Dillard, Judge.
Lafarge Building Materials, Inc. (“Lafarge”) filed this action on a materialman’s lien discharge bond against Talbot Construction, Inc. (“Talbot”) and Fidelity and Deposit Company of Maryland (“Fidelity”) (collectively, “appellants”), seeking to recover payment for building materials that Lafarge supplied to the Lake Shore Mall project (the “Project”). The parties filed cross-motions for summary judgment, and the trial court denied appellants’ motion and granted [822]*822partial summary judgment to Lafarge, holding that Lafarge’s failure to send a Notice to Contractor did not extinguish its lien rights because Talbot’s Notice of Commencement was legally deficient. For the reasons discussed infra, we reverse.
Viewed in the light most favorable to the nonmovant,1 the record shows that in May 2006, Talbot, acting as a general contractor for the Project, filed a timely Notice of Commencement in accordance with OCGA § 44-14-361.5 (b),2 which contained all of the requisite information save Talbot’s telephone number.
Lafarge contracted with a subcontractor, Michael B. Cline d/b/a Clinecrete (“Cline”), to provide building materials to the Project. Lafarge furnished materials that were incorporated into the Project but never sent a Notice to Contractor as required by OCGA § 44-14-361.5 (a), (c).
When Cline failed to pay Lafarge for the materials provided, Lafarge filed a materialman’s lien against the Project. In January 2008, Talbot and Fidelity recorded, as principal and surety respectively, a lien-discharge bond pursuant to OCGA § 44-14-364. Lafarge subsequently filed a lawsuit and obtained a final judgment against Cline, which included the outstanding debt owed to Lafarge related to the Project. When payment was not forthcoming, Lafarge filed the instant lawsuit, asserting a claim against the lien-discharge bond.
The parties then filed cross-motions for summary judgment. Appellants asserted that Lafarge was not entitled to payment because it failed to perfect its lien by providing a Notice to Contractor in accordance with OCGA § 44-14-361.5 (a), (c). Lafarge countered, maintaining that its duty to file the Notice to Contractor was obviated because Talbot’s Notice of Commencement was fatally deficient under OCGA § 44-14-361.5 (b), (d) in that it failed to include Talbot’s telephone number. The trial court, recognizing several competing legal principles, granted partial summary judg[823]*823ment to Lafarge after concluding that the missing telephone number in Talbot’s Notice of Commencement constituted a fatal defect that rendered it ineffective.
The issue before this Court, then, is whether the failure to include a contractor’s telephone number on a Notice of Commencement triggers OCGA § 44-14-361.5 (d), such that it renders inapplicable the remaining provisions of that statute. In answering this question, we, like the trial court, are mindful of the competing legal principles that must guide our analysis.
We begin by recognizing the fundamental principle of statutory construction that “requires us to follow the literal language of the statute unless it produces contradiction, absurdity or such an inconvenience as to insure that the legislature meant something else.”3 Thus, when “the language of a statute is plain and unambiguous, judicial construction is not only unnecessary but forbidden.”4
We are further mindful that, unless a statute evinces the General Assembly’s plain and unambiguous intent to the contrary, “[a] substantial compliance with any statutory requirement. . . shall be deemed and held sufficient, and no proceeding shall be declared void for want of such compliance.”5 But when “a statute is plain and susceptible of but one natural and reasonable construction, . . . the legislature’s clear intent will not be thwarted by invocation of the rule of substantial compliance.”6 Finally, we note that “lien statutes in derogation of the common law must be strictly construed in favor of the property owner and against the materialman.”7 With these governing principles in mind, we turn now to the statutory provisions at issue.
