Washington International Insurance v. Hughes Supply, Inc.

609 S.E.2d 99, 271 Ga. App. 50, 2004 Fulton County D. Rep. 3353, 2004 Ga. App. LEXIS 1342
CourtCourt of Appeals of Georgia
DecidedOctober 13, 2004
DocketA04A1198
StatusPublished
Cited by4 cases

This text of 609 S.E.2d 99 (Washington International Insurance v. Hughes Supply, Inc.) is published on Counsel Stack Legal Research, covering Court of Appeals of Georgia primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Washington International Insurance v. Hughes Supply, Inc., 609 S.E.2d 99, 271 Ga. App. 50, 2004 Fulton County D. Rep. 3353, 2004 Ga. App. LEXIS 1342 (Ga. Ct. App. 2004).

Opinion

Phipps, Judge.

Hughes Supply, Inc. (Hughes) furnished material and equipment to New South Electric, Inc. (New South) an electrical subcontractor that worked on a construction project on which Motel Construction Management Group (MCM) was the general contractor. After New South failed to pay Hughes for the materials, Hughes filed suit against New South and filed a materialman’s lien on the improved realty. MCM and its surety, Washington International Insurance Company (WIIC), discharged the lien by filing a bond. Hughes obtained a judgment against New South and then filed suit against MCM and WIIC to recover on the lien release bond. In awarding summary judgment to Hughes, the trial court rejected MCM and WIIC’s argument that Hughes’s purported failure to fully comply with the notice requirement of the lien statute barred Hughes from recovering on the bond. After review, we affirm.

This litigation arose from the vestiges of a construction project for a Comfort Inn in LaGrange. MCM engaged New South as its electrical subcontractor and paid New South for the electrical work. New South, however, failed to pay Hughes, its supplier. On October 4, 1999, Hughes filed a materialman’s lien in Troup County, the site of the Comfort Inn. On October 15, 1999, Hughes filed suit against New South in Lowndes County. 1 Then, on October 26, 1999, Hughes filed a “Notice of Filing of Action for Claim on Mechanics’ and Materialmen’s Liens” in Troup County. Hughes’s notice of filing accurately cross-referenced the lien “recorded in the Office of the *51 Clerk of the Superior Court of Troup County at Deed Book 863, Page 626,” properly identified the civil suit filed by Hughes against New South in Lowndes County, and correctly identified the current owner of the property as KSST Investments. The notice, however, contained what MCM and WIIC claim was an invalid or incomplete legal description of the underlying real property. To extricate the realty encumbered by Hughes’s lien, MCM and WIIC filed a lien release bond in Troup County that discharged Hughes’s lien.

Hughes obtained a judgment against New South then filed this action in Fulton County against MCM and WIIC to recover on the bond that discharged the lien. After MCM and WIIC contested the legal sufficiency of the notice of the action filed by Hughes in Troup County in October 1999, Hughes filed an amendment to that notice to include a reference to a specific recorded instrument in the chain of title of the realty against which Hughes had filed its lien.

Hughes moved for summary judgment. Asserting its right to recover on the bond, Hughes sought payment of the bond and requested a bad faith penalty and attorney fees. MCM and WIIC filed a cross-motion for summary judgment. They claimed that Hughes’s lien had become ineffective and unenforceable as a result of its failure to strictly comply with OCGA§ 44-14-361.1 (a) (3) in that Hughes did not timely file a nondefective notice of commencement of action.

The trial court granted summary judgment to Hughes as to the principal amount plus interest but denied its claim for bad faith attorney fees. After Hughes dismissed its claim for bad faith damages, the trial court entered final judgment in favor of Hughes. MCM and WIIC appeal the final judgment and the prior order denying their cross-motion for summary judgment that was effectively subsumed into the final judgment.

1. MCM and WIIC contend that Hughes’s notice of commencement of action did not comply with the chain of title reference requirement of OCGA § 44-14-361.1; and that as a result of this failure, the lien became invalid and unenforceable as of the fifteenth day following the commencement by Hughes of its suit against New South. Specifically, MCM and WIIC claim that Hughes’s notice contained a defective description of the real property so that Hughes failed to timely file a nondefective notice of commencement as required by OCGA§ 44-14-361.1 (a) (3). The thrust of their argument is that “because Hughes’s lien had already become void and unenforceable before the bond was filed, the lien itself had no validity and the bond releasing the lien was necessarily without effect.”

In enacting OCGA§ 44-14-361, the legislature created a detailed statutory scheme for regulating liens filed by materialmen who furnish supplies and materials for building, repairing, or improving property. To perfect a lien, the provisions of OCGA § 44-14-361.1 (a) *52 (1) through (3), as summarized below, require a materialman who has substantially complied with his contract to:

(a) file a claim of lien in the county where the property is located within three months of furnishing the materials; (b) send a copy of the lien claim to the property owner; (c) commence an action against the contractor to recover the amount of the claim within 12 months of when the claim became due; and (d) file a notice of the action with the superior court clerk of the county where the lien was filed so that the clerk can enter information about the lawsuit in county records. 2

When a property owner obtains a lien release bond, “the bond stands in the place of the real property as security for the lien claimant.” 3 Nevertheless, even when a property owner obtains a discharge bond under OCGA § 44-14-364, “the lien claimant in an action on the bond must still comply with the statutory requirements for perfecting a lien, with one exception . . . and the principal and the surety on the bond are entitled to raise any defense that would have been available as a defense to the lien foreclosure.” 4 The exception recognized by the Supreme Court is that lien claimants who sue to recover on the bond do not have to comply with the notice provision in subparagraph (a) (3) to perfect the lien. 5

Here, MCM and WIIC assert that Hughes, the lien claimant, failed to file a proper notice of the action as required by subparagraph (3) of OCGA § 44-14-361.1 (a). They point out that subparagraph (3) requires that “[t]he notice shall contain a caption referring to the then owner of the property against which the lien was filed and referring to a deed or other recorded instrument in the chain of title of the affected property 6

Free access — add to your briefcase to read the full text and ask questions with AI

Related

West Main I, LLC v. Siteone Landscape Supply, LLC
Court of Appeals of Georgia, 2023
Cook Sales, Inc. v. Concrete Enterprises, LLC
Court of Appeals of Georgia, 2020
General Electric Co. v. North Point Ministries, Inc.
657 S.E.2d 297 (Court of Appeals of Georgia, 2008)

Cite This Page — Counsel Stack

Bluebook (online)
609 S.E.2d 99, 271 Ga. App. 50, 2004 Fulton County D. Rep. 3353, 2004 Ga. App. LEXIS 1342, Counsel Stack Legal Research, https://law.counselstack.com/opinion/washington-international-insurance-v-hughes-supply-inc-gactapp-2004.