Perkins v. Petrilli

2022 Ohio 2029
CourtOhio Court of Appeals
DecidedJune 16, 2022
Docket21 MA 0089
StatusPublished
Cited by1 cases

This text of 2022 Ohio 2029 (Perkins v. Petrilli) is published on Counsel Stack Legal Research, covering Ohio Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Perkins v. Petrilli, 2022 Ohio 2029 (Ohio Ct. App. 2022).

Opinion

[Cite as Perkins v. Petrilli, 2022-Ohio-2029.]

IN THE COURT OF APPEALS OF OHIO SEVENTH APPELLATE DISTRICT MAHONING COUNTY

DON PERKINS DBA A1 CONCRETE LEVELING AND FOUNDATION REPAIR,

Plaintiff-Appellant,

v.

JOSEPH PETRILLI,

Defendant-Appellee.

OPINION AND JUDGMENT ENTRY Case No. 21 MA 0089

Civil Appeal from the Mahoning County Court Number Five of Mahoning County, Ohio Case No. 2019 CV F 0032 CNF

BEFORE: Carol Ann Robb, Cheryl L. Waite, David A. D’Apolito, Judges.

JUDGMENT: Affirmed.

Atty. Scott R. Cochran, 19 E. Front Street, Youngstown, Ohio 44503 for Plaintiff-Appellant and Atty. Matthew C. Giannini, 1040 S. Commons Place, Suite 200, Youngstown, Ohio 44514, for Defendant-Appellee, No Brief Filed. –2–

Dated: June 15, 2022

Robb, J.

{¶1} Plaintiff-Appellant Don Perkins, dba A1 Concrete Leveling and Foundation Repair, appeals the decision of the Mahoning County Court Number Five, wherein the court rejected his claims seeking the balance due from Defendant-Appellee Joseph Petrilli on a construction project. Appellant contends the court’s decision was against the manifest weight of the evidence. For the following reasons, the trial court’s decision is affirmed. STATEMENT OF THE CASE {¶2} On May 12, 2015, the parties executed a contract calling for Appellant to perform the following work on a wall around Appellee’s patio: remove all of the existing brick on the walls and steps. Cement block will be returned to original position (replaced if cracked). The block will be filled with rebar every 16” and made solid with Portland cement. The area behind the wall will be excavated to remove existing soil and replaced with clean gravel. Drains will be opened or replace[d] to allow water to flow from behind the wall. All brick replaced. Return to rough grade. The contract also said, “Block will be chosen by customer from sample board as close to house brick.” The testimony indicated this should have said brick instead of block. (Tr. 49). {¶3} The contract price was $15,000. (Def.Ex. 1); (Tr. 24 Stipulation). Appellee paid $7,500 on June 3, 2015 but thereafter refused to pay the remaining $7,500. {¶4} Appellant filed a complaint against Appellee with claims for breach of contract and unjust enrichment, seeking the unpaid balance. Appellee’s answer raised various defenses, such as failure of consideration and unclean hands. Appellee counterclaimed for breach of contract, alleging Appellant failed to perform in a workmanlike manner and used defective materials, which breached the agreement and caused additional property damage. Appellee also set forth a breach of warranty claim. {¶5} The case was tried to the court. Appellant testified he owned the company for 22 years, stating they do some walls but 75% of their work is concrete leveling. He

Case No. 21 MA 0089 –3–

generally did not participate much in the construction work. (Tr. 6). He said Appellee’s old wall was deteriorating, crumbling, and spalling, which may have been from age and water leaching through the brick. (Tr. 27-28). For the replacement wall, he acknowledged providing a five-year warranty for any workmanship issues. (Tr. 44). {¶6} The new wall spanned approximately 50 feet with a break between the two sections for brick stairs. (Tr. 32). From the photographs, the brick wall appeared to be waist high. The section that was a retaining wall was also bench seating (with the top part of the wall constituting the back of the seating). When asked if the bench was level, Appellant acknowledged that some of the bench had a “dip” causing water to pool when it rains. (Tr. 37). {¶7} On the issue of drainage from behind the retaining wall, Appellant admitted he was to install weep holes through the wall so the area behind the wall could drain (rather than deteriorate the wall or freeze behind it). (Tr. 9, 16). He acknowledged he used river rock as fill after excavating the soil, rather than the gravel called for by the contract. (Tr. 39). He did not install drainage pipe (or tile) behind the weep holes, claiming the non-conforming rock would allow for drainage while noting the contract did not specify pipe. (Tr. 40, 46-47). {¶8} Appellant’s attorney asked whether anything occurred during the time the mortar may have been still curing, and Appellant said a brick came off the wall when Appellee put his hand on it as he was using the stairs. (Tr. 14). Appellant concluded the wall had no structural problems and was very functional. (Tr. 15, 37, 51). He acknowledged it was not a perfect wall and there were cosmetic issues (such as an oddly large seam of mortar compared to the other seams) but opined the wall looked good with no movement, deterioration, or evidence of leaching. (Tr. 15, 37, 46-48). {¶9} On the issue of color, the brick did not match the house or the small portion of the old wall which was left intact adjacent to the house. Appellant acknowledged Appellee may have instructed him to make the final choice but pointed out Appellee was contractually responsible for choosing the color. (Tr. 38, 49). However, some of the new bricks seemed as if they did not match each other. {¶10} Appellee’s daughter testified she lived with her father and was living there during construction. At the time, Appellee was recovering from back surgery and could

Case No. 21 MA 0089 –4–

not oversee the work on his patio. (Tr. 63, 81). The daughter spoke about some photographs she took, showing: the retaining portion of the wall; water pooling on the bench; the river rock and the absence of drainage pipes discovered during an investigatory excavation; and a worker drinking beer on the wall. When she complained to Appellant about the beer, he told her to go tell the workers to stop drinking. (Tr. 62). {¶11} The daughter used a level to determine the wall was not level. (Tr. 71). The mortar from where the brick fell off eventually crumbled away a year later. (Tr. 70-71). She said the extra-large seam of mortar ran the entire length of the wall and was not merely in one area as Appellant suggested. (Tr. 68). Within three to four weeks of construction, she noticed mortar “popping off” which thereafter continued to occur on a regular basis; she brought a baggie of the scraps representing what she regularly cleaned from the patio. (Tr. 69). {¶12} She also testified there were “giant cracks” in both sections of the wall, but the court would not permit her to show the photographs due to the failure to provide them in discovery (with the court noting she could testify about the cracks). (Tr. 69, 71, 75-77). She was also not permitted to testify about the three estimates she obtained to repair the wall, but the court agreed to consider her testimony on wanting the wall replaced. (Tr. 65-67). Finally, the daughter showed a photograph of a scratch running down the driveway, which was caused when Appellant’s Bobcat trailer fell apart and scraped the asphalt as they drove away. (Tr. 74). {¶13} Appellee testified his old wall was built with the house in 1979 and was cracked, peeling, and spalling from water pushing through the brick. (Tr. 79-80). Drainage was one of the main items he wanted from the contract in order to avoid the same situation. (Tr. 89). He assumed that since the soil was being removed, the additional contract requirement that “Drains will be opened or replace[d] to allow water to flow from behind the wall” would include the installation of perforated pipes leading to the installed weep holes (opining it was common sense and noting he has never witnessed the weep holes functioning). (Tr. 90). {¶14} Appellee also complained about the following: the use of river rock instead of gravel; the wall being “half a bubble” off level all around; the pooling of water on the bench; the mortar spontaneously flaking off; grit from the mortar falling off when rubbed

Case No. 21 MA 0089 –5–

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Crockett Homes, Inc. v. Tracy
2024 Ohio 1464 (Ohio Court of Appeals, 2024)

Cite This Page — Counsel Stack

Bluebook (online)
2022 Ohio 2029, Counsel Stack Legal Research, https://law.counselstack.com/opinion/perkins-v-petrilli-ohioctapp-2022.