The materialman-lien statutes were passed for the dual purposes of providing “a means of protecting owners and general contractors from being unfairly surprised by unknown debts of subcontractors,”8 as well as providing a “method of ensuring that [824]*824remote subcontractors and materialmen receive compensation for their contributions to the project.”9 In furtherance of these stated goals, Georgia law allows for a materialman to hold a special lien on property for which it furnishes materials, but imposes upon it the duty of sending a Notice to Contractor to the owner (or agent of the owner) in order to perfect that lien.10 The materialman is relieved of that duty, however, in the absence of a Notice of Commencement.11
OCGA § 44-14-361.5 (b) sets forth what the Notice of Commencement “shall” contain, including “[t]he name, address, and telephone number of the contractor!.]”12 And OCGA § 44-14-361.5 (d) clearly and unambiguously dictates the consequence of failing to file a Notice of Commencement, namely, such a failure renders the remaining provisions of that Code section inapplicable and absolves a materialman of the duty to file a Notice to Contractor in order to perfect its lien rights.13
Nowhere, however, does the statute evince the General Assembly’s intended result/consequence when a Notice of Commencement is timely filed but contains less than each of the enumerated items delineated in OCGA § 44-14-361.5 (b). And in the absence of clear legislative direction, we must examine the Notice of Commencement to determine whether it substantially complies with the statutory requirements.14
[825]*825As stated by our Supreme Court, “ [substantial compliance does not require that the language should be exactly as prescribed by the statute but that all the essential requirements of the form be prescribed.”15 To this end, in General Electric Company u. North Point Ministries, Inc,,16
Free access — add to your briefcase to read the full text and ask questions with AI
Dillard, Judge.
Lafarge Building Materials, Inc. (“Lafarge”) filed this action on a materialman’s lien discharge bond against Talbot Construction, Inc. (“Talbot”) and Fidelity and Deposit Company of Maryland (“Fidelity”) (collectively, “appellants”), seeking to recover payment for building materials that Lafarge supplied to the Lake Shore Mall project (the “Project”). The parties filed cross-motions for summary judgment, and the trial court denied appellants’ motion and granted [822]*822partial summary judgment to Lafarge, holding that Lafarge’s failure to send a Notice to Contractor did not extinguish its lien rights because Talbot’s Notice of Commencement was legally deficient. For the reasons discussed infra, we reverse.
Viewed in the light most favorable to the nonmovant,1 the record shows that in May 2006, Talbot, acting as a general contractor for the Project, filed a timely Notice of Commencement in accordance with OCGA § 44-14-361.5 (b),2 which contained all of the requisite information save Talbot’s telephone number.
Lafarge contracted with a subcontractor, Michael B. Cline d/b/a Clinecrete (“Cline”), to provide building materials to the Project. Lafarge furnished materials that were incorporated into the Project but never sent a Notice to Contractor as required by OCGA § 44-14-361.5 (a), (c).
When Cline failed to pay Lafarge for the materials provided, Lafarge filed a materialman’s lien against the Project. In January 2008, Talbot and Fidelity recorded, as principal and surety respectively, a lien-discharge bond pursuant to OCGA § 44-14-364. Lafarge subsequently filed a lawsuit and obtained a final judgment against Cline, which included the outstanding debt owed to Lafarge related to the Project. When payment was not forthcoming, Lafarge filed the instant lawsuit, asserting a claim against the lien-discharge bond.
The parties then filed cross-motions for summary judgment. Appellants asserted that Lafarge was not entitled to payment because it failed to perfect its lien by providing a Notice to Contractor in accordance with OCGA § 44-14-361.5 (a), (c). Lafarge countered, maintaining that its duty to file the Notice to Contractor was obviated because Talbot’s Notice of Commencement was fatally deficient under OCGA § 44-14-361.5 (b), (d) in that it failed to include Talbot’s telephone number. The trial court, recognizing several competing legal principles, granted partial summary judg[823]*823ment to Lafarge after concluding that the missing telephone number in Talbot’s Notice of Commencement constituted a fatal defect that rendered it ineffective.
The issue before this Court, then, is whether the failure to include a contractor’s telephone number on a Notice of Commencement triggers OCGA § 44-14-361.5 (d), such that it renders inapplicable the remaining provisions of that statute. In answering this question, we, like the trial court, are mindful of the competing legal principles that must guide our analysis.
