Mid Am. Constr., L.L.C. v. Univ. of Akron

2018 Ohio 4513
CourtOhio Court of Claims
DecidedOctober 1, 2018
Docket2016-00685JD
StatusPublished

This text of 2018 Ohio 4513 (Mid Am. Constr., L.L.C. v. Univ. of Akron) is published on Counsel Stack Legal Research, covering Ohio Court of Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Mid Am. Constr., L.L.C. v. Univ. of Akron, 2018 Ohio 4513 (Ohio Super. Ct. 2018).

Opinion

[Cite as Mid Am. Constr., L.L.C. v. Univ. of Akron, 2018-Ohio-4513.]

MID AMERICAN CONSTRUCTION, LLC Case No. 2016-00685JD

Plaintiff/Counter Defendant Judge Dale A. Crawford

v. DECISION

UNIVERSITY OF AKRON

Defendant/Counter Plaintiff/Third-Party Plaintiff

v.

FIDELITY AND DEPOSIT COMPANY OF MARYLAND

Third-Party Defendant

{¶1} Plaintiff Mid American Construction, LLC (MAC) filed its complaint against defendant, University of Akron (the University), asserting three claims, two breach of contract claims and a claim under R.C. 1311.31. Along with its answer, the University filed a counterclaim and third-party complaint. The University’s counterclaim asserts two breach of contract claims and a breach of warranty claim against MAC. The University’s third-party complaint asserts two breach of contract claims against MAC’s surety, the Fidelity and Deposit Company of Maryland (Fidelity). For the following reasons, the Court hereby renders judgment in favor of MAC in the amount of $2,258,700.

BACKGROUND {¶2} MAC and the University executed a contract on December 12, 2014 (the original contract) (Ex. 2) whereby the University agreed to pay MAC a total of $5,137,700 to act the general trades contractor for the Zook Hall Renovation Project Case No. 2016-00685JD -2- DECISION

Phase 2B (the project). MAC was not involved with the project’s previous phases. MAC executed a bond, issued by Fidelity, in favor of the University. MAC’s work included, among other items, patching, painting, framing and other carpentry work, tile work, and drywall work. (Ex. 2, p. 131). MAC performed substantial work on various parts of Zook’s interior including the lecture hall and classrooms as well as extensive exterior work expanding and renovating parts of the building’s facade, windows and exterior doors. Mr. Dan Trinetti, MAC’s senior project manager, acted as MAC’s representative and handled day-to-day operations on the project. {¶3} The project was a “multi-prime” project, meaning that the University entered into separate contracts with other contractors for fire suppression, plumbing, HVAC, and electrical work. The University also executed separate contracts with a construction manager, Thomarios, and an architect, Stantec. Thomarios employed George Brkich as its project manager who was in charge on a day-to-day basis. Thomarios’ responsibilities included coordinating the scheduling and work of all prime contractors including MAC for the express purpose of ensuring completion of the project by the completion date of February 10, 2016. (Ex. 2, § 6.5 of the general conditions; Contracting Definitions, p. 3 of 10). Stantec employed Ryan McNutt as its project manager. Stantec provided architectural design services and construction administration services and contracted with another firm for engineering services. Mr. James Haskell, the University’s Director of Campus Planning and Space Utilization, was the University’s primary representative during the project. Messrs. Brkich and McNutt acted, for the first time, in their respective roles. {¶4} MAC began work on the project in January of 2015. The original contract provided 401 days, or until February 10, 2016, for completion of the project. (Ex. 2, p. 2; 29; 138). As explained more below, the project experienced delay. The University attributed all delay on the project to MAC and stopped paying MAC and its Case No. 2016-00685JD -3- DECISION

