Fidelity & Deposit Co. of Maryland v. Lafarge Building Materials, Inc.

720 S.E.2d 288, 312 Ga. App. 821, 2011 Fulton County D. Rep. 3892, 2011 Ga. App. LEXIS 1045
CourtCourt of Appeals of Georgia
DecidedNovember 22, 2011
DocketA11A1320
StatusPublished
Cited by8 cases

This text of 720 S.E.2d 288 (Fidelity & Deposit Co. of Maryland v. Lafarge Building Materials, Inc.) is published on Counsel Stack Legal Research, covering Court of Appeals of Georgia primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Fidelity & Deposit Co. of Maryland v. Lafarge Building Materials, Inc., 720 S.E.2d 288, 312 Ga. App. 821, 2011 Fulton County D. Rep. 3892, 2011 Ga. App. LEXIS 1045 (Ga. Ct. App. 2011).

Opinion

Dillard, Judge.

Lafarge Building Materials, Inc. (“Lafarge”) filed this action on a materialman’s lien discharge bond against Talbot Construction, Inc. (“Talbot”) and Fidelity and Deposit Company of Maryland (“Fidelity”) (collectively, “appellants”), seeking to recover payment for building materials that Lafarge supplied to the Lake Shore Mall project (the “Project”). The parties filed cross-motions for summary judgment, and the trial court denied appellants’ motion and granted [822]*822partial summary judgment to Lafarge, holding that Lafarge’s failure to send a Notice to Contractor did not extinguish its lien rights because Talbot’s Notice of Commencement was legally deficient. For the reasons discussed infra, we reverse.

Viewed in the light most favorable to the nonmovant,1 the record shows that in May 2006, Talbot, acting as a general contractor for the Project, filed a timely Notice of Commencement in accordance with OCGA § 44-14-361.5 (b),2 which contained all of the requisite information save Talbot’s telephone number.

Lafarge contracted with a subcontractor, Michael B. Cline d/b/a Clinecrete (“Cline”), to provide building materials to the Project. Lafarge furnished materials that were incorporated into the Project but never sent a Notice to Contractor as required by OCGA § 44-14-361.5 (a), (c).

When Cline failed to pay Lafarge for the materials provided, Lafarge filed a materialman’s lien against the Project. In January 2008, Talbot and Fidelity recorded, as principal and surety respectively, a lien-discharge bond pursuant to OCGA § 44-14-364. Lafarge subsequently filed a lawsuit and obtained a final judgment against Cline, which included the outstanding debt owed to Lafarge related to the Project. When payment was not forthcoming, Lafarge filed the instant lawsuit, asserting a claim against the lien-discharge bond.

The parties then filed cross-motions for summary judgment. Appellants asserted that Lafarge was not entitled to payment because it failed to perfect its lien by providing a Notice to Contractor in accordance with OCGA § 44-14-361.5 (a), (c). Lafarge countered, maintaining that its duty to file the Notice to Contractor was obviated because Talbot’s Notice of Commencement was fatally deficient under OCGA § 44-14-361.5 (b), (d) in that it failed to include Talbot’s telephone number. The trial court, recognizing several competing legal principles, granted partial summary judg[823]*823ment to Lafarge after concluding that the missing telephone number in Talbot’s Notice of Commencement constituted a fatal defect that rendered it ineffective.

The issue before this Court, then, is whether the failure to include a contractor’s telephone number on a Notice of Commencement triggers OCGA § 44-14-361.5 (d), such that it renders inapplicable the remaining provisions of that statute. In answering this question, we, like the trial court, are mindful of the competing legal principles that must guide our analysis.

We begin by recognizing the fundamental principle of statutory construction that “requires us to follow the literal language of the statute unless it produces contradiction, absurdity or such an inconvenience as to insure that the legislature meant something else.”3 Thus, when “the language of a statute is plain and unambiguous, judicial construction is not only unnecessary but forbidden.”4

We are further mindful that, unless a statute evinces the General Assembly’s plain and unambiguous intent to the contrary, “[a] substantial compliance with any statutory requirement. . . shall be deemed and held sufficient, and no proceeding shall be declared void for want of such compliance.”5 But when “a statute is plain and susceptible of but one natural and reasonable construction, . . . the legislature’s clear intent will not be thwarted by invocation of the rule of substantial compliance.”6 Finally, we note that “lien statutes in derogation of the common law must be strictly construed in favor of the property owner and against the materialman.”7 With these governing principles in mind, we turn now to the statutory provisions at issue.

The materialman-lien statutes were passed for the dual purposes of providing “a means of protecting owners and general contractors from being unfairly surprised by unknown debts of subcontractors,”8 as well as providing a “method of ensuring that [824]*824remote subcontractors and materialmen receive compensation for their contributions to the project.”9 In furtherance of these stated goals, Georgia law allows for a materialman to hold a special lien on property for which it furnishes materials, but imposes upon it the duty of sending a Notice to Contractor to the owner (or agent of the owner) in order to perfect that lien.10 The materialman is relieved of that duty, however, in the absence of a Notice of Commencement.11

OCGA § 44-14-361.5 (b) sets forth what the Notice of Commencement “shall” contain, including “[t]he name, address, and telephone number of the contractor!.]”12 And OCGA § 44-14-361.5 (d) clearly and unambiguously dictates the consequence of failing to file a Notice of Commencement, namely, such a failure renders the remaining provisions of that Code section inapplicable and absolves a materialman of the duty to file a Notice to Contractor in order to perfect its lien rights.13

Nowhere, however, does the statute evince the General Assembly’s intended result/consequence when a Notice of Commencement is timely filed but contains less than each of the enumerated items delineated in OCGA § 44-14-361.5 (b). And in the absence of clear legislative direction, we must examine the Notice of Commencement to determine whether it substantially complies with the statutory requirements.14

[825]*825As stated by our Supreme Court, “ [substantial compliance does not require that the language should be exactly as prescribed by the statute but that all the essential requirements of the form be prescribed.”15 To this end, in General Electric Company u. North Point Ministries, Inc,,16

Free access — add to your briefcase to read the full text and ask questions with AI

Related

SPI HOLDCO, LLC v. SIDDHARTHA MOOKERJI
Court of Appeals of Georgia, 2021
Capitol Materials, Inc. v. JLB Buckhead, LLC
789 S.E.2d 803 (Court of Appeals of Georgia, 2016)
Aa-Professional Bail Bonding v. Deal
775 S.E.2d 217 (Court of Appeals of Georgia, 2015)
Citibank (South Dakota), N.A. v. Graham
726 S.E.2d 617 (Court of Appeals of Georgia, 2012)

Cite This Page — Counsel Stack

Bluebook (online)
720 S.E.2d 288, 312 Ga. App. 821, 2011 Fulton County D. Rep. 3892, 2011 Ga. App. LEXIS 1045, Counsel Stack Legal Research, https://law.counselstack.com/opinion/fidelity-deposit-co-of-maryland-v-lafarge-building-materials-inc-gactapp-2011.