Davis v. J & J Concrete

2019 Ohio 1407
CourtOhio Court of Appeals
DecidedApril 15, 2019
Docket2018-T-0074
StatusPublished
Cited by5 cases

This text of 2019 Ohio 1407 (Davis v. J & J Concrete) is published on Counsel Stack Legal Research, covering Ohio Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Davis v. J & J Concrete, 2019 Ohio 1407 (Ohio Ct. App. 2019).

Opinion

[Cite as Davis v. J & J Concrete, 2019-Ohio-1407.]

IN THE COURT OF APPEALS

ELEVENTH APPELLATE DISTRICT

TRUMBULL COUNTY, OHIO

WILLIAM ROGER DAVIS, : OPINION

Plaintiff-Appellant, : CASE NO. 2018-T-0074 - vs - :

J&J CONCRETE, et al., :

Defendants-Appellees. :

Civil Appeal from the Trumbull County Court of Common Pleas, Case No. 2015 CV 01992.

Judgment: Affirmed.

David L. Engler, Engler Law Firm, 181 Elm Road, N.E., Warren, OH 44483 (For Plaintiff- Appellant).

Michael D. Rossi, Guarnieri & Secrest, PLL, 151 East Market Street, P.O. Box 4270, Warren, OH 44482 (For Defendants-Appellees).

MARY JANE TRAPP, J.

{¶1} Appellant, William Roger Davis, appeals the judgment of the Trumbull

County Court of Common Pleas adopting the magistrate’s $100 award of nominal

damages in Mr. Davis’ breach of contract claim against appellee, J&J Concrete (“J&J”).

For the following reasons, we affirm.

Substantive and Procedural History {¶2} Mr. Davis and J&J entered into a contract towards the end of 2013, whereby

J&J agreed to pour a concrete mono slab foundation (a mono foundation is a combined

footer and floor that is one unit and moves with the ground formed with a single pour of

concrete) for Mr. Davis’ “Quonset hut.” A Quonset hut is a prefabricated storage structure

made of steel that has a semicircular “bow” shape with all its weight on two sides. The

parties agreed on a price of $9,500, which was increased to $10,000 when the foundation

was laid.

{¶3} Mr. Davis purchased the Quonset hut kit and accompanying blueprints from

a friend, and he used those blueprints and their specifications to obtain estimates from

various contractors, including J&J. Mr. Davis later obtained a second set of blueprints

directly from the manufacturer, American Steel, when he changed the design of the

Quonset hut after the footer was poured in July of 2014.

{¶4} The original blueprints were not before the trial court, but the second set

required the mono foundation to be at least 16 inches in depth. The parties stipulated

that the 16-inch depth was a specification, together with a requirement that No. 6 rebar

be incorporated into the foundation and that the foundation’s strength was to be no less

than 2,500 psi (“per square inch” of concrete measures the “crush strength” of concrete).

{¶5} Mr. Davis was running electricity to the Quonset hut a few weeks after the

structure was assembled when he noticed the mono foundation was not 16 inches all

around.

{¶6} Mr. Davis filed a complaint against J&J in the Trumbull Court of Common

Pleas alleging breach of contract, breach of warranty, fraud, and violation of the Ohio

Consumer Sales Practice Act (“CSPA”) for J&J’s failure to lay down the foundation with

2 a 16-inch depth and omission of No. 6 rebar that was to be embedded in the foundation

for beam strength.

{¶7} The case proceeded to a hearing before the magistrate where both parties

presented witnesses, and a site view was conducted with parties actually digging five

random holes for measurement and inspection by the magistrate. The inspection

revealed the concrete depth varied from 12 to 16 inches.

{¶8} Mr. Davis submitted two expert witnesses as to the cost of repair. The first,

William Conger, owner of W.D.C. Concrete Inc., was also one of the contractors who

initially submitted an estimate to lay down the foundation. Mr. Conger explained that the

depth of a footer is important to protect structures from frost, especially in northeast Ohio.

