Wolfson v. Regency Homes

CourtNebraska Court of Appeals
DecidedAugust 12, 2025
DocketA-24-778
StatusUnpublished

This text of Wolfson v. Regency Homes (Wolfson v. Regency Homes) is published on Counsel Stack Legal Research, covering Nebraska Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Wolfson v. Regency Homes, (Neb. Ct. App. 2025).

Opinion

IN THE NEBRASKA COURT OF APPEALS

MEMORANDUM OPINION AND JUDGMENT ON APPEAL (Memorandum Web Opinion)

WOLFSON V. REGENCY HOMES

NOTICE: THIS OPINION IS NOT DESIGNATED FOR PERMANENT PUBLICATION AND MAY NOT BE CITED EXCEPT AS PROVIDED BY NEB. CT. R. APP. P. § 2-102(E).

IRA WOLFSON, APPELLANT, V.

REGENCY HOMES, A NEBRASKA CORPORATION, APPELLEE.

Filed August 12, 2025. No. A-24-778.

Appeal from the District Court for Douglas County: SHELLY R. STRATMAN, Judge. Affirmed. Ira Wolfson, pro se. Thomas J. Culhane and Raymond E. Walden, of Erickson | Sederstrom, P.C., for appellee.

PIRTLE, BISHOP, and FREEMAN, Judges. FREEMAN, Judge. INTRODUCTION Ira Wolfson, representing himself, appeals from an order of the district court for Douglas County granting summary judgment in favor of Regency Homes, a Nebraska corporation. Wolfson generally alleges that the district court erred in determining that his suit was barred by the statute of limitations. For the reasons that follow, we affirm. BACKGROUND Regency Homes completed construction of a model home located in the Millard area of Omaha, Nebraska, in late 2013. Wolfson and his wife purchased the home from Regency Homes via a uniform purchase agreement in March 2016. During the following 5 years, Wolfson discovered some defects with the home’s landscaping that are relevant to this appeal.

-1- In the spring of 2018, Wolfson noticed that the concrete on his front patio was sinking. He hired a company to “mud jack” the concrete, which is a repair technique used to raise and level sunken concrete slabs. The company completed the work in May 2018. In the spring of 2021, Wolfson hired three landscaping companies to provide him with estimates for landscaping work he was considering for his property. At least one of the three companies inspected Wolfson’s property and informed him of defects with the boulder wall supporting the front patio and the backyard retaining wall. On May 20, 2021, Wolfson sent an email to a Regency Homes representative describing the defects and their causes. According to Wolfson’s email, the landscaping company informed him that the boulder wall was sliding out of position due to ineffective placement of the boulders at the time of construction and insufficient fill dirt, thus causing erosion. The company also advised him that the backyard retaining wall was leaning away from the house and was stressed by erosion and pressure from the weight behind it. This defect was attributed to an inappropriate choice of backfill and an inadequate design for drainage. Wolfson specified in his email that he was “writing to inform [Regency Homes] of these issues and to seek whatever path can address them.” Sometime thereafter, Wolfson engaged Terracon Consultants, Inc., to provide a comprehensive report on the landscaping defects. On August 31, 2021, Terracon issued its report to Wolfson. The report attributes the sinking of the front patio to insufficient compaction of the home’s basement wall backfill. The report attributes the distress of the backyard retaining wall to use of backfill materials which do not meet industry standards or additional water pressure behind the wall due to lack of free draining material. On December 3, 2021, Wolfson sent an email to Regency Homes’ attorney. Based on the email’s contents, we can infer that Wolfson had previously requested Regency Homes to cover the repair costs for the defects. In his email, Wolfson stated that his previous efforts to engage in informal discussions “were met with [a] blanket refusal to discuss.” Relevant to this appeal, Wolfson also wrote: While I am aware of the arguments you make as to the statute of limitations, it is clear from the facts stated above that our discovery of these defects was only triggered in the late Spring of 2021 and the defects now discovered were not reasonably noted or known before that time frame.

