Kersh v. Montgomery Developmental Center

519 N.E.2d 665, 35 Ohio App. 3d 61, 1987 Ohio App. LEXIS 10531
CourtOhio Court of Appeals
DecidedFebruary 12, 1987
Docket86AP-629
StatusPublished
Cited by44 cases

This text of 519 N.E.2d 665 (Kersh v. Montgomery Developmental Center) is published on Counsel Stack Legal Research, covering Ohio Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Kersh v. Montgomery Developmental Center, 519 N.E.2d 665, 35 Ohio App. 3d 61, 1987 Ohio App. LEXIS 10531 (Ohio Ct. App. 1987).

Opinion

Strausbaugh, P.J.

Plaintiff appeals from a judgment of the Court of Claims denying her claim for payment of compensatory time earned, but not used.

Plaintiff Lois H. Kersh, D.O., a.k.a. Lois H. Chambers, D.O., was employed by defendant Montgomery Developmental Center, commencing October 19, 1981, as a Physician Administrator 2 and Medical Director. In order to implement the provisions of R.C. 5123.85(E), the Department of Mental Retardation and Developmental Disabilities (“DMRDD”) required that each developmental center have twenty-four-hour physician coverage. Plaintiff’s contract with . defendant called for around-the-clock coverage, seven days per week.

The contract provided that plain *62 tiff would be compensated at a specified hourly rate. Plaintiff was to be paid this rate for all “hands-on” time — time plaintiff was actually present at the facility.

The additional hours of coverage needed to fulfill the twenty-four-hour coverage would be met by plaintiff being “on call.” Compensation for on-call time has to be made under a system where three hours of on-call time equalled one hour of compensable time. All hours over forty hours per week were to be compensated by compensatory time off (“comp-time”).

When plaintiff resigned her position in April 1984, she made demand of defendant for payment of the comp-time accumulated, but not used. The Court of Claims entered judgment for defendant, finding that plaintiff was not entitled to further compensation.

The court based its decision on two grounds. First, since plaintiff had breached her contract with defendant, plaintiff was barred from making a claim under that contract. But more importantly, the court found that plaintiff’s overtime-exempt status barred her claim for reimbursement of comp-time.

Plaintiff asserts two assignments of error:

“ 1. The court erred in holding that appellant’s ‘overtime-exempt’ status barred her from converting compensatory time earned into straight time pay.
“2. The court erred in holding that appellant did not fulfill the terms of her employment contract.”

In order to reach plaintiff’s second assignment of error, it is first necessary to consider the breach of contract claim. Since the court below found that plaintiff’s breach of contract barred her claim in any event, that issue must be addressed in order to reach the statutory “overtime-exempt” question.

The Court of Claims found that plaintiff’s contract specifically required her to be present at the facility ten hours per week. We agree. Plaintiffs testimony and evidence clearly reveal this. Moreover, the court found that plaintiff was present only 5.8 to 6.9 horn's per week. From the foregoing the court concluded that plaintiff breached her contract and denied her claim under that contract, stating: “[o]ne seeking equitable relief must come into court with clean hands.”

The gist of the decision is that plaintiff’s breach of a specific term in her contract barred her from seeking relief under that contract. With this we do not agree.

A breach of one of several terms in a contract does not discharge the obligations of the parties to the contract, unless performance of that term is essential to the purpose of the agreement. Boehl v. Maidens (1956), 102 Ohio App. 211, 2 O.O. 2d 204, 139 N.E. 2d 645. Stated another way, default by a party who has substantially performed does not relieve the other party from performance. Hadden v. Consolidated Edison Co. of N.Y., Inc. (1974), 34 N.Y. 2d 88, 356 N.Y. Supp. 2d 249, 312 N.E. 2d 445. Cf. 6 Williston, Contracts (3 Ed. 1962) 165, Section 842; Restatement of the Law 2d, Contracts (1981) 237, Section 241.

The Restatement sets out five factors to be considered in deciding whether a failure to render performance is material:

“(a) the extent to which the injured party will be deprived of the benefit which he reasonably expected;
“(b) the extent to which the injured party can be adequately compensated for the part of that benefit of which he will be deprived;
“(c) the extent to which the. party failing to perform or to offer to perform will suffer forfeiture;
“(d) the likelihood that the party *63 failing to perform or to offer to perform will cure his failure, taking account of all the circumstances including any reasonable assurances;
“(e) the extent to which the behavior of the party failing to perform or to offer to perform comports with standards of good faith and fair dealing.” Restatement of the Law 2d, Contracts (1981) 237, Section 241.