When structures are subjected to wet and then cold conditions, footers can buckle, twist,

and at their worst, destroy a building. Footers are also meant to be completely smooth

on the outside so that “the ground can move without moving the structure.” Mr. Conger

opined that J&J failed to perform in a workmanlike manner because the foundation

bubbled, was not the correct depth, and contained only 3/8 rebar, not the stronger No. 6

rebar called for in the plans.

{¶9} John L. Miller, co-owner of J&J along with his wife, Cindy, disagreed with

Mr. Conger’s assessment. Mr. Miller testified that any foundation that was not 40 or more

inches, the minimum required to be below the frost level of Trumbull County, was

considered a “floating foundation” or a “mono foundation.” In his opinion, “the top just

has to be square. What it looks like below ground level does not matter.” Mr. Miller also

contested Mr. Davis’ and Mr. Conger’s testimony, contending that he installed No. 6 rebar.

He did not have purchase tickets for the rebar (on which Mr. Conger based his testimony)

3 because Mr. Davis requested a materials list only after the fact, and he “didn’t purchase

[the No.6 rebar] specifically for that job.” Mr. Miller supplied the No. 6 rebar from materials

he had in his own inventory.

{¶10} As to the cost of repair, Mr. Conger advocated dissembling the entire

building, removing the defective foundation, re-pouring it, and lastly, reassembling the

building. In his own words, “You cannot put a footer in after the fact.” Digging underneath

and putting a new slab in would undermine the strength of the building. This undertaking

would cost approximately $50,000.

{¶11} The second expert to testify was the carpenter who assembled the Quonset

hut, James R. Wakefield. Mr. Wakefield provided Mr. Davis with an estimate of $49,118

to completely dissemble the structure, remove and then pour a new foundation, and

finally, reassemble the building.

{¶12} Both Mr. Davis and Mr. Miller agreed the foundation met the psi

requirements of the contract since it had a psi of 4,500.

{¶13} Both parties also agreed the foundation and, correspondingly, the Quonset

hut, were undamaged and that the foundation served its purpose without fault since it was

built over three years ago.

{¶14} The magistrate issued her findings of fact and conclusions of law. In

addition to her findings regarding the parties’ agreement on three particular specifications

for the foundation and her observations at the site view as to the depth variances, she

also found that the lower portions of the concrete had a “rough, ‘bubbled,’ appearance.”

The magistrate found Mr. Miller credibly testified that he did incorporate the No. 6 rebar

and the foundation’s strength was 4,500 psi. Further, the Quonset hut served its intended

4 purpose, and there was no evidence of foundation cracks or other compromise of the

building’s structural integrity. The magistrate also found Mr. Conger qualified as an expert

in concrete, but not engineering, and was “not a competent expert to render an opinion

as to the structural effects of an uneven footer of a Quonset hut.”

{¶15} In her findings of law, the magistrate determined J&J did not materially

breach the parties’ contract because it had substantially performed its obligations. While

the cost of repairs is ordinarily the proper measure of damages for construction defects,

the magistrate found this case does not support a damage award equaling the cost of

replacement at the estimate given of $50,000. There was no credible evidence the

contract failed its essential purpose and no evidence quantifying any harm from the faulty

footers. Therefore, the magistrate concluded Mr. Davis was entitled to nominal damages

only and awarded him $100 on the breach of contract claim.

{¶16} After overruling Mr.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Mapleview Operating Co. v. Valletto
2025 Ohio 1898 (Ohio Court of Appeals, 2025)
Crockett Homes, Inc. v. Tracy
2024 Ohio 1464 (Ohio Court of Appeals, 2024)
Perkins v. Petrilli
2022 Ohio 2029 (Ohio Court of Appeals, 2022)
O'Brien v. Shorey
2021 Ohio 2519 (Ohio Court of Appeals, 2021)
In re H.N.M.
2019 Ohio 1601 (Ohio Court of Appeals, 2019)

Cite This Page — Counsel Stack

Bluebook (online)
2019 Ohio 1407, Counsel Stack Legal Research, https://law.counselstack.com/opinion/davis-v-j-j-concrete-ohioctapp-2019.