Huddleston Concrete Co. v. Safeco Insurance Co. of America

368 S.E.2d 117, 186 Ga. App. 531, 1988 Ga. App. LEXIS 404
CourtCourt of Appeals of Georgia
DecidedFebruary 24, 1988
Docket75748
StatusPublished
Cited by8 cases

This text of 368 S.E.2d 117 (Huddleston Concrete Co. v. Safeco Insurance Co. of America) is published on Counsel Stack Legal Research, covering Court of Appeals of Georgia primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Huddleston Concrete Co. v. Safeco Insurance Co. of America, 368 S.E.2d 117, 186 Ga. App. 531, 1988 Ga. App. LEXIS 404 (Ga. Ct. App. 1988).

Opinion

Birdsong, Chief Judge.

This is a suit by a materialman (Huddleston Concrete Co.) against the bond of the contractor (Williams Bridge Co., Inc.) filed after the subcontractor (Coastal Bridge Co.) defaulted with $34,078.61 left owing to Huddleston. The trial court granted summary judgment to the appellee bonding company (Safeco) on the basis that under OCGA § 36-82-104 (b) Huddleston was required to, but did not, give written notice of its claim to the contractor within 90 days from the last delivery. The trial court held that the evidence of both parties clearly shows the contractor “did not . . . assume Coastal Bridge’s *532 contract obligations,” and that Huddleston had no “direct contractual relationship, express or implied,” with the contractor, so as to excuse notice.

In support of its case Huddleston presents the affidavit of its officer, Raven, who states under oath that the contractor first approached Huddleston to supply concrete to the contractor for its work on the 1-675 project, whereupon Huddleston (apparently) quoted a price to the contractor. The contractor then asked Huddleston to supply concrete at the same rate to a subcontractor doing a portion of the contractor’s work. Huddleston made a delivery to the subcontractor, Coastal Bridge, before it made a delivery to the contractor. Deliveries continued apace, with Williams Bridge paying for all the deliveries to it; Huddleston billed the subcontractor separately.

Ultimately Mike Williams, the principal of the contractor, met with Huddleston’s officer Raven in Williams’ home and told Raven that the subcontractor was about to declare bankruptcy. Raven told Williams that Huddleston had not been paid by the subcontractor for $34,078.61 in materials. Raven then told Williams that if the subcontractor was going to declare bankruptcy, Huddleston needed to notify the contractor’s bonding company of the debt. Williams told Raven that he (Williams) had already by letter notified the bonding company of the debt. Thereafter Huddleston’s officer, in a telephone conversation with Williams, learned of a written assignment to the contractor of retainage due the subcontractor, for the payment of six creditors including Huddleston. Raven states that “[b]ased on Williams’ assurances to Affiant that Williams Bridge would pay Coastal’s debt of $34,078.61 to Huddleston out of retainage after the project was complete, Affiant did not pursue a claim to the bonding company.” Thereafter, Huddleston continued to deliver concrete to the contractor and was paid for those deliveries. Naturally, Huddleston did not receive payment out of the retainage for its deliveries to the subcontractor. Hence the parties find themselves in court, with the surety contesting the claim on grounds of no notice, pursuant to OCGA § 36-82-104. Held:

1. One thing must be settled first. The parties and the trial court have repeatedly referred to the statutory requirement as being that one with no “direct contractual relationship” with the contractor must give notice. Some federal cases interpreting the parallel Miller Act, 40 USCA § 270 (b), and a chief Georgia case also refer to this necessity of the supplier to prove a direct contractual relationship with the contractor in order to dispense with notice. Porter-Lite Corp. v. Warren Scott Contracting Co., 126 Ga. App. 436, 438 (2) (191 SE2d 95); see United States v. Hesselden Constr. Co., 404 F2d 774 (10th Cir. 1968). This is not what the statute says. It says: “(b) Every person entitled to the protection of the payment bond . . . *533 shall have the right to bring an action on such payment bond . . . provided, however, that any person having direct contractual relationship with a subcontractor, but no contractual relationship express or implied with the contractor furnishing such payment bond, shall have the right of action upon the payment bond upon giving written notice to the contractor within 90 days from the day [of the last delivery]. . . .” (Emphasis supplied.)

