Watershed Mgt., L.L.C. v. Neff

2012 Ohio 1020
CourtOhio Court of Appeals
DecidedMarch 8, 2012
Docket10CA42
StatusPublished
Cited by10 cases

This text of 2012 Ohio 1020 (Watershed Mgt., L.L.C. v. Neff) is published on Counsel Stack Legal Research, covering Ohio Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Watershed Mgt., L.L.C. v. Neff, 2012 Ohio 1020 (Ohio Ct. App. 2012).

Opinion

[Cite as Watershed Mgt., L.L.C. v. Neff, 2012-Ohio-1020.]

IN THE COURT OF APPEALS OF OHIO FOURTH APPELLATE DISTRICT PICKAWAY COUNTY

WATERSHED MANAGEMENT, LLC, : : Plaintiff-Appellee, : Case No. 10CA42 : vs. : Released: March 8, 2012 : JOHN NEFF, : DECISION AND JUDGMENT : ENTRY Defendant-Appellant. :

APPEARANCES:

Richard T. Ricketts, Ricketts Co., LPA, Pickerington, Ohio, for Appellant.

Michael N. Beekhuizen, Carpenter Lipps & Leland, LLP, Columbus, Ohio, for Appellee.

McFarland, J.:

{¶1} Appellant John Neff appeals the trial court’s decision granting

summary judgment to Appellee Watershed Management, LLC, the trial court’s

denial of a motion to intervene, and the imposition of attorney fees and costs. Neff

argues 1) the trial court erred by granting summary judgment when genuine issues

of material fact remained; 2) the trial court erred in not finding that res judicata

applied to certain issues; 3) the trial court erred in denying a third party’s motion to

intervene; 4) the trial court erred in finding Appellant acted in bad faith and

awarding attorney fees for such; 5) the trial court erred in awarding attorney fees Pickaway App. No. 10CA42 2

without requiring evidence they were reasonable and necessary; 6) the trial court

erred in calculating costs, which included deposition and transcript costs; and 7)

the trial court erred in granting a motion for a final judgment without giving the

adverse party an opportunity to respond.

{¶2} Having reviewed the record, we find that the trial court erred in

granting summary judgment on Appellee’s breach of contract claim, and in issuing

its final judgment entry without affording Appellant an opportunity to be heard on

the matter. Accordingly, we reverse the judgment of the trial court in part, and

remand the case for further proceedings.

FACTS

{¶3} In 2005, Pickaway County completed the construction of a ditch near

Caldwell Road. The purpose of the ditch was to divert water from the roadbed and

prevent its softening. According to Douglas Kohli (“Kohli”), a district technician

for the Pickaway County Soil & Water Conservation District (“SWCD”), the

Caldwell Road project did not break watershed, or change the ultimate destination

of the water. The ditch merely diverted water from the roadbed and directed it to

its natural outlet, albeit via a faster route.

{¶4} However, Appellant John Neff (“Neff”) believed otherwise. Neff

maintained that the ditch diverted water onto his land, creating drainage and

erosion problems. Neff voiced his concern and displeasure to the Pickaway Pickaway App. No. 10CA42 3

County commissioners. In response, the commissioners consulted Kohli for a

possible solution. Kohli suggested that Neff and surrounding landowners install

grass waterways, which were grass-covered parabolic channels. Kohli explained

the Natural Resources Conservation Service (“NRCS”) and the Farm Service

Agency (“FSA”) administered programs that could reimburse landowners for up to

90% of the cost of constructing these waterways. The landowners would have to

agree to maintain the waterways for a certain number of years, and the

government, in addition to reimbursing most of the construction costs, would pay

rental fees to the landowners as compensation for the tillable acreage the

waterways replaced.

{¶5} Subsequently, Mark Ruff (“Ruff”), who farmed Neff’s land; Carl

Hamman (“Hamman”), who was the owner and sole member of Appellee

Watershed Management, LLC (“Watershed”); and Neff met. Ruff had organized

the meeting to suggest Neff select Watershed as the contractor to construct the

waterways. Ruff had worked with Watershed in the past and was familiar with the

process, so he again outlined the process for constructing the waterways, obtaining

reimbursement, and paying the contractor. Kohli would design the waterways and

Watershed would construct them. Watershed would only charge Neff the amount

that the government would reimburse him – 90% of the estimated cost – plus

additional fees for any extra materials or work that was required. Pickaway App. No. 10CA42 4

{¶6} Neff agreed to this arrangement, though he did not sign a written

contract. Neff selected to upgrade the clay drainage tile for a portion of the

project, which meant that he would owe Watershed $1,900 above the amount the

government would reimburse him for the waterways.

