Georgetowne Ltd. Partnership v. Geotechnical Services, Inc.

430 N.W.2d 34, 230 Neb. 22, 1988 Neb. LEXIS 353
CourtNebraska Supreme Court
DecidedSeptember 30, 1988
Docket86-870
StatusPublished
Cited by83 cases

This text of 430 N.W.2d 34 (Georgetowne Ltd. Partnership v. Geotechnical Services, Inc.) is published on Counsel Stack Legal Research, covering Nebraska Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Georgetowne Ltd. Partnership v. Geotechnical Services, Inc., 430 N.W.2d 34, 230 Neb. 22, 1988 Neb. LEXIS 353 (Neb. 1988).

Opinion

Warren, D.J.

This is an appeal by Georgetowne Ltd. Partnership from the dismissal of its negligence action against Geotechnical Services, Inc. (Geotech), after a separate trial to the court on the issue of the statute of limitations defense.

On October 4, 1978, after performing soil tests and analysis for Georgetowne, Geotech submitted to plaintiff a written consultation report évaluating soils and making foundation recommendations for the proposed construction of commercial buildings at a site near 140th Street and West Center Road in Omaha. Separate from its services for plaintiff, Geotech later performed compaction tests at the same site for a building contractor. The shopping center building was completed by April 1979.

Subsequently, two problems developed which plaintiff alleges were caused by the negligence of Geotech in failing to properly investigate subsoils and evaluate and report thereon, as a result of which the building settled. In February 1982, a Georgetowne representative notified Geotech that a crack had appeared in the floor of a restaurant located in the building. Geotech investigated, after which, on March 26, 1982, it advised Georgetowne that the crack was not caused by settling and could be remedied simply by filling it with grout. In March 1983, the crack reappeared, there were vertical cracks found on the building face through the brick, the roof would not drain water due to a change in the roof Une, and a plate glass window in the restaurant shattered for no apparent reason. Secondly, a *24 floral business tenant complained of the smell of gas around its premises. The fire marshal and Metropolitan Utilities District employees investigated and attributed the methane gas (swamp gas) to decaying matter in the soils. Geotech was again notified of these problems, and it investigated. On April 8, 1983, the plaintiff’s architect notified Georgetowne that he had detected a 2-inch settlement of floor lines and doorsills, and he advised that the crack in the restaurant floor was possibly caused by settlement which could be occurring further down in the lower soils. The architect requested that Geotech return to the site and investigate settlement of the building as a possible cause. On April 18, 1983, Geotech gave plaintiff an estimate of costs for further testing. Georgetowne was also investigating other possible causes.

After an April 25, 1983, meeting with its architect and a representative of another soil engineering firm, Woodward-Clyde, during which Geotech’s 1978 report was discussed and criticized, the Georgetowne representative called an attorney as directed by her superior to discuss representation of Georgetowne regarding its legal rights against Geotech. On April 27, 1983, this same employee, Nancy Pratt, delivered a letter to Geotech advising it that Georgetowne had relied upon Geotech’s soil report of October 4,1978, requesting Geotech to return to the site and make all necessary tests at its own expense to determine the cause of the settling, and concluding as follows:

The cracked floor in Godfathers and improper roof drainage are two of the problems that are apparent at this time. To the extent these damages and other undisclosed damages have occurred or may occur as a result of incomplete or inaccurate soil investigations, we would as [sic] Geotechnical Services to make the necessary repairs and take other preventative actions made necessary by the situation (subject to our prior approval of construction methods.).

Woodward-Clyde then performed test borings, and its findings were presented to Georgetowne on June 14, 1983, by a report dated June 8,1983. Plaintiff filed suit June 7,1984.

After an evidentiary hearing, the district court dismissed *25 plaintiff’s second amended petition for the reason that the action was barred by the statute of limitations governing professional services set forth in Neb. Rev. Stat. § 25-222 (Reissue 1985). The trial court specifically found that (1) defendant Geotech was a civil engineering firm which provided professional services within the meaning of § 25-222; (2) Geotech performed its services for plaintiff on October 4,1978; (3) Georgetowne’s cause of action was not discovered and could not have been reasonably discovered within 2 years from October 4, 1978, and, therefore, plaintiff had 1 year from the date of discovery or the discovery of facts which would reasonably lead to such discovery, whichever was earlier, to commence its action; (4) by April 27, 1983, plaintiff had discovered sufficient facts that the statute of limitations had commenced to run; (5) plaintiff’s cause of action was barred by the limitation of § 25-222 on April 27, 1984; and (6) the statute of limitations had run by the time the suit was filed on June 7, 1984.