subcontractors for their work on or around September 30, 2015. On December 18, 2015, the University sent MAC a 5-day notice of termination letter under § 11.3 of the general conditions asserting MAC failed “to prosecute the Work with the necessary force or in a timely manner” and requested a “recovery plan” within 15 days. (Ex. 40). The University also requested that MAC and Fidelity meet with it and representatives from Thomarios and Stantec on December 22, 2015. {¶5} At the December 22, 2015 meeting, MAC provided a recovery schedule but did not provide a recovery plan. MAC has asserted that it could not provide a recovery plan due to the failure of the University, Stantec, and/or Thomarios to provide responses to requests for information (RFIs) and/or to approve construction change directives (CCDs). Mr. Trinetti presented at the meeting a copy of Zook Hall’s floor plan on which he circled areas of the building where outstanding RFIs and/or CCDs, requiring responses from Stantec and/or Thomarios, hindered MAC’s work. Stantec informed MAC at the December 22, 2015 meeting that it would be closed from December 22, 2015 to January 4, 2016. Despite this fact, the University wrote MAC a letter the next day in which it granted MAC an extension to provide the recovery plan until December 30, 2015 and indicated “[t]he University is tasking [Stantec] to respond to” several outstanding RFIs. (Ex. 42). {¶6} On January 7, 2016, the University issued a Notice of Termination (Ex. C) to MAC via email and made demand on Fidelity to complete the contract. MAC did not receive an original signed Notice of Termination until January 13, 2016, four business days later. On or around January 11, 2016, the University refused to allow MAC’s subcontractors to work on the project. On this same day, the University sent a letter to MAC informing it that subcontractors should cease work or risk not being paid. (Ex. 61). MAC requested $1.2 million in its pay application for work prior to its termination. (Ex. 261). Case No. 2016-00685JD -4- DECISION

{¶7} Fidelity agreed to complete the project and entered into a second contract with the University (the takeover agreement) (Ex. 8). The takeover agreement was provided to the University on or around January 13, 2016 but the University did not execute it until February 25, 2016, during which time the project was down per Mr. Brkich’s testimony. The takeover agreement did not modify the original completion date of February 10, 2016. Fidelity appointed MAC as the replacement contractor based on completion status, time constraints, and the recommendation of a construction consultant. Fidelity estimated the project was 85% complete at the time of termination. {¶8} The University indicated that contract funds would be released, upon the takeover agreement’s execution, which obligated the University to remit the contract balance to Fidelity. (Ex. 8, § 5; 8). On March 15, 2016, the University sent a letter to MAC indicating it would not be paying MAC’s recent payment applications based on MAC’s termination for cause. MAC left the job site on May 27, 2016 and projected six items that needed to be completed. (Ex. 186). The project was not completed until August 16, 2016, a delay of 188 days from its original planned completion date. The project’s 81-page punch list, prepared by Stantec, reflects numerous unfinished items and areas of construction within MAC’s scope of work but does not differentiate between MAC’s work and the work completed by other contractors after MAC left the job site on May 27, 2016. (Ex. GGG). Mr. Trinetti offered unrebutted testimony that the University never provided the punch list to MAC prior to the filing of this case. The University withheld approximately $2 million from MAC and currently holds the $1.2 million in contract balance funds in an escrow account. {¶9} Mr. Dennis Walsh testified regarding Fidelity’s assignment of its claims to MAC. As this testimony is not in dispute and the University offered no evidence to rebut it, the Court finds that Fidelity assigned its rights under the takeover agreement to MAC and, therefore, MAC has the right to pursue claims and collect under both the original contract and takeover agreement. Case No. 2016-00685JD -5- DECISION

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Arbino v. Johnson & Johnson
2007 Ohio 6948 (Ohio Supreme Court, 2007)
Boone Coleman Construction, Inc. v. Village of Piketon
2016 Ohio 628 (Ohio Supreme Court, 2016)
Jacob & Youngs, Inc. v. Kent
129 N.E. 889 (New York Court of Appeals, 1921)
National Pumps Corp. v. American Pumps, Inc.
32 N.E.2d 422 (Ohio Court of Appeals, 1940)
Rhodes v. Rhodes Industries, Inc.
595 N.E.2d 441 (Ohio Court of Appeals, 1991)
Kersh v. Montgomery Developmental Center
519 N.E.2d 665 (Ohio Court of Appeals, 1987)
Geygan v. Queen City Grain Co.
593 N.E.2d 328 (Ohio Court of Appeals, 1991)
State v. Brand
442 N.E.2d 805 (Ohio Court of Appeals, 1981)
National Pumps Corp. v. American Pumps, Inc.
34 N.E.2d 775 (Ohio Supreme Court, 1941)

Cite This Page — Counsel Stack

Bluebook (online)
2018 Ohio 4513, Counsel Stack Legal Research, https://law.counselstack.com/opinion/mid-am-constr-llc-v-univ-of-akron-ohioctcl-2018.