Consolidated Pipe & Supply Co. v. Genoa Construction Services, Inc.

690 S.E.2d 894, 302 Ga. App. 255, 2010 Fulton County D. Rep. 410, 2010 Ga. App. LEXIS 104
CourtCourt of Appeals of Georgia
DecidedFebruary 10, 2010
DocketA09A2017
StatusPublished
Cited by1 cases

This text of 690 S.E.2d 894 (Consolidated Pipe & Supply Co. v. Genoa Construction Services, Inc.) is published on Counsel Stack Legal Research, covering Court of Appeals of Georgia primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Consolidated Pipe & Supply Co. v. Genoa Construction Services, Inc., 690 S.E.2d 894, 302 Ga. App. 255, 2010 Fulton County D. Rep. 410, 2010 Ga. App. LEXIS 104 (Ga. Ct. App. 2010).

Opinion

Phipps, Judge.

Consolidated Pipe & Supply Company, Inc. sued Genoa Construction Services, Inc. and Westfield Insurance Company to recover under a payment bond and a lien discharge bond for monies allegedly owed it for materials it supplied to a construction project. The trial court granted summary judgment to Genoa and Westfield. Consolidated appeals, but has shown no error. We affirm.

To prevail at summary judgment, the moving party must demonstrate that there is no genuine issue of material fact and that the undisputed facts, viewed in the nonmovant’s favor, warrant judgment as a matter of law. 1 We review de novo a trial court’s grant of summary judgment, construing the evidence in a light most favorable to the nonmoving party. 2

So construed, the record showed that St. James United Methodist Church, Inc. hired Genoa to act as the general contractor of a construction project. Subsequently, in October 2003, Genoa contracted with Red-Hawk Construction, LLC to perform project work.

Red-Hawk ordered and received construction materials from Consolidated for use on the project, but Red-Hawk filed for bankruptcy and never paid Consolidated for the materials. Consolidated filed a claim of lien on the project in the unpaid amount.

Westfield, as surety for Genoa, issued a payment bond for the project, as well as a mechanic’s lien release bond to discharge Consolidated’s claim of lien. Consolidated demanded payment from Genoa, as general contractor, and from Westfield, as surety for Genoa. Genoa and Westfield failed to pay the demand, and Consolidated filed suit.

This case was previously before this court. 3 On review then was the trial court’s conclusion that Genoa and Westfield were entitled to judgment on the pleadings on the grounds that Consolidated’s Notice to Contractor was deficient in light of OCGA §§ 10-7-31 (a) and 44-14-361.5 (c). 4 We did not reach the substantive question of the argued insufficiency. 5 Instead, we noted that OCGA §§ 10-7-31 and 44-14-361.5 each imposed a separate duty on the contractor to file a *256 Notice of Commencement with the superior court and that a contractor’s failure to file the Notice of Commencement renders the notice-to-contractor requirements inapplicable. 6 We recognized that “if Consolidated could prove a fatal defect in Genoa’s notice of commencement, then any defect in Consolidated’s notice to the contractor would not bar relief under the complaint.” 7 Because the pleadings, construed in favor of Consolidated, 8 did not show that Consolidated would have been unable to establish a defect in the Notice of Commencement, we reversed the judgment on the pleadings and remanded the case. 9

On remand, after a period of discovery, Genoa and Westfield moved for summary judgment on the same grounds asserted in their prior motions — that Consolidated’s Notice to Contractor was deficient in light of OCGA §§ 10-7-31 (a) and 44-14-361.5 (c). Consolidated did not pursue any claim that the Notice of Commencement was defective, acknowledging instead that whether it had given a proper Notice to Contractor was a genuine issue of material fact. At issue in this appeal by Consolidated is whether the trial court erred in granting Genoa’s and Westfield’s motions for summary judgment on those grounds.

OCGA § 10-7-31 (a) requires persons entitled to claim the protection of a payment bond, who do not otherwise have a contractual relationship with the contractor furnishing the payment bond, to give to the contractor a written Notice to Contractor in accordance with the statute’s provisions. Otherwise, such persons “shall not have the right to bring an action on such payment bond ... in accordance with the terms thereof.” 10 Similarly, OCGA § 44-14-361.5 provides that in order “[t]o make good” specified liens, persons having a right to the lien but who do not have privity of contract with the contractor “shall. . . give a written Notice to Contractor as set out in subsection (c) of this Code section.”

Claiming entitlement to summary judgment, Genoa and West-field argued that Consolidated’s Notice to Contractor failed to include certain information specified by OCGA §§ 10-7-31 (a) and 44-14-361.5 (c). Among other things, they pointed out that both Code provisions required that the Notice to Contractor set forth: “[t]he *257 name and address of each person at whose instance the . . . materials] are being furnished.” 11 Although Consolidated’s Notice to Contractor set forth the entity’s name as “Red-Hawk Construction, LLC,” the notice failed to provide any address for that entity. Genoa and Westfield also pointed out that both OCGA §§ 10-7-31 (a) and 44-14-361.5 (c) required that the Notice to Contractor set forth: the name “and location of the project set forth” in the Notice of Commencement. 12 Although Consolidated’s Notice to Contractor set forth the name of the project as “St. James United Methodist Church,” the notice failed to state the location of the construction project.

Consolidated maintains that, notwithstanding these omissions, its Notice to Contractor substantially complied with the statutory provisions. Furthermore, it maintains that the omissions from its Notice to Contractor were immaterial because the contractor knew the location of its construction project for St. James United Methodist Church and there was no evidence that the contractor had any other construction project for that entity. Consolidated also points to evidence that the contractor knew that a “Red-Hawk, LLC” was working on that construction project and evidence that the contractor had an address for a company using that name.

We reject Consolidated’s argument that its Notice to Contractor was in substantial compliance with the statutory provisions. In enacting OCGA §§ 10-7-31

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Great West Casualty Co. v. Bloomfield
693 S.E.2d 99 (Court of Appeals of Georgia, 2010)

Cite This Page — Counsel Stack

Bluebook (online)
690 S.E.2d 894, 302 Ga. App. 255, 2010 Fulton County D. Rep. 410, 2010 Ga. App. LEXIS 104, Counsel Stack Legal Research, https://law.counselstack.com/opinion/consolidated-pipe-supply-co-v-genoa-construction-services-inc-gactapp-2010.