O. W. Grun Roofing & Construction Co. v. Cope

529 S.W.2d 258, 1975 Tex. App. LEXIS 3128
CourtCourt of Appeals of Texas
DecidedOctober 15, 1975
Docket15401
StatusPublished
Cited by9 cases

This text of 529 S.W.2d 258 (O. W. Grun Roofing & Construction Co. v. Cope) is published on Counsel Stack Legal Research, covering Court of Appeals of Texas primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
O. W. Grun Roofing & Construction Co. v. Cope, 529 S.W.2d 258, 1975 Tex. App. LEXIS 3128 (Tex. Ct. App. 1975).

Opinion

CADENA, Justice.

Plaintiff, Mrs. Fred M. Cope, sued defendant, O. W. Grun Roofing & Construction Co., to set aside a mechanic’s lien filed by defendant and for damages in the sum of $1,500.00 suffered by plaintiff as a result of the alleged failure of defendant to perform a contract calling for the installation of a new roof on plaintiff’s home. Defendant, in addition to a general denial, filed a cross-claim for $648.00, the amount which plaintiff agreed to pay defendant for installing the roof, and for foreclosure of the mechanic’s lien on plaintiff’s home.

Following trial to a jury, the court below entered judgment awarding plaintiff $122.60 as damages for defendant’s failure to perform the contract; setting aside the mechanic’s lien; and denying defendant recovery on its cross-claim. It is from this judgment that defendant appeals.

The jury found (1) defendant failed to perform his contract in a good and workmanlike manner; (2) defendant did not substantially perform the contract; (3) plaintiff received no benefits from the labor performed and the materials furnished by defendant; the reasonable cost of performing the contract in a good and workmanlike manner would be $777.60. Although the verdict shows the cost of proper performance to be $777.60, the judgment describes this finding as being in the amount of $770.60, and the award of $122.60 to plaintiff is based on the difference between $770.60 and the contract price of $648.00.

By its first point, defendant questions the factual and legal sufficiency of the evidence to support the jury’s findings. The argument under this point (defendant’s brief contains no statement following each point), is limited to the contention that all of the elements of “substantial performance” were established.

We find no assignments of error in the motion for new trial specifically calling the trial court’s attention to the complaint that the evidence is insufficient to support the finding that defendant did not perform the contract in a good and workmanlike manner (issue no. 1), or that the finding that defendant did not substantially perform the contract (issue no. 2) was contrary to the overwhelming weight and preponderance of the evidence. The motion for new trial does assert that the trial court erred in overruling defendant’s motion for judgment n. o. v. because “a. The jury disclosed by their answers to the special issues that they were in sympathy with the Plaintiff and that their answers to the questions proposed by the Court were not founded on any evidence or upon wholly insufficient evidence,” and “b. Defendant should have been granted Judgment as a matter of law because the evidence was legally sufficient for such a verdict.” Assuming that this portion of the motion for new trial raises the question of factual sufficiency of the evidence, it amounts to no more than a complaint that the verdict is contrary to the evidence. The assignment is multifarious, complaining of the sufficiency of the evidence to support the answers to each of five issues and will not support a factual insufficiency of the evidence point on appeal. Rule 322, Tex.R.Civ.P. (1967).

The only questions, therefore, which we can consider under defendant’s first point are that there is no evidence to support the finding that defendant did not perform in a good and workmanlike manner and that the evidence establishes as a matter of law that defendant substantially performed the contract. In considering these “no evidence” points, we look only to the evidence supporting the verdict. In re King’s Estate, 150 Tex. 662, 244 S.W.2d 660 (1952).

The written contract required defendant to install a new roof on plaintiff’s home for $648.00. The contract describes the color of *261 the shingles to be used as “russet glow,” which defendant defined as a “brown varied color.” Defendant acknowledges that it was his obligation to install a roof of uniform color.

After defendant had installed the new roof, plaintiff noticed that it had streaks which she described as yellow, due to a difference in color or shade of some of the shingles. Defendant agreed to remedy the situation and he removed the nonconforming shingles. However, the replacement shingles do not match the remainder, and photographs introduced in evidence clearly show that the roof is not of a uniform color. Plaintiff testified that her roof has the appearance of having been patched, rather than having been completely replaced. According to plaintiff’s testimony, the yellow streaks appeared on the northern, eastern and southern sides of the roof, and defendant only replaced the non-matching shingles on the northern and eastern sides, leaving the southern side with the yellow streaks still apparent. The result is that only the western portion of the roof is of uniform color.

When defendant originally installed the complete new roof, it used 24 “squares” of shingles. In an effort to achieve a roof of uniform color, five squares were ripped off and replaced. There is no testimony as to the number of squares which would have to be replaced on the southern, or rear, side of the house in order to eliminate the original yellow streaks. Although there is expert testimony to the effect that the disparity in color would not be noticeable after the shingles have been on the roof for about a year, there is testimony to the effect that, although some nine or ten months have elapsed since defendant attempted to achieve a uniform coloration, the roof is still “streaky” on three sides. One of defendant’s experts testified that if the shingles are properly applied the result will be a “blended” roof rather than a streaked roof.

In view of the fact that the disparity in color has not disappeared in nine or ten months, and in view of the fact that there is testimony to the effect that it would be impossible to secure matching shingles to replace the nonconforming ones, it can reasonably be inferred that a roof or uniform coloration can be achieved only by installing a completely new roof.

The evidence is undisputed that the roof is a substantial roof and will give plaintiff protection against the elements.

The principle which allows recovery for part performance in cases involving dependent promises may be expressed by saying that a material breach or a breach which goes to the root of the matter or essence of the contract defeats the promis- or’s claim despite his part performance, or it may be expressed by saying that a prom-isor who has substantially performed is entitled to recover, although he has failed in some particular to comply with his agreement. The latter mode of expressing the rule is generally referred to as the doctrine of substantial performance and is especially common in cases involving building contracts, although its application is not restricted to such contracts.

It is difficult to formulate definitive rule for determining whether the contractor’s performance, less than complete, amounts to “substantial performance,” since the question is one of fact and of degree, and the answer depends on the particular facts of each case. But, although the decisions furnish no rule of thumb, they are helpful in suggesting guidelines. One of the most obvious factors to be considered is the extent of the nonperformance. The deficiency will not be tolerated if it is so pervasive as to frustrate the purpose of the contract in any real or substantial sense.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Iannetta v. JDL Concrete
2025 Ohio 5472 (Ohio Court of Appeals, 2025)
Davis v. J & J Concrete
2019 Ohio 1407 (Ohio Court of Appeals, 2019)
William C. Cocke v. E. Paul Schexnailder
Court of Appeals of Texas, 2006
Lange Industries, Inc. v. Hallam Grain Co.
507 N.W.2d 465 (Nebraska Supreme Court, 1993)
John T. Measday v. Kwik-Kopy Corporation
713 F.2d 118 (Fifth Circuit, 1983)

Cite This Page — Counsel Stack

Bluebook (online)
529 S.W.2d 258, 1975 Tex. App. LEXIS 3128, Counsel Stack Legal Research, https://law.counselstack.com/opinion/o-w-grun-roofing-construction-co-v-cope-texapp-1975.