We begin by recognizing the fundamental principle of statutory construction that “requires us to follow the literal language of the statute unless it produces contradiction, absurdity or such an inconvenience as to insure that the legislature meant something else.”3 Thus, when “the language of a statute is plain and unambiguous, judicial construction is not only unnecessary but forbidden.”4
We are further mindful that, unless a statute evinces the General Assembly’s plain and unambiguous intent to the contrary, “[a] substantial compliance with any statutory requirement. . . shall be deemed and held sufficient, and no proceeding shall be declared void for want of such compliance.”5 But when “a statute is plain and susceptible of but one natural and reasonable construction, . . . the legislature’s clear intent will not be thwarted by invocation of the rule of substantial compliance.”6 Finally, we note that “lien statutes in derogation of the common law must be strictly construed in favor of the property owner and against the materialman.”7 With these governing principles in mind, we turn now to the statutory provisions at issue.
The materialman-lien statutes were passed for the dual purposes of providing “a means of protecting owners and general contractors from being unfairly surprised by unknown debts of subcontractors,”8 as well as providing a “method of ensuring that [824]*824remote subcontractors and materialmen receive compensation for their contributions to the project.”9 In furtherance of these stated goals, Georgia law allows for a materialman to hold a special lien on property for which it furnishes materials, but imposes upon it the duty of sending a Notice to Contractor to the owner (or agent of the owner) in order to perfect that lien.10 The materialman is relieved of that duty, however, in the absence of a Notice of Commencement.11
OCGA § 44-14-361.5 (b) sets forth what the Notice of Commencement “shall” contain, including “[t]he name, address, and telephone number of the contractor!.]”12 And OCGA § 44-14-361.5 (d) clearly and unambiguously dictates the consequence of failing to file a Notice of Commencement, namely, such a failure renders the remaining provisions of that Code section inapplicable and absolves a materialman of the duty to file a Notice to Contractor in order to perfect its lien rights.13
Nowhere, however, does the statute evince the General Assembly’s intended result/consequence when a Notice of Commencement is timely filed but contains less than each of the enumerated items delineated in OCGA § 44-14-361.5 (b). And in the absence of clear legislative direction, we must examine the Notice of Commencement to determine whether it substantially complies with the statutory requirements.14
[825]*825As stated by our Supreme Court, “ [substantial compliance does not require that the language should be exactly as prescribed by the statute but that all the essential requirements of the form be prescribed.”15 To this end, in General Electric Company u. North Point Ministries, Inc,,16 this Court held that the name of the true owner and a legal description of the subject property were essential requirements of a Notice of Commencement such that their omissions triggered OCGA § 44-14-361.5 (d), because the failure to include that information vitiated one of the primary purposes of the statute — namely, to ensure that a lien claimant could identify the property owner and receive compensation for contributions to a given project.17 On the other hand, in Rey Coliman Contractors, Inc. v. PCL Construction Services, Inc.,18 we concluded that a contractor’s failure to post at the worksite an otherwise complete and timely filed Notice of Commencement was not of the same import and did not render the Notice of Commencement fatally defective.19
Guided by the foregoing statutory language and precedents, we conclude that the absence of Talbot’s telephone number presents a technical, as opposed to substantive, omission and thus does not render the remaining provisions of the statute inapplicable. Unlike a failure to adequately identify the owner and property at issue, a failure to include the telephone number of the contractor, who is otherwise accurately identified by name and address, presents merely a potential inconvenience to a materialman trying to contact same. As such, because Talbot’s Notice of Commencement substantially complied with OCGA § 44-14-361.5 (b), and because we are charged with construing lien statutes in favor of a landowner and against the materialman, we conclude that the omission of Talbot’s telephone number in the Notice of Commencement did not relieve Lafarge of its duty to file a Notice to Contractor. We therefore reverse the trial court’s grant of partial summary judgment to Lafarge.
Judgment reversed.
Mikell, C. J., and Smith, P. J., concur.
[826]*826Decided November 22, 2011.
David J. Merbaum, for appellants.
Dietrich, Evans, Scholz & Williams, Scott A. Schweber, for appellee.