{¶7} With all of the landowners agreeing to the waterways project, Kohli

actually designed the waterways and Watershed began construction. During

construction, Kohli noticed that a span of nearly 400 feet of the waterway could

potentially break watershed. Breaking watershed would result in changes in peak

water flow downstream, as well as increased erosion, which could subject the

entities involved to litigation. Additionally, Kohli knew that the Pickaway County

Engineer’s policy was not to break watershed, so Kohli amended the plans to avoid

breaking watershed. Kohli asked Watershed not to complete the remaining 400

feet as a waterway, but to have the waterway stop short of its originally intended

termination point and blend it into the landscape instead.

{¶8} When the waterways were completed, Kohli examined them and

certified they were constructed as designed and were working properly. Kohli

forwarded his plans and certification to the NRCS, which agreed with his

assessments and approved and forwarded the plans to the appropriate authorities.

{¶9} Prior to completion, Ruff sent a letter to each landowner, stating that

they needed to meet with the SWCD to complete additional paperwork and if there Pickaway App. No. 10CA42 5

was a perceived problem with the waterway, they needed to address it

immediately. Ruff then sent out letters to the landowners, including Neff,

explaining that Watershed would be sending them bills for the work completed.

Ruff explained that the bill was only to be used for submission to the FSA, but

there would also be a second bill with a negotiated balance, the amount the

landowner would have to pay. Neff never complained about the waterways to

anyone involved, nor did he dispute the bill when Watershed presented it to him.

{¶10} To finalize the project and have the government reimburse him, Neff

completed the final paperwork, wherein he certified that the waterways had been

constructed as designed and requested reimbursement for his costs. The

government ultimately approved Neff’s request for reimbursement.

{¶11} Contrary to Kohli’s certification that the waterways were working

correctly, Neff believed that they were not. Despite Kohli’s concern for breaking

watershed, Neff believed that the waterways should have extended the additional

400 feet. Neff also stated that there was a lip, or ridge, along the edge of part of

the waterways that prevented portions of his fields from draining. Having these

complaints, Neff initially did not accept the government reimbursement checks,

but finally acquiesced.

{¶12} Meanwhile, Watershed was at a loss as to why Neff had not paid his

bill, since Kohli and the NCRS had certified that the waterways were working Pickaway App. No. 10CA42 6

properly, Neff had certified that they were built correctly, and the government had

approved Neff’s reimbursement. Watershed also understood, as did Kohli, that the

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Castro v. Hero Havens, L.L.C.
Ohio Court of Appeals, 2026
Waldock v. Waldock Invest. Co.
2025 Ohio 872 (Ohio Court of Appeals, 2025)
Williams v. Edgell
2024 Ohio 2129 (Ohio Court of Appeals, 2024)
Teays Valley Local School Dist. Bd. of Edn. v. Struckman
2023 Ohio 244 (Ohio Court of Appeals, 2023)
Taylor v. Honda Motorcars, Inc.
2019 Ohio 1891 (Ohio Court of Appeals, 2019)
Rojas v. Concrete Designs, Inc.
2017 Ohio 379 (Ohio Court of Appeals, 2017)
Fade v. Morris
2015 Ohio 5337 (Ohio Court of Appeals, 2015)
Martin v. Jones
2015 Ohio 3168 (Ohio Court of Appeals, 2015)
Watershed Mgt. v. Neff
2014 Ohio 3631 (Ohio Court of Appeals, 2014)
Sexton v. Certified Oil Co.
2013 Ohio 482 (Ohio Court of Appeals, 2013)
Am. Sav. Bank v. Pertuset
2013 Ohio 566 (Ohio Court of Appeals, 2013)

Cite This Page — Counsel Stack

Bluebook (online)
2012 Ohio 1020, Counsel Stack Legal Research, https://law.counselstack.com/opinion/watershed-mgt-llc-v-neff-ohioctapp-2012.