Davis v. J & J Concrete

2019 Ohio 1407
Ohio Court of Appeals·Decided April 15, 2019·No. 2018-T-0074·Published·Cited by 5 cases

Opinion

IN THE COURT OF APPEALS

ELEVENTH APPELLATE DISTRICT TRUMBULL COUNTY, OHIO

WILLIAM ROGER DAVIS, : OPINION

Plaintiff-Appellant, :

CASE NO. 2018-T-0074

- vs - :

J&J CONCRETE, et al., :

Defendants-Appellees. :

Civil Appeal from the Trumbull County Court of Common Pleas, Case No. 2015 CV 01992.

Judgment: Affirmed.

David L. Engler, Engler Law Firm, 181 Elm Road, N.E., Warren, OH 44483 (For Plaintiff- Appellant).

Michael D. Rossi, Guarnieri & Secrest, PLL, 151 East Market Street, P.O. Box 4270, Warren, OH 44482 (For Defendants-Appellees).

MARY JANE TRAPP, J.

{¶1} Appellant, William Roger Davis, appeals the judgment of the Trumbull County Court of Common Pleas adopting the magistrate’s $100 award of nominal damages in Mr. Davis’ breach of contract claim against appellee, J&J Concrete (“J&J”). For the following reasons, we affirm.

Substantive and Procedural History

{¶2} Mr. Davis and J&J entered into a contract towards the end of 2013, whereby J&J agreed to pour a concrete mono slab foundation (a mono foundation is a combined footer and floor that is one unit and moves with the ground formed with a single pour of concrete) for Mr. Davis’ “Quonset hut.” A Quonset hut is a prefabricated storage structure made of steel that has a semicircular “bow” shape with all its weight on two sides. The parties agreed on a price of $9,500, which was increased to $10,000 when the foundation was laid.

{¶3} Mr. Davis purchased the Quonset hut kit and accompanying blueprints from a friend, and he used those blueprints and their specifications to obtain estimates from various contractors, including J&J. Mr. Davis later obtained a second set of blueprints directly from the manufacturer, American Steel, when he changed the design of the Quonset hut after the footer was poured in July of 2014.

{¶4} The original blueprints were not before the trial court, but the second set required the mono foundation to be at least 16 inches in depth. The parties stipulated that the 16-inch depth was a specification, together with a requirement that No. 6 rebar be incorporated into the foundation and that the foundation’s strength was to be no less than 2,500 psi (“per square inch” of concrete measures the “crush strength” of concrete).

{¶5} Mr. Davis was running electricity to the Quonset hut a few weeks after the structure was assembled when he noticed the mono foundation was not 16 inches all around.

{¶6} Mr. Davis filed a complaint against J&J in the Trumbull Court of Common Pleas alleging breach of contract, breach of warranty, fraud, and violation of the Ohio Consumer Sales Practice Act (“CSPA”) for J&J’s failure to lay down the foundation with

a 16-inch depth and omission of No. 6 rebar that was to be embedded in the foundation for beam strength.

{¶7} The case proceeded to a hearing before the magistrate where both parties presented witnesses, and a site view was conducted with parties actually digging five random holes for measurement and inspection by the magistrate. The inspection revealed the concrete depth varied from 12 to 16 inches.

{¶8} Mr. Davis submitted two expert witnesses as to the cost of repair. The first, William Conger, owner of W.D.C. Concrete Inc., was also one of the contractors who initially submitted an estimate to lay down the foundation. Mr. Conger explained that the depth of a footer is important to protect structures from frost, especially in northeast Ohio. When structures are subjected to wet and then cold conditions, footers can buckle, twist, and at their worst, destroy a building. Footers are also meant to be completely smooth on the outside so that “the ground can move without moving the structure.” Mr. Conger opined that J&J failed to perform in a workmanlike manner because the foundation bubbled, was not the correct depth, and contained only 3/8 rebar, not the stronger No. 6 rebar called for in the plans.

