Southern Electric Supply Co. v. Trend Construction, Inc.

578 S.E.2d 279, 259 Ga. App. 666, 2003 Ga. App. LEXIS 232
CourtCourt of Appeals of Georgia
DecidedFebruary 14, 2003
DocketA02A1722
StatusPublished
Cited by4 cases

This text of 578 S.E.2d 279 (Southern Electric Supply Co. v. Trend Construction, Inc.) is published on Counsel Stack Legal Research, covering Court of Appeals of Georgia primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Southern Electric Supply Co. v. Trend Construction, Inc., 578 S.E.2d 279, 259 Ga. App. 666, 2003 Ga. App. LEXIS 232 (Ga. Ct. App. 2003).

Opinion

Andrews, Presiding Judge.

The issues in this appeal are whether a supply company that provided electrical equipment to a subcontractor engaged in a public works project gave sufficient notice of its claim under a payment bond obtained by the general contractor under Georgia’s Little Miller Act, and whether suit against the contractor was timely filed. The trial court found that Southern Electric Supply Company (Southern) *667 failed to provide proper written notice of its claim to Trend Construction, Inc. (Trend) as required by that Act. The court also found that Southern’s lawsuit was time-barred because Southern did not file suit within one year of June 1999, when' “the Project was substantially complete and had been accepted.”

Southern challenges both findings, arguing that the trial court misconstrued the law and overlooked certain facts. We agree and reverse.

Trend was the general contractor on the Georgia Perimeter College Testing Center and Computer Training Center project which involved certain renovations to a testing lab and a lecture hall in an existing building for a. contract price of $445,600. Before beginning work, Trend obtained performance and payment bonds from Fidelity & Guaranty Insurance Company. The payment bond afforded protection to persons not fully paid for materials or equipment furnished or supplied to the project.

During the project, Trend subcontracted with Georgia Electrical Contractors, Inc. (GEC) to provide labor and materials. GEC purchased all of its electrical supplies from Southern on an open account, but failed to pay Southern for those supplies. Unable to obtain payment from GEC, Southern sued Trend and United States Fidelity & Guaranty Company (USF&G), the surety on the payment bond. Southern claimed that GEC owed $34,843.33 plus interest, for electrical supplies that GEC obtained from Southern and used in the Perimeter College project. 1

Both Trend and Southern filed motions for summary judgment. The trial court granted Trend’s motion, finding that Southern did not give Trend sufficient notice of its claim and also that Southern’s suit was barred by the one-year statute of limitation. This appeal followed.

1. Southern contends the trial court erred as a matter of law and fact in finding that the notice provisions of the.Georgia Little Miller Act, former OCGA § 36-82-104 (b) (1), were not met. 2 The trial court held that nothing in the faxed invoices could be construed as implying a demand on Trend for payment and also held that the written demand for payment could not be satisfied by sending a fax.

*668 In considering the grant of a motion for summary judgment, this Court conducts a de novo review to determine whether the trial court correctly found the absence of material issues of fact. Moore v. Food Assoc., 210 Ga. App. 780, 781 (437 SE2d 832) (1993). In conducting this review, we consider the evidence and all reasonable inferences therefrom in the light most favorable to the nonmovant. Davis v. Rich’s Dept. Stores, 248 Ga. App. 116 (545 SE2d 661) (2001).

As a condition precedent for recovery under a payment bond, former OCGA § 36-82-104 (b) (1) required a supplier to give “written notice to the contractor within 90 days from the day on which such person . . . furnished the last of the material ... for which such claim is made, stating with substantial accuracy the amount claimed and the name of the party to whom the material was furnished or supplied.” Courts have added an additional requirement to the statute; namely, that the writing must inform the prime contractor, expressly or by implication, that the supplier is looking to the contractor for payment of the subcontractor’s bill. See, e.g., Amcon, Inc. v. Southern Pipe &c. Co., 134 Ga. App. 655, 657 (215 SE2d 712) (1975).

The purpose of providing sufficient notice of a claim is “to place the general contractor and its bondsman in a position to protect themselves.” Amcon, supra. Even so, “the Georgia act giving materialmen the right to sue on the contractor’s bond on public works projects, is a remedial law and therefore is to be liberally construed to secure that object.” Huddleston Concrete Co. v. Safeco Ins. Co. &c., 186 Ga. App. 531, 533 (1) (368 SE2d 117) (1988).

Southern submitted evidence that on or about March 27, 1999, Southern’s district credit manager, Paul Hunt, called Ed Davis, the president of Trend and told him about GEC’s failure to pay its account with Southern. Hunt testified that “[t]he purpose of my discussions with Mr. Davis was to inform him that Georgia Electrical owed Southern $34,843.33 in electrical materials supplied to the Project, and that Georgia Electrical had never paid any amount to Southern for these materials.” According to Hunt, he called Davis “to see that the outstanding invoices relating to the Project were paid.” Hunt further testified, “I requested that Mr. Davis assist me in seeing that these outstanding amounts were paid. I also conveyed to Mr. Davis that if Georgia Electrical did not pay these amounts, then Southern would look to Trend to pay these amounts.”

On March 27, Hunt faxed Davis a copy of the “Statement of Account on Perimeter College Project” for “Georgia Electrical Contr.,” . and enclosed three pages of invoices. The last page of the statement faxed to Trend shows that as of March 25, 1999, GEC owed $35,366.26 to Southern.

Davis confirmed that “[o]n or about March 27, 1999 I received a *669 telephone call from Paul Hunt, a representative of Southern Electric regarding invoices payable by Georgia Electrical.” Davis added, “Mr. Hunt told me that Georgia Electrical owed Southern Electric on various invoices.” Davis stated that Trend never received any demand for payment from Southern, either orally or in writing.

Turner, GEC’s president, testified that he received a letter from Davis dated March 29, 1999, where Davis advised Turner as follows:

As you are aware from our telephone conversation today, we' are very concerned about your firm completing the above project. You assured me that you wanted to complete the project and would provide sufficient personnel to complete the remaining electrical work on this project. I also advised you we would not issue any further payments on this project to Georgia Electrical Contractors, Inc. until project is complete. We will schedule payments to Southern Electrical Supply Co. by joint check after all material has been purchased to complete this project. We have talked with your electrical supplier Southern Electric Supply Co., Mr. Paul Hunt, who advised me Georgia Electrical Contractors would not be extended any additional credit. Southern Electric Supply is also holding the dimmer panel, which we need, and will not release until payment of $8,000.00 is received. Mr. Hunt agreed to release the panel if Trend Construction, Inc. would issue a joint check.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Consolidated Pipe & Supply Co. v. Genoa Construction Services, Inc.
690 S.E.2d 894 (Court of Appeals of Georgia, 2010)
Southway Crane & Rigging, Inc. v. Federal Insurance Co.
669 S.E.2d 482 (Court of Appeals of Georgia, 2008)
Mock v. Kroger Co.
598 S.E.2d 789 (Court of Appeals of Georgia, 2004)

Cite This Page — Counsel Stack

Bluebook (online)
578 S.E.2d 279, 259 Ga. App. 666, 2003 Ga. App. LEXIS 232, Counsel Stack Legal Research, https://law.counselstack.com/opinion/southern-electric-supply-co-v-trend-construction-inc-gactapp-2003.