Consolidated Pipe & Supply Co. v. Genoa Construction Services, Inc.

633 S.E.2d 59, 279 Ga. App. 894, 2006 Fulton County D. Rep. 1995, 2006 Ga. App. LEXIS 731
CourtCourt of Appeals of Georgia
DecidedJune 19, 2006
DocketA06A0131
StatusPublished
Cited by8 cases

This text of 633 S.E.2d 59 (Consolidated Pipe & Supply Co. v. Genoa Construction Services, Inc.) is published on Counsel Stack Legal Research, covering Court of Appeals of Georgia primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Consolidated Pipe & Supply Co. v. Genoa Construction Services, Inc., 633 S.E.2d 59, 279 Ga. App. 894, 2006 Fulton County D. Rep. 1995, 2006 Ga. App. LEXIS 731 (Ga. Ct. App. 2006).

Opinion

Miller, Judge.

Consolidated Pipe & Supply Company, Inc. (“Consolidated”) sued Genoa Construction Services, Inc. (“Genoa”) and Westfield Insurance Company (“Westfield”) to recover under a payment bond for materials allegedly supplied by Consolidated for a construction project. The trial court granted judgment on the pleadings to Genoa and Westfield. OCGA§ 9-11-12 (c). Consolidated appeals. Since Genoa *895 and Westfield have failed to show that Consolidated would not be entitled to any relief based on the well-pled allegations in the complaint that could be proved in support of its claim, we reverse.

In deciding a motion for judgment on the pleadings, the issue is whether the undisputed facts appearing from the pleadings entitle the movant to judgment as a matter of law. All well-pleaded material allegations by the nonmovant are taken as true, and all denials by the movant are taken as false. But the trial court need not adopt a party’s legal conclusions based on these facts.

(Citations and punctuation omitted.) Holsapple v. Smith, 267 Ga. App. 17, 20 (1) (599 SE2d 28) (2004). Our review is de novo. Bogard v. Inter-State Assurance Co., 263 Ga. App. 767 (589 SE2d 317) (2003).

So viewed, the pleadings show that St. James United Methodist Church, Inc. engaged Genoa to act as the general contractor of a construction project. Westfield, as surety for Genoa, issued a payment bond for the project. Genoa subsequently contracted with Red Hawk Construction, LLC (“Red Hawk”) to perform project work.

Red Hawk ordered and received $109,654.22 of construction materials from Consolidated for use on the project, but Red Hawk filed for bankruptcy and never paid Consolidated for the materials. Consolidated filed a claim of lien on the project in the amount of $109,654.22, plus interest, and demanded payment from Genoa, as general contractor, and Westfield, as surety for Genoa. Genoa and Westfield failed to pay the demand, and Consolidated filed this action to recover under the payment bond.

At issue is whether the pleadings establish that Consolidated failed to comply with OCGA §§ 10-7-31 and 44-14-361.5. OCGA § 10-7-31 (a) requires that persons entitled to claim the protection of a payment bond who do not otherwise have a contractual relationship with the contractor furnishing the payment bond must deliver a notice to the contractor in accordance with the statute’s provisions. Otherwise, such persons “shall not have the right to bring an action on such payment bond ... in accordance with the terms thereof.” Id. Similarly, OCGA § 44-14-361.5 (a) provides that in order to make good certain liens under OCGA § 44-14-361, persons having a right to the lien but not otherwise in privity of contract with the contractor must provide a notice to the contractor in accordance with the statute.