{¶9} John L. Miller, co-owner of J&J along with his wife, Cindy, disagreed with Mr. Conger’s assessment. Mr. Miller testified that any foundation that was not 40 or more inches, the minimum required to be below the frost level of Trumbull County, was considered a “floating foundation” or a “mono foundation.” In his opinion, “the top just has to be square. What it looks like below ground level does not matter.” Mr. Miller also contested Mr. Davis’ and Mr. Conger’s testimony, contending that he installed No. 6 rebar. He did not have purchase tickets for the rebar (on which Mr. Conger based his testimony)

because Mr. Davis requested a materials list only after the fact, and he “didn’t purchase [the No.6 rebar] specifically for that job.” Mr. Miller supplied the No. 6 rebar from materials he had in his own inventory.

{¶10} As to the cost of repair, Mr. Conger advocated dissembling the entire building, removing the defective foundation, re-pouring it, and lastly, reassembling the building. In his own words, “You cannot put a footer in after the fact.” Digging underneath and putting a new slab in would undermine the strength of the building. This undertaking would cost approximately $50,000.

{¶11} The second expert to testify was the carpenter who assembled the Quonset hut, James R. Wakefield. Mr. Wakefield provided Mr. Davis with an estimate of $49,118 to completely dissemble the structure, remove and then pour a new foundation, and finally, reassemble the building.

{¶12} Both Mr. Davis and Mr. Miller agreed the foundation met the psi requirements of the contract since it had a psi of 4,500.

{¶13} Both parties also agreed the foundation and, correspondingly, the Quonset hut, were undamaged and that the foundation served its purpose without fault since it was built over three years ago.

{¶14} The magistrate issued her findings of fact and conclusions of law. In addition to her findings regarding the parties’ agreement on three particular specifications for the foundation and her observations at the site view as to the depth variances, she also found that the lower portions of the concrete had a “rough, ‘bubbled,’ appearance.” The magistrate found Mr. Miller credibly testified that he did incorporate the No. 6 rebar and the foundation’s strength was 4,500 psi. Further, the Quonset hut served its intended

purpose, and there was no evidence of foundation cracks or other compromise of the building’s structural integrity. The magistrate also found Mr. Conger qualified as an expert in concrete, but not engineering, and was “not a competent expert to render an opinion as to the structural effects of an uneven footer of a Quonset hut.”

{¶15} In her findings of law, the magistrate determined J&J did not materially breach the parties’ contract because it had substantially performed its obligations. While the cost of repairs is ordinarily the proper measure of damages for construction defects, the magistrate found this case does not support a damage award equaling the cost of replacement at the estimate given of $50,000. There was no credible evidence the contract failed its essential purpose and no evidence quantifying any harm from the faulty footers. Therefore, the magistrate concluded Mr. Davis was entitled to nominal damages only and awarded him $100 on the breach of contract claim.

{¶16} After overruling Mr. Davis’ objections, the trial court adopted the magistrate’s findings of fact and conclusions of law. This appeal followed in which Mr. Davis raises the following assignment of error:

{¶17} “The trial court committed reversible error in deciding that plaintiff-appellant was only entitled to recover nominal damages of One Hundred Dollars ($100.00).”

Standard of Review

{¶18} “On appeal, a trial court’s adoption of magistrate’s decision will not be overruled unless the trial court abused its discretion in adopting the decision.” Marble Builder Direct Internatl., Inc. v. Hauxhurst, 11th Dist. Lake No. 2011-L-040, 2012-Ohio- 1674, ¶16, quoting Brown v. Gabram, 11th Dist. Geauga No. 2004-G-2605, 2005-Ohio- 6416, ¶11, citing Lovas v. Mullet, 11th Dist. Geauga No. 2000-G-2289, 2001 Ohio App.

Free access — add to your briefcase to read the full text and ask questions with AI

Davis v. J & J Concrete, 2019 Ohio 1407 (Ohio Ct. App. 2019).

2019 Ohio 1407 (Davis v. J & J Concrete) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Mapleview Operating Co. v. Valletto
2025 Ohio 1898 (Ohio Court of Appeals, 2025)
Crockett Homes, Inc. v. Tracy
2024 Ohio 1464 (Ohio Court of Appeals, 2024)
Perkins v. Petrilli
2022 Ohio 2029 (Ohio Court of Appeals, 2022)
O'Brien v. Shorey
2021 Ohio 2519 (Ohio Court of Appeals, 2021)
In re H.N.M.
2019 Ohio 1601 (Ohio Court of Appeals, 2019)