Williams v. Edgell

2024 Ohio 2129
CourtOhio Court of Appeals
DecidedJune 3, 2024
Docket23 CO 0013
StatusPublished
Cited by2 cases

This text of 2024 Ohio 2129 (Williams v. Edgell) is published on Counsel Stack Legal Research, covering Ohio Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Williams v. Edgell, 2024 Ohio 2129 (Ohio Ct. App. 2024).

Opinion

[Cite as Williams v. Edgell, 2024-Ohio-2129.]

IN THE COURT OF APPEALS OF OHIO SEVENTH APPELLATE DISTRICT COLUMBIANA COUNTY

BILLY J. WILLIAMS ET AL.,

Plaintiffs-Appellees,

v.

CHRIS EDGELL ET AL.,

Defendants-Appellants.

OPINION AND JUDGMENT ENTRY Case No. 23 CO 0013

Civil Appeal from the Court of Common Pleas of Columbiana County, Ohio Case No. 2021 CV 360

BEFORE: Katelyn Dickey, Cheryl L. Waite, Carol Ann Robb, Judges.

JUDGMENT: Affirmed in part. Reversed and Vacated in part.

Atty. Mark A. Hutson, for Plaintiffs-Appellees and

Atty. Carl J. King, for Defendants-Appellants.

Dated: June 3, 2024 –2–

DICKEY, J.

{¶1} Appellants, Chris Edgell (“Edgell”) and Edgell Construction, LLC (“Edgell Construction” or “company”), appeal the decision and judgment entry of the Columbiana County Court of Common Pleas awarding damages in the amount of $14,586.16 to Appellees, Billy Joe and Betsy Williams following a bench trial in this action for breach of contract and unjust enrichment. Both sides agree they entered into an oral contract for the construction of a 40’ x 60’ pole building. Appellees successfully argued at trial the pole building was not constructed in a workmanlike manner. {¶2} Appellants advance two assignments of error. First, they argue the judgment entry is against the manifest weight of the evidence. Second, they contend the trial court erred in concluding they were unjustly enriched by Appellees, insofar as the parties agree an express agreement existed regarding the construction of the pole building. For the following reasons, the decision and judgment entry is affirmed in part, as it relates to the breach of contract claim, and reversed and vacated in part, as it relates to the unjust enrichment claim.

FACTS AND PROCEDURAL HISTORY

{¶3} Five witnesses testified at the December 14, 2022 bench trial: Appellees (“Billy Joe” and “Betsy”), and Keith English (“English”), who performed an inspection of the pole building, on behalf of Appellees; and Edgell, and Gary Pankuch (“Pankuch”), the foreman of Edgell Construction, on behalf of the company. {¶4} In the spring of 2020, Appellees elected to remove an impractical 24’ x 34’ barn1 from their property located in Columbiana County and build a four-bay garage. Billy Joe, who worked for his father’s construction company when he was a teen, first considered purchasing a building kit, which would require assembly and installation by Appellees. Daunted by the amount of work required with a building kit, Appellees chose instead to hire a local contractor.

1The barn was destroyed by the West Point Fire Department in a controlled burn training exercise on May 6, 2020.