Therefore, it is clear that the statute does not, as the surety repeatedly contends and as the trial court held, require the appellant to prove a direct contractual relationship with the contractor in order to dispense with notice. The distinction is obvious.

The 90-day notice requirement protects the contractor by fixing the date beyond which he will not be liable for subcontractor debts; but this object is “subsidiary” to the main purpose of the whole act, which is to protect the materialmen. Noland Co. v. Allied Contractors, 273 F2d 917, 920-921 (4th Cir. 1959). See also American Cas. Co. v. Southern Materials Co., 261 F2d 197, 200 (4th Cir. 1958). Therefore, any ambiguity in the act should be resolved in support of the main object of the whole law, which is to protect materialmen. Noland Co., supra at 921.

Moreover, the Georgia act giving materialmen the right to sue on the contractor’s bond on public works projects, is a remedial law and therefore is to be liberally construed to secure that object. See United States v. James Stewart Co., 195 FSupp. 715, 716 (1961); United States ex rel. Hargis v. Md. Cas. Co., 64 FSupp. 522, 526 (1946); Carey v. Giles, 9 Ga. 253. To put a finer point on it, this “liberal construction” has also been interpreted to mean that in construing a remedial statute, limitations which would take away the right from one to whom the statute gave it, must be express and not subject to varying interpretations. Pullen v. Otis Elevator Co., 292 FSupp. 715 (1968). This means that the appellant’s right to maintain an action on the bond in this case will not be governed by a greater or different limitation than the statute expressly provides. No more should be en-grafted onto the term “[implied] contractual relationship” than is clearly said.

The purpose of the notice requirement is to protect the contractor, so that he may with impunity pay subcontractors if no notice of claims by materialmen and suppliers has been filed. United States v. James Stewart Co., supra. Therefore, at the very least, whatever it means, the precise language of the statute indicates in policy that if in the circumstances of the case the materialman has such a relationship with the contractor that the contractor is bound to know of the claim, or especially bound to pay it, the 90-day notice is not required. In interpreting the same requirement in the Miller Act, the federal court in United States v. James Stewart Co., supra, considered it sig *534 nificant that a course of dealing among contractor, subcontractor and materialman provided the contractor with “more notice of the claim than it would have had if [the materialman] had merely complied with the notice provisions of the Miller Act,” and that if the material-men did. not give notice, nevertheless, the contractor was not prejudiced.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Gerhold Concrete Co. v. St. Paul Fire & Marine Insurance Co.
695 N.W.2d 665 (Nebraska Supreme Court, 2005)
Southern Electric Supply Co. v. Trend Construction, Inc.
578 S.E.2d 279 (Court of Appeals of Georgia, 2003)
J. Kinson Cook, Inc. v. Weaver
556 S.E.2d 831 (Court of Appeals of Georgia, 2001)
Osborne Bonding & Surety Co. v. State
481 S.E.2d 578 (Court of Appeals of Georgia, 1997)
Quiktrip Corp. v. Childs
469 S.E.2d 763 (Court of Appeals of Georgia, 1996)
Devore & Johnson, Inc. v. Bowen & Watson, Inc.
453 S.E.2d 67 (Court of Appeals of Georgia, 1994)
J & a PIPELINE CO. v. DeKalb County
430 S.E.2d 13 (Court of Appeals of Georgia, 1993)
Atlantic Sea-Con. Ltd. v. Robert Dann Co.
560 A.2d 592 (Court of Special Appeals of Maryland, 1989)

Cite This Page — Counsel Stack

Bluebook (online)
368 S.E.2d 117, 186 Ga. App. 531, 1988 Ga. App. LEXIS 404, Counsel Stack Legal Research, https://law.counselstack.com/opinion/huddleston-concrete-co-v-safeco-insurance-co-of-america-gactapp-1988.