (8th Cir. 2019).

ANALYSIS

A. Applicable Nebraska Statute: Neb. Rev. Stat. § 45-1210 or Neb. Rev. Stat. § 16-726.

At the core of this motion, the parties disagree as to which statute provides the appropriate means for seeking recovery of contractual damages from the City. AMC argues that Neb. Rev. Stat. § 45-1210 (the Nebraska Construction Prompt Pay Act (“NCPPA”)) controls; the City argues Neb. Rev. Stat. § 16-726 controls. Ultimately, I find the conditions precedent of § 16-726 govern this action and AMC’s complaint must be dismissed. Statutes in existence at the time of executing a contract generally become part of the contract. Travelers Indem. Co. v. Int'l Nutrition, Inc., 734 N.W.2d 719, 727 (Neb. 2007); see In re Estate of Peterson, 381 N.W.2d 109 (Neb. 1986). Statutory interpretation is a question of law. Loves v. World Ins. Co., 758 N.W.2d 640, 643 (Neb. 2008). Clyde Bergemann Power Grp. Americas, Inc. v. City of Fremont, Nebraska, No. 8:15CV321, 2017 WL 11485731, at *3 (D. Neb. Apr. 24, 2017).

Prior to enacting the NCPPA, Neb. Rev. Stat. § 16-726 governed claims and accounts payable for cities of the first class. It required “as a condition precedent to maintaining an action against a city of the first class, that ‘the claimant . . . file such claim within ninety days of the accrual of the claim in the office of the city clerk.’” Centric Jones v. City of Kearney, Neb., 324 F.3d 646, 949 (8th Cir. 2003)(quoting Neb. Rev. Stat. § 16-726).

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Bell Atlantic Corp. v. Twombly
550 U.S. 544 (Supreme Court, 2007)
Ashcroft v. Iqbal
556 U.S. 662 (Supreme Court, 2009)
Irving F. Jensen Co. v. State
719 N.W.2d 716 (Nebraska Supreme Court, 2006)
Cavanaugh v. City of Omaha
580 N.W.2d 541 (Nebraska Supreme Court, 1998)
Travelers Indemnity Co. v. International Nutrition, Inc.
734 N.W.2d 719 (Nebraska Supreme Court, 2007)
Niemoller v. City of Papillion
752 N.W.2d 132 (Nebraska Supreme Court, 2008)
Francis v. v. City of Columbus
676 N.W.2d 346 (Nebraska Supreme Court, 2004)
Loves v. World Ins. Co.
758 N.W.2d 640 (Nebraska Supreme Court, 2008)
L.J. Vontz Construction Co. v. Department of Roads
440 N.W.2d 664 (Nebraska Supreme Court, 1989)
Snyder v. Case
611 N.W.2d 409 (Nebraska Supreme Court, 2000)
In Re Estate of Peterson
381 N.W.2d 109 (Nebraska Supreme Court, 1986)
Hoeft v. Five Points Bank
539 N.W.2d 637 (Nebraska Supreme Court, 1995)
Reinke Manufacturing Co. v. Hayes
590 N.W.2d 380 (Nebraska Supreme Court, 1999)
Corrado v. Life Investors Insurance Co. of America
804 F.3d 915 (Eighth Circuit, 2015)
Paula Schmidt v. Newland & Associates PLLC
927 F.3d 1038 (Eighth Circuit, 2019)

Cite This Page — Counsel Stack

Bluebook (online)
A.M. Cohron & Son, Inc. v. City of Columbus, Nebraska, Counsel Stack Legal Research, https://law.counselstack.com/opinion/am-cohron-son-inc-v-city-of-columbus-nebraska-ned-2021.