Applying these factors to the instant case, the most significant circumstance is the extent to which defendant was deprived of the benefit it sought. Clearly, because defendant required it by rule, the benefit expected was twenty-four-hours-per-day, seven-days-per-week coverage. In fact, that is what the contract specifically provided for. Merely because one term called for ten hours of hands-on care per week does not negate the fact that plaintiff substantially complied with the purpose of the contract. She was available twenty-four hours per day, seven days per week. Whether she was ever called or not is immaterial. Defendant required around-the-clock coverage and plaintiff was available around the clock.

Therefore, plaintiffs second assignment of error is well-taken and sustained. We note in passing, however, that plaintiff’s breach of a term, even if a minor term, does not relieve her of liability. On remand, the trial court may consider this issue if it is raised by defendant.

Turning to plaintiffs first assignment of error, we find that the court based its decision denying plaintiffs claim primarily on the fact that plaintiff was “overtime exempt.” As such, there was no statutory basis for converting “comp-time” into cash payments for overtime hours worked. The Court of Claims found that plaintiff’s only option was to take the time off. Such conclusion is not in accord with Ohio law.

To adopt the Court of Claims’ position would place state employees like Dr. Kersh in a quandary. By contract, plaintiff was entitled to one hour of comp-time for every three horns over forty hours per week actually earned. Plaintiff was required to earn comp-time since she was on call twenty-four hours per day, seven days per week. As the only physician on call for most of her tenure, plaintiff could not use the time she earned since she was always on call. Thus, although she earned the time, plaintiff could not use it. Nor could she, according to the trial court, be compensated for it. We do not believe this state’s law requires that result.

Clearly, plaintiff was “overtime exempt.” R.C. 124.18 specifies that employees paid under Schedule C of R.C. 124.15(A) are overtime exempt. 1 Since plaintiff was paid under that schedule, and because her position was classified by defendant as overtime exempt, she was not entitled to overtime pay.

But plaintiff does not claim she is entitled to pay.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

SJBK, L.L.C. v. Northwood Energy Corp.
2023 Ohio 4729 (Ohio Court of Appeals, 2023)
Perkins v. Petrilli
2022 Ohio 2029 (Ohio Court of Appeals, 2022)
ZUZEL v. SEPTA
E.D. Pennsylvania, 2021
Artistic Carpet Warehouse, Inc. v. King
2021 Ohio 849 (Ohio Court of Appeals, 2021)
Mid Am. Constr., L.L.C. v. Univ. of Akron
2018 Ohio 4513 (Ohio Court of Claims, 2018)
Whitt Sturtevant, L.L.P. v. NC Plaza L.L.C.
2015 Ohio 3976 (Ohio Court of Appeals, 2015)
491 N. Park Real Estate, L.L.C. v. Spice Partners, L.L.C.
2014 Ohio 5164 (Ohio Court of Appeals, 2014)
Watershed Mgt. v. Neff
2014 Ohio 3631 (Ohio Court of Appeals, 2014)
N.L. Constr. Corp. v. Ohio Dept. of Adm. Servs.
2012 Ohio 6328 (Ohio Court of Claims, 2012)
Crockett Homes, Inc. v. Hamilton
2012 Ohio 2162 (Ohio Court of Appeals, 2012)
Hostetler v. Cent. Farm & Garden, Inc.
2012 Ohio 507 (Ohio Court of Appeals, 2012)
Marlon Jackson v. State Farm Fire & Casualty Co
461 F. App'x 422 (Sixth Circuit, 2012)
In Re Old Carco LLC
452 B.R. 100 (S.D. New York, 2011)
State ex rel. Dann v. Nacional
2011 Ohio 2818 (Ohio Court of Claims, 2011)

Cite This Page — Counsel Stack

Bluebook (online)
519 N.E.2d 665, 35 Ohio App. 3d 61, 1987 Ohio App. LEXIS 10531, Counsel Stack Legal Research, https://law.counselstack.com/opinion/kersh-v-montgomery-developmental-center-ohioctapp-1987.