The trial court concluded that Genoa and Westfield were entitled to judgment on the pleadings because Consolidated’s notice to the contractor failed to include Red Hawk’s address, which the trial court *896 found to be required in light of OCGA §§ 10-7-31 (a) (2) and 44-14-86!.5 (c) (2). 1 OCGA§§ 10-7-31 and 44-14-361.5, however, impose a separate duty on the contractor to file a “notice of commencement” with the superior court in which the project is located, and a contractor’s failure to file the notice of commencement renders the notice-to-contractor requirements inapplicable. OCGA§§ 10-7-31 (c); 44-14-361.5 (d). Accordingly, if Consolidated could prove a fatal defect in Genoa’s notice of commencement, then any defect in Consolidated’s notice to the contractor would not bar relief under the complaint. “A defendant’s motion for judgment on the pleadings should be granted only where the pleadings disclose with certainty that the plaintiff would not be entitled to relief under any state of provable facts.” Blier v. Greene, 263 Ga. App. 35 (587 SE2d 190) (2003).

The pleadings do not show that Consolidated was unable to establish a defect in the notice of commencement. Genoa averred in its first affirmative defense that it had filed a notice of commencement with the Clerk of the Superior Court of Fulton County and had posted the notice of commencement at the project site. Such an averment, however, must be considered to be denied by Consolidated for purposes of a motion for judgment on the pleadings. See OCGA § 9-11-8 (d) (“[a]verments in a pleading to which no responsive pleading is required... shall be taken as denied or avoided”); Lord v. Smith, 143 Ga. App. 378, 379 (1) (238 SE2d 731) (1977) (although answer alleged facts that if well founded would be grounds for dismissal, judgment on the pleadings was not warranted).

Furthermore, Consolidated’s pleadings must be construed in a light most favorable to showing a question of fact. See Auerback v. Maslia, 142 Ga. App. 184, 185 (2) (235 SE2d 594) (1977). Accordingly, we do not consider Consolidated’s averments that its “Notice to Owner/Contractor” complied with OCGA §§ 10-7-31 and 44-14-361.5 or admission that it received a copy of the notice of commencement to establish that Genoa’s notice of commencement was otherwise proper and timely filed as required by the statutes. Since the pleadings do not disclose with certainty that Consolidated would not be entitled to relief, Genoa and Westfield were not entitled to judgment on the pleadings.

Judgment reversed.

Johnson, P. J., concurs. Ellington, J., concurs in judgment only. *897 Decided June 19, 2006. Vaughn, Wright & Boyer, Frederick L. Wright II, for appellant. Griffin, Cochrane & Marshall, W. Henry Parkman, Peter H. Strott, for appellees.
1

Consolidated attached a copy of its notice to contractor as an exhibit to the complaint. Accordingly, the trial court was entitled to consider this exhibit in considering a judgment on the pleadings. Tidikis v. Network for Med. &c. Research,

Free access — add to your briefcase to read the full text and ask questions with AI

Related

The Cline Drive Land Trust v. Wells Fargo Bank, N.A.
793 S.E.2d 550 (Court of Appeals of Georgia, 2016)
Capitol Materials, Inc. v. JLB Buckhead, LLC
789 S.E.2d 803 (Court of Appeals of Georgia, 2016)
Consolidated Pipe & Supply Co. v. Genoa Construction Services, Inc.
690 S.E.2d 894 (Court of Appeals of Georgia, 2010)
Perry Golf Course Development, LLC v. HOUS. AUTH. OF CITY OF ATLANTA
670 S.E.2d 171 (Court of Appeals of Georgia, 2008)
Beacon Medical Products, LLC v. Travelers Casualty & Surety Co. of America
665 S.E.2d 710 (Court of Appeals of Georgia, 2008)
General Electric Co. v. North Point Ministries, Inc.
657 S.E.2d 297 (Court of Appeals of Georgia, 2008)
Sierra Craft, Inc. v. T. D. Farrell Construction, Inc.
638 S.E.2d 815 (Court of Appeals of Georgia, 2006)

Cite This Page — Counsel Stack

Bluebook (online)
633 S.E.2d 59, 279 Ga. App. 894, 2006 Fulton County D. Rep. 1995, 2006 Ga. App. LEXIS 731, Counsel Stack Legal Research, https://law.counselstack.com/opinion/consolidated-pipe-supply-co-v-genoa-construction-services-inc-gactapp-2006.