Plaintiff assigns as error that the court erred in (1) determining that the commencement date for the running of the statute of limitations was April 27, 1983, rather than June 8, 1983, and (2) determining that the appropriate statute of limitations was § 25-222, instead of Neb. Rev. Stat. § 25-223 (Reissue 1985). We affirm.

There is no question that Geotech had fully performed its soil testing services as of the date of its report on October 4, 1978. Similarly, no one contends that Georgetowne could have reasonably discovered its cause of action within 2 years thereafter. Therefore, the question is, When did Georgetowne have sufficient facts to discover its cause of action? Plaintiff contends that the statute of limitations did not begin to run until June 8, 1983, when the Woodward-Clyde report was completed.

A defendant alleging the statute of limitations as an affirmative defense has the burden to prove such defense. League v. Vanice, 221 Neb. 34, 374 N.W.2d 849 (1985). The point at which a statute of limitations commences to run must be determined from the facts of each case. Suzuki v. Holthaus, 221 Neb. 72, 375 N.W.2d 126 (1985). In our review of the *26 district court’s judgment on the issue of the statute of limitations, the finding and decision of the district court, unless clearly wrong, will not be set aside. League v. Vanice, supra.

Discovery, as applied to statutes of limitations, refers to the fact that one knows of the existence of an injury or damage and not that he or she has a legal right to seek redress in court. A cause of action accrues, and the statute of limitations begins to run, when there has been discovery of facts constituting the basis of the cause of action or the existence of facts sufficient to put a person of ordinary intelligence and prudence on inquiry which, if pursued, would lead to the discovery. See Grand Island School Dist. #2 v. Celotex Corp., 203 Neb. 559, 279 N.W.2d 603 (1979).

Here, Georgetowne was aware of damage to its building as early as February 1982.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Wehrer v. Dynamic Life Therapy & Wellness
302 Neb. 1025 (Nebraska Supreme Court, 2019)
Wehrer v. Dynamic Life Therapy & Wellness, P.C.
302 Neb. 1025 (Nebraska Supreme Court, 2019)
E3 Biofuels, LLC v. Biothane, LLC
781 F.3d 972 (Eighth Circuit, 2015)
Adams v. Manchester Park
Nebraska Court of Appeals, 2014
Mahnke v. STATE, DEPT. OF HEALTH
751 N.W.2d 635 (Nebraska Supreme Court, 2008)
Opinion No. (2007)
Nebraska Attorney General Reports, 2007
Anonymous v. Vasconcellos
727 N.W.2d 708 (Nebraska Court of Appeals, 2007)
Parks v. MERRILL, LYNCH, PIERCE, FENNER
684 N.W.2d 543 (Nebraska Supreme Court, 2004)
Parks v. Merrill, Lynch, Pierce, Fenner & Smith, Inc.
684 N.W.2d 543 (Nebraska Supreme Court, 2004)
Cooper v. Paap
634 N.W.2d 266 (Nebraska Court of Appeals, 2001)
ALEGENT HEALTH BERGAN MERCY MED. v. Haworth
615 N.W.2d 460 (Nebraska Supreme Court, 2000)
Alegent Health Bergan Mercy Medical Center v. Hawort
615 N.W.2d 460 (Nebraska Supreme Court, 2000)
Opinion No. (1998)
Nebraska Attorney General Reports, 1998
Jorgensen v. State National Bank & Trust Co.
583 N.W.2d 331 (Nebraska Supreme Court, 1998)
Opinion No. (1997)
Nebraska Attorney General Reports, 1997
Brown v. Wilson
567 N.W.2d 124 (Nebraska Supreme Court, 1997)
State Ex Rel. City of Elkhorn v. Haney
566 N.W.2d 771 (Nebraska Supreme Court, 1997)
Goolsby v. Anderson
549 N.W.2d 153 (Nebraska Supreme Court, 1996)

Cite This Page — Counsel Stack

Bluebook (online)
430 N.W.2d 34, 230 Neb. 22, 1988 Neb. LEXIS 353, Counsel Stack Legal Research, https://law.counselstack.com/opinion/georgetowne-ltd-partnership-v-geotechnical-services-inc-neb-1988.