Centric Jones Company, Appellant-Cross-Appellee v. City of Kearney, Nebraska, Appellee-Cross-Appellant

324 F.3d 646, 2003 U.S. App. LEXIS 5844, 2003 WL 1561710
CourtCourt of Appeals for the Eighth Circuit
DecidedMarch 27, 2003
Docket02-1964, 02-1965
StatusPublished
Cited by8 cases

This text of 324 F.3d 646 (Centric Jones Company, Appellant-Cross-Appellee v. City of Kearney, Nebraska, Appellee-Cross-Appellant) is published on Counsel Stack Legal Research, covering Court of Appeals for the Eighth Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Centric Jones Company, Appellant-Cross-Appellee v. City of Kearney, Nebraska, Appellee-Cross-Appellant, 324 F.3d 646, 2003 U.S. App. LEXIS 5844, 2003 WL 1561710 (8th Cir. 2003).

Opinion

MAGILL, Circuit Judge.

Centric Jones Co. (“Centric”) appeals from a final order entered in the district court 1 granting summary judgment for the City of Kearney, Nebraska, (“City”) 2 and the district court’s subsequent denial of Centric’s Federal Rule of Civil Procedure 69(e) motion to alter or amend the judgment. For the reasons discussed below, we affirm.

I.

The City of Kearney is a city of the “first class,” see Neb.Rev.Stat. § 16.101 (2002), which means, inter alia, the City can sue and be sued and enter into contracts, see id. § 16.201. Centric is a Colorado limited partnership engaged in the business of performing construction contracts as a prime contractor.

In May 1996, Centric entered into a contract with the City for completion of the construction portion of the Kearney Wastewater Treatment Plant for $12,960,000. CH2M Hill (“CH2M”), an engineering firm, served as the City’s project engineer. The contract defined CH2M’s duties: among other things, CH2M was to act as the City’s representative during the construction period; receive payment applications from Centric and make recommendations to the city council regarding progress payments 3 ; and act as an impartial initial interpreter of the contract requirements and judge of the acceptability of the work, if and when disputes arose. See J.A. at 664-65. If CH2M was unable to resolve an issue to the parties’ satisfaction, either party could invoke the dispute resolution procedures described in the contract. If those dispute resolution procedures were unsuccessful, the contract provided that a party could institute suit in a court of competent jurisdiction.

During the course of construction, Centric submitted thirty payment applications *648 to CH2M. CH2M reviewed the applications and forwarded them to Kirk Stocker, the City’s Utilities Director, along with either a certification that the application should be paid in full or a recommendation to pay a different amount. Stocker then forwarded the applications to the city clerk for filing, and the applications were placed on the city council’s agenda. The city council’s resolutions regarding the payment applications routinely provided, “the City’s engineer, CH2M Hill, has filed with the City Clerk a Payment Application .... ” J.A. at 1683-1716. The City adopted CH2M’s certifications, resulting in full payment of twelve payment applications, refusal to pay in whole or in part twelve applications, and six instances of payment in excess of that actually requested on the application. 4 As a result of the refusals to pay Centric the full amount requested, on March 2, 1999, Centric requested that the parties mediate the dispute pursuant to the contract.

In May 1999, the parties participated in an unsuccessful mediation. On or about May 10, 1999, a written notice of termination of mediation was sent to the parties. By September 1999, the project was entirely completed. On September 24, 1999, Centric sent a letter to Stocker demanding payment of $1,266,486.53 within thirty days. In a letter dated October 22, 1999, the City rejected Centric’s demand, proposing instead a final payment of $670,256.00.

On March 24, 2000, Centric filed suit 5 against the City asserting causes of action for breach of contract and unjust enrichment. Centric sought damages in excess of $2,000,000. On December 26, 2001, the district court granted the City’s motion for summary judgment based on the affirmative defense that Centric had failed to comply with the claim statute governing claims against the City, Neb.Rev.Stat. § 16-726, and dismissed the whole case with prejudice. Subsequently, the district court denied Centric’s motion to alter or amend the judgment. This appeal and cross-appeal follow.

II.

Centric argues that this court should reverse because (1) Centric complied, actually or at least substantially, with Nebraska Revised Statute section 16-726, and so, Centric’s claim is not time-barred; (2) the City should be equitably estopped from claiming that section 16-726 applies to the case at bar; (3) there were material factual disputes between the parties, making summary judgment inappropriate; and (4) the district court abused its discretion by denying Centric’s motion to amend or alter the judgment.

This court reviews a district court’s grant of summary judgment de novo. E.g., Norwalk Ready Mixed Concrete, Inc. v. Travelers Ins. Cos., 246 F.3d 1132, 1135 (8th Cir.2001) (citation omitted). Summary judgment is appropriate if, viewing the facts in the light most favorable to the non-moving party, there are no genuine issues of material fact and the moving party is entitled to judgment as a matter of law. Id. (citation omitted). Additionally, this court reviews a district court’s *649 interpretation of state law de novo. E.g., Salve Regina Coll. v. Russell, 499 U.S. 225, 239, 111 S.Ct. 1217, 113 L.Ed.2d 190 (1991) (“The obligation of responsible appellate review and the principles of a cooperative judicial federalism underlying Eñe require that courts of appeals review the state-law determinations of district courts de novo.”); ANR Western Coal Dev. Co. v. Basin Elec. Power Co-op., 276 F.3d 957, 964 n. 10 (8th Cir.2002) (citation omitted). This court reviews a district court’s interpretation of a contract de novo. E.g., Norwalk, 246 F.3d at 1135-36 (citation omitted); Rapid Leasing Inc. v. Nat’l Am. Ins. Co., 263 F.3d 820, 825 (8th Cir.2001) (citation omitted). Finally, this court reviews a district court’s denial of a Rule 59 motion for abuse of discretion. E.g., Twin City Constr. Co. of Fargo v. Turtle Mountain Band of Chippewa Indians, 911 F.2d 137, 139 (8th Cir.1990) (citations omitted).

First, Centric argues that it, actually or at least substantially, complied with Nebraska Revised Statute section 16-726. We disagree. Section 16-726 requires, as a condition precedent to maintaining an action against a city of the first class, that “the claimant ... file such claim within ninety days of the accrual of the claim in the office of the city clerk.” Neb. Rev.Stat. § 16-726. Section 16-726 functions as a statute of limitations, resulting in the time bar of suits not filed within the requisite ninety days. Sinn v. City of Seward,

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
324 F.3d 646, 2003 U.S. App. LEXIS 5844, 2003 WL 1561710, Counsel Stack Legal Research, https://law.counselstack.com/opinion/centric-jones-company-appellant-cross-appellee-v-city-of-kearney-ca8-2003.