Wolfson reiterated his willingness to informally resolve the dispute, but indicated that if he was rebuffed again, he would seek arbitration. At this time, Wolfson believed that the uniform purchasing agreement required “binding arbitration” to settle all disputes. On August 15, 2023, Wolfson, representing himself, filed a petition against Regency Homes in the district court seeking damages for breach of implied warranty of “workman like performance” in connection with the construction of his home. In his petition, Wolfson asserts that in October 2022, he filed an “Application to Compel Arbitration.” Our record has no further information on this separate case except proffered statements from Wolfson that the court ultimately declined to order arbitration. On May 17, 2024, Regency Homes filed a motion for summary judgment accompanied by a brief, an evidence index, and an annotated statement of undisputed facts. The corporation asserted that Wolfson’s claims were barred by the applicable statute of limitations found in Neb.

-2- Rev. Stat. § 25-223 (Cum. Supp. 2022). In addition to the communications discussed above, Regency Homes also submitted as evidence Wolfson’s April 2024 deposition wherein Wolfson admitted that by the spring of 2021, he “knew of the problem, [but] not the cause” of the landscaping defects. In response to the motion, Wolfson filed a “Memorandum and Motion for Denial of Summary Judgment Pleading.” He did not file an evidence index or an annotated statement of disputed facts as required by Neb. Ct. R. § 6-1526(B) (rev. 2022). A hearing on the motion for summary judgment was held on August 22, 2024. The district court received evidence from both parties, then arguments. Regency Homes argued that under § 25-223(1), Wolfson’s suit had to be filed within 4 years of the conclusion of the real property work unless the landscaping defects were not discovered within that period. If the latter were true, Regency Homes argued that Wolfson had 2 years from the date he discovered the defects to pursue an action against the corporation. Regency Homes asserted that by May 2021, Wolfson had discovered all the defects listed in his petition and thus had until May 2023 to file a suit. Because Wolfson filed in August 2023, Regency Homes concluded that he filed outside the 2-year statute of limitations. Wolfson disagreed and argued that he had not fully discovered the defects until he received the Terracon report on August 31, 2021. Accordingly, he concluded that his petition was timely filed within the 2-year statute of limitations. Wolfson also argued that the Nebraska Legislature has encouraged parties to pursue alternative dispute resolutions and that statutes such as Neb. Rev. Stat. § 25-2917 (Cum. Supp. 2024) provide for tolling the limitations period while such efforts are underway. However, Wolfson admitted that § 25-2917 “is not on point” in this case. On September 20, 2024, the district court issued an order granting summary judgment in favor of Regency Homes. The court agreed with Regency Homes that Wolfson had discovered all the facts constituting the basis of his cause of action by May 2021. The court specifically cited Wolfson’s description of the landscaping defects in his May 2021 email to Regency Homes. Thus, the court concluded that Wolfson’s suit was barred by the 2-year statute of limitations. The court acknowledged that while Wolfson may not have known the exact nature or cause of the defects at that time, § 25-223 only required that he had knowledge that the problems existed. The court also noted its appreciation of Wolfson’s efforts to resolve this dispute outside of the court, but it found that those efforts did not toll the statute of limitations. Thus, the court dismissed Wolfson’s complaint with prejudice. Wolfson appeals.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Andres v. McNeil Co., Inc.
707 N.W.2d 777 (Nebraska Supreme Court, 2005)
Kearney Clinic Building Corp. v. Weaver
319 N.W.2d 95 (Nebraska Supreme Court, 1982)
Walz v. Harvey
28 Neb. Ct. App. 7 (Nebraska Court of Appeals, 2020)
Susman v. Kearney Towing & Repair Ctr.
310 Neb. 910 (Nebraska Supreme Court, 2022)
Zook v. Zook
978 N.W.2d 156 (Nebraska Supreme Court, 2022)
Syring v. Archdiocese of Omaha
317 Neb. 195 (Nebraska Supreme Court, 2024)
State v. Kalita
317 Neb. 906 (Nebraska Supreme Court, 2024)
Galloway v. Husker Auto Group
318 Neb. 178 (Nebraska Supreme Court, 2024)

Cite This Page — Counsel Stack

Bluebook (online)
Wolfson v. Regency Homes, Counsel Stack Legal Research, https://law.counselstack.com/opinion/wolfson-v-regency-homes-nebctapp-2025.