Case No. 23 CO 0013 –3–

{¶5} After seeking recommendations from various lumber suppliers, Appellees solicited estimates from several construction companies. Billy Joe explained “[it is] hard to get [contractors] to show up,” but he was able to acquire bids from two companies. (Trial Tr., p. 85.) Edgell, who testified he had constructed between 200 to 300 pole barns in the past, visited the property and formulated a bid for a 40’ by 60’ pole building based on Appellees’ planned use for the structure. {¶6} Edgell testified the site “should have been a little bit more level [than] it was” (he estimated that “there was about four foot [sic] from end to end that was off”) and “once [ ] the pole barn [was built] there was about five foot [sic] of fill that needed put in this pole barn.” As a consequence, Edgell recommended an excavator that he had used on roughly 100 previous jobs. However, Appellees chose to employ the excavator who was currently constructing a pond on their property. (Id., p. 201-203.) The parties agreed that Appellees would be responsible for the cement and electrical work and the gutter installation after construction of the building was complete. {¶7} Billy Joe testified he asked Edgell if Edgell “would want to write up a – more or less formal agreement.” Edgell responded, “No, [I am] a man of my word, do a handshake thing, and [it will] be fine.” (Id., p. 89.) Edgell did not dispute that he declined to execute a written agreement. {¶8} Edgell quoted a price of $26,000 for the building and $5,600 for the garage doors. Appellees testified Edgell intended to acquire the garage doors from a local company. Billy Joe testified that Edgell agreed to pay the cost of the installation of the garage doors. Betsy similarly testified that Edgell agreed to pay “Hayd[e]n Wright” to install them. (Id., p. 180.) {¶9} Edgell testified the company does not install garage doors, and at the time the oral contract was entered, he regularly recommended Hayden Wright as a garage door installer to his customers. He denied having offered or agreed to pay for the installation of the garage doors. {¶10} Appellees paid $13,000 in cash to Edgell on April 17, 2020 as a down payment, which Edgell used to purchase materials for the job. Construction materials were purchased on April 20, 2020 from Tri-State Metal Sales.

Case No. 23 CO 0013 –4–

{¶11} Construction began on May 13, 2020 and concluded five days later. Pankuch, who testified that he had constructed over 2000 pole buildings in the past, oversaw the construction with Edgell. Edgell testified the project crew as constituted had previously constructed roughly 100 pole buildings. {¶12} At some point during construction, Edgell destroyed two pots containing tomato plants in Appellees’ driveway. Edgell testified he drives a large truck and was not aware that he had broken the pots. When Appellees discovered the damage to the pots, they asked Edgell to replace them. {¶13} On May 13, 2020, Appellees made an additional payment of $3,000 in order for Edgell to “meet payroll.” (Id., p. 92.) On May 15, 2020, Appellees made a cash payment in the amount of $5,600 for the garage doors. On May 19, 2020, Appellees made a final cash payment in the amount of $10,000. Appellants concede the contract was paid in full. {¶14} Edgell testified he discovered on the first day of construction that Appellees’ excavator “had dug three foot [sic] [of dirt] out of the wrong side of the building when [Edgell] told him where to dig.” (Id., p. 209.) Edgell explained “that raises the building up out of the ground. It’s way more fill that needs to go in, and then it shortens the poles on the gables.” (Id., p. 210.) Edgell remedied the situation by using 20-foot poles instead of 16-foot poles. He testified 20-foot poles are the longest treated poles available. Pankuch likewise testified the grade of the property was “severely off” requiring the use of longer poles. (Id., p. 277.) {¶15} During construction and for several months following, Appellees were occupied with the care of Billy Joe’s father, who was an invalid and required near constant care. After he passed on July 13, 2020, Appellees were occupied with the administration of his estate. As a consequence, the cement and electrical work for which Appellees were responsible was delayed. {¶16} Gutters were installed on June 29, 2020. The gutter installer informed Billy Joe that there was no drip edge on the building, and the bottom row of screws, front and back, had not been installed. The gutter installer furnished the drip edge and screws and installed them free of charge.

Case No. 23 CO 0013 –5–

{¶17} The interior floor was poured on July 26, 2020 and the exterior concrete on August 24, 2020. Billy Joe testified “a lot of deficiencies [in the workmanship of the building construction] got pointed out to [him] by the concrete guys.” (Id., p. 98.) {¶18} Appellees testified the summer of 2020 was unseasonably dry. After a rare storm, Appellees noticed five different water leaks, as well as pools of water inside the west end of the building, which were previously masked by the gravel floor.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Estate of Gregory v. QDP Wholesale Auto, L.L.C.
2025 Ohio 1979 (Ohio Court of Appeals, 2025)
Johnson v. Sailor
2025 Ohio 212 (Ohio Court of Appeals, 2025)

Cite This Page — Counsel Stack

Bluebook (online)
2024 Ohio 2129, Counsel Stack Legal Research, https://law.counselstack.com/opinion/williams-v-edgell-ohioctapp-2024.