Cook Sales, Inc. v. Concrete Enterprises, LLC
Opinion
FIFTH DIVISION
REESE, P. J.,
MARKLE and COLVIN, JJ.
NOTICE: Motions for reconsideration must be physically received in our clerk’s office within ten days of the date of decision to be deemed timely filed.
https://www.gaappeals.us/rules
DEADLINES ARE NO LONGER TOLLED IN THIS COURT. ALL FILINGS MUST BE SUBMITTED WITHIN THE TIMES SET BY OUR COURT RULES.
October 6, 2020
In the Court of Appeals of Georgia A20A1037. COOK SALES, INC. v. CONCRETE ENTERPRISES, LLC.
COLVIN, