Yashphalt Seal Coating v. Giura

2019 Ohio 4231
CourtOhio Court of Appeals
DecidedOctober 15, 2019
Docket18 MA 0107
StatusPublished
Cited by7 cases

This text of 2019 Ohio 4231 (Yashphalt Seal Coating v. Giura) is published on Counsel Stack Legal Research, covering Ohio Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Yashphalt Seal Coating v. Giura, 2019 Ohio 4231 (Ohio Ct. App. 2019).

Opinion

[Cite as Yashphalt Seal Coating v. Giura, 2019-Ohio-4231.]

IN THE COURT OF APPEALS OF OHIO SEVENTH APPELLATE DISTRICT MAHONING COUNTY

YASHPHALT SEAL COATING, LLC,

Plaintiff-Appellee,

v.

THOMAS GIURA,

Defendant-Appellant.

OPINION AND JUDGMENT ENTRY Case No. 18 MA 0107

Civil Appeal from the Court of Common Pleas of Mahoning County, Ohio Case No. 2017 CV 01866

BEFORE: Gene Donofrio, Cheryl L. Waite, Carol Ann Robb, Judges.

JUDGMENT: Affirmed.

Atty. Damian DeGenova, DeGenova & Yarwood, Ltd., 42 North Phelps Street, Youngstown, Ohio 44503, for Plaintiff-Appellee, and

Atty. Charles Dunlap, 7330 Market Street, Youngstown, Ohio 44512, for Defendant- Appellant. –2–

Dated: October 8, 2019

DONOFRIO, J.

{¶1} Defendant-appellant, Thomas Giura (individually and as the operator of Tom Giura Automotive Service), appeals the judgment of the Mahoning County Common Pleas Court following a bench trial finding in favor of plaintiff-appellee, Yashphalt Seal Coating, LLC, on appellee’s claims of breach of contract and unjust enrichment. {¶2} In June of 2015, appellant contacted appellee for the purpose of hiring appellee to repave the parking lot at appellant’s place of business. In July of 2016, appellant and appellee agreed to the terms of the repaving job. Under the written agreement, appellee was to: remove and haul away the concrete in the lot as needed, bring in gravel where needed, roll and compact the gravel, lay a 1.5 inch base layer of asphalt, roll and compact the base layer, lay a 1.5 inch top layer of asphalt, and roll and compact the top layer. In exchange, appellant would pay appellee $22,000 for the repaved parking lot. Appellant made an initial deposit of $10,000, and appellee began work on the repaving job on July 13, 2016. {¶3} Appellee completed the repaving job in approximately two weeks. After the repaving job was completed, appellant complained that the job was not done in a satisfactory manner. Appellant claimed the parking lot was not a uniform color, the parking lot was not flat, and cracks began to form. Appellant also claimed that appellee damaged part of his fence, did not replace the concrete parking bumpers on the lot, and removed too much concrete from the original lot. As a result, appellant refused to pay the remaining $12,000 on the contract. {¶4} On April 4, 2017, appellee filed this action in the Youngstown Municipal Court alleging claims of breach of contract and unjust enrichment. Appellee sought the unpaid $12,000 for the repaving job. On April 24, 2017, appellant filed an answer and counterclaim as well as a motion to transfer this action to the Mahoning County Common Pleas Court. The counterclaim raised claims of breach of contract and unjust enrichment on the basis that appellee only partially performed on the contract in an unworkmanlike manner. The counterclaim sought damages for appellant’s damaged fence and the costs of hiring another company to repave appellant’s parking lot. The motion to transfer argued

Case No. 18 MA 0107 –3–

that appellant’s counterclaim exceeded the jurisdictional amount of the Youngstown Municipal Court. On July 19, 2017, the Youngstown Municipal Court granted the motion to transfer the matter to the Mahoning County Common Pleas Court. {¶5} The matter proceeded to a bench trial before a magistrate on May 22, 2018. Three witnesses testified at trial: Albert Yash (appellee’s managing member), Nick Chammas (appellant’s engineering expert), and appellant. Yash testified that the discoloration of the parking lot was due to purchasing asphalt from two different suppliers. As for the varying heights of the parking lot, Yash testified that the parking lot was paved thinner near the street and thicker in the middle to allow for water drainage. Yash also testified that the concrete parking bumpers were not immediately replaced because it was too hot to operate the necessary machinery to replace the bumpers without damaging the parking lot. Yash admitted that his work damaged the fence. {¶6} Chammas testified that he took five core samples of appellant’s parking lot after appellee’s repaving job. The asphalt samples Chammas took ranged in thickness from 1.56 inches (near the entrance of the parking lot) to 6.01 inches. On average, the asphalt was approximately 3.5 inches thick. Chammas opined that appellee’s performance on the repaving job did not meet industry standards. {¶7} Appellant testified that it cost $787.88 to repair the damage done to his fence. Appellant testified that he did not pay the remaining $12,000 because the asphalt appellee laid was cracking. Appellant also testified that appellee ripped out more concrete than what was originally agreed upon and the cost to replace the excessively removed concrete was $3,456. Finally, appellant testified that, after appellee completed the repaving job, appellant was using the parking lot for its intended purpose. {¶8} On July 10, 2018, the magistrate issued his findings of fact and conclusions of law. The magistrate found that appellee substantially performed on the contract and therefore, did not breach the contract. The magistrate therefore found that appellant breached the contract by not paying the remaining $12,000. But the magistrate held that appellant was entitled to offset the unpaid invoice amount by $787.88 for the cost to repair the fence as well as $3,456 for the concrete appellee erroneously removed. {¶9} On July 23, 2018, appellant filed an objection to the magistrate’s decision arguing the magistrate’s legal and factual conclusions were not supported by the

Case No. 18 MA 0107 –4–

evidence. Appellant argued that Chammas’ testimony showed that appellee’s repaving job did not substantially comply with the contract. Appellee did not file a response to this objection. {¶10} On September 11, 2018, the trial court overruled appellant’s objection and adopted the magistrate’s decision in its entirety. Appellant timely filed this appeal on October 4, 2018. Appellant now raises one assignment of error. {¶11} Appellant’s sole assignment of error states:

THE TRIAL COURT ERRED IN ADOPTING THE JULY 10, 2018 MAGISTRATE’S DECISION. JUDGMENT ENTRY T.D. 15, P. 1.

{¶12} Appellant makes two arguments regarding his sole assignment of error. First, appellant argues that the trial court erred in finding appellee did not breach the contract because appellee repaved the parking lot in an unworkmanlike manner. Second, appellant argues that the evidence produced at trial showed that appellee breached the contract by not substantially complying with the terms of the contract. {¶13} Appellant and appellee disagree on the standard of review this court is to apply in this assignment of error. Appellant argues that a mixed de novo and abuse of discretion standard of review apply because the magistrate misapplied the doctrine of substantial compliance and the trial court erred when it overruled his objection. Appellee argues that a manifest weight of the evidence standard of review applies because appellant is appealing the trial court’s judgment after a trial. {¶14} This court has previously held that a trial court’s ruling on an objection to a magistrate’s decision after a bench trial is subject to an abuse of discretion standard of review. RBS Citizens, NA v. Sharp, 7th Dist. Mahoning No. 13 MA 11, 2015-Ohio-5438, ¶ 5, 18. An abuse of discretion is more than an error of law or judgment; it implies that the trial court's judgment was unreasonable, arbitrary, or unconscionable. Blakemore v. Blakemore, 5 Ohio St.3d 217, 219, 450 N.E.2d 1140 (1983). {¶15} The claims relevant to this appeal are the parties’ respective breach of contract claims.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Williams v. Edgell
2024 Ohio 2129 (Ohio Court of Appeals, 2024)
Crockett Homes, Inc. v. Tracy
2024 Ohio 1464 (Ohio Court of Appeals, 2024)
Perkins v. Petrilli
2022 Ohio 2029 (Ohio Court of Appeals, 2022)
Watkins v. Alwishah
2021 Ohio 3589 (Ohio Court of Appeals, 2021)
State v. Fowler
2021 Ohio 2854 (Ohio Court of Appeals, 2021)
State v. Italiano
2021 Ohio 1283 (Ohio Court of Appeals, 2021)
Gionino's Pizzeria, Inc. v. Reynolds
2021 Ohio 1289 (Ohio Court of Appeals, 2021)

Cite This Page — Counsel Stack

Bluebook (online)
2019 Ohio 4231, Counsel Stack Legal Research, https://law.counselstack.com/opinion/yashphalt-seal-coating-v-giura-ohioctapp-2019.