General Electric Co. v. North Point Ministries, Inc.

657 S.E.2d 297, 289 Ga. App. 382, 2008 Fulton County D. Rep. 314, 2008 Ga. App. LEXIS 94
CourtCourt of Appeals of Georgia
DecidedJanuary 29, 2008
DocketA07A2161
StatusPublished
Cited by10 cases

This text of 657 S.E.2d 297 (General Electric Co. v. North Point Ministries, Inc.) is published on Counsel Stack Legal Research, covering Court of Appeals of Georgia primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
General Electric Co. v. North Point Ministries, Inc., 657 S.E.2d 297, 289 Ga. App. 382, 2008 Fulton County D. Rep. 314, 2008 Ga. App. LEXIS 94 (Ga. Ct. App. 2008).

Opinion

MlKELL, Judge.

General Electric Company d/b/a GE Consumer & Industrial Products, a Division of General Electric Company (“GE”), sued North Point Ministries, Inc. (“NPMI”) to foreclose on a materialman’s lien. The trial court granted summary judgment to NPMI, ruling that GE’s lien was unenforceable due to GE’s failure to provide a Notice to *383 Contractor. GE appeals on the grounds that it was not required to provide a Notice to Contractor, because the Notice of Commencement filed by NPMI’s contractor was fatally defective. We agree and reverse.

As this Court has previously noted, there exists in Georgia “a detailed statutory scheme for regulating liens filed by materialmen who furnish supplies and materials for building, repairing, or improving property.” 1 Under this statutory scheme, a materialman must comply with the provisions of OCGA § 44-14-361.1 (a) in order to “make good” his lien. 2 In addition, OCGA§ 44-14-361.5 (a) provides that in cases where the contractor has filed a proper Notice of Commencement, 3 a lien claimant “who does not have privity of contract with the contractor” must provide a Notice to Contractor or forfeit his lien. 4 The contractor’s Notice of Commencement must contain the information required in OCGA § 44-14-361.5 (b), including the “legal description” of the property where the construction project is located, and the name of the “true owner of the property.” 5 Further, the Notice of Commencement must be filed with the clerk of the superior court of the county in which the construction project is located; 6 and the clerk of the superior court is then directed to file the Notice in its records and to index “[e]ach such Notice of Commencement . . . under the name of the true owner and the contractor as contained in the Notice of Commencement.” 7 Failure to file a Notice of Commencement renders the provisions of OCGA § 44-14-361.5 inapplicable, 8 so that the lien claimant does not have to provide a Notice to Contractor in order to preserve his lien. 9 Moreover, under *384 Consolidated, Pipe & Supply Co., 10 the lien claimant would also be relieved of the duty to provide a Notice to Contractor in the event the contractor files a Notice of Commencement which proves to contain a “fatal defect.”* 11

In the case at bar, we must determine whether the Notice of Commencement filed by NPMI’s contractor sufficiently complied with OCGA § 44-14-361.5 (b) so as to trigger the application of that Code section in this case. We conclude that it did not.

The facts in this case are not in dispute. Viewing the evidence and all reasonable inferences and conclusions drawn from it in the light most favorable to the nonmoving party, as we must on review of a grant of summary judgment, 12 the record reflects that on May 18, 2005, Garrard Construction Interiors, LLC (“Garrard”), entered into a contract to provide improvements to a church facility in Alpharetta (the “project”). Garrard provided a Notice of Commencement for the project on June 16,2005, in purported compliance with subsection (b) of OCGA § 44-14-361.5.

Garrard subcontracted with Miller Electric, LLP (“Miller”), for electrical work on the project. In connection with this work, Miller ordered supplies from GE but never paid GE. GE did not provide a written Notice to Contractor. After filing a timely claim of lien against NPMI’s property, GE filed the underlying action against NPMI, the property owner. 13 The trial court granted summary judgment to NPMI on the grounds that GE’s materialman’s lien was unenforceable because GE failed to provide a Notice to Contractor as contemplated by OCGA § 44-14-361.5 (a) for lien claimants not in privity of contract with the contractor. In its sole enumeration of error, GE contends that the trial court erred in determining that its lien was unenforceable for this reason. We agree.

Garrard’s Notice of Commencement deviated in two essential ways from the requirements of OCGA § 44-14-361.5 (b). First, it described the property on which the project was located by street address only, without supplying the legal description required under OCGA § 44-14-361.5 (b) (2). Second, it listed “North Point Community Church” as the owner, rather than NPMI, the actual owner of the property. Thus, the Notice of Commencement failed to name the “true *385 owner” of the property, as required by OCGA § 44-14-361.5 (b) (3). Garrard’s Notice of Commencement was therefore fatally deficient. To be sure, “generally speaking, when there is actual compliance as to all matters of substance[,] then mere technicalities of form or variations in the mode of expression should not be given the stature of noncompliance.” 14 But the requirement to furnish a legal description of the property and the name of the true owner are matters of substance, “not mere technicalities.” 15 Providing merely the property’s street address and an “a/k/a” name for the owner amounted to neither actual nor substantial compliance with the provisions of the statute. Either of these defects on the face of Garrard’s Notice of Commencement would render the Notice insufficient to trigger the provisions of OCGA § 44-14-361.5, so that GE was relieved of the obligation to provide a Notice to Contractor in order to preserve its lien. 16

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Capitol Materials, Inc. v. JLB Buckhead, LLC
789 S.E.2d 803 (Court of Appeals of Georgia, 2016)
Fidelity & Deposit Co. of Maryland v. Lafarge Building Materials, Inc.
720 S.E.2d 288 (Court of Appeals of Georgia, 2011)
Southeast Culvert, Inc. v. Hardin Bros., LLC
718 S.E.2d 28 (Court of Appeals of Georgia, 2011)
Madison Retail Suwanee, LLC v. Orion Enterprises Sales & Service, Inc.
711 S.E.2d 71 (Court of Appeals of Georgia, 2011)
Consolidated Pipe & Supply Co. v. Genoa Construction Services, Inc.
690 S.E.2d 894 (Court of Appeals of Georgia, 2010)
Rey Coliman Contractors, Inc. v. PCL Construction Services, Inc.
676 S.E.2d 298 (Court of Appeals of Georgia, 2009)
Bollers v. Noir Enterprises, Inc.
677 S.E.2d 338 (Court of Appeals of Georgia, 2009)
Beacon Medical Products, LLC v. Travelers Casualty & Surety Co. of America
665 S.E.2d 710 (Court of Appeals of Georgia, 2008)
Harris Ventures, Inc. v. Mallory and Evans, Inc.
662 S.E.2d 874 (Court of Appeals of Georgia, 2008)

Cite This Page — Counsel Stack

Bluebook (online)
657 S.E.2d 297, 289 Ga. App. 382, 2008 Fulton County D. Rep. 314, 2008 Ga. App. LEXIS 94, Counsel Stack Legal Research, https://law.counselstack.com/opinion/general-electric-co-v-north-point-ministries-inc-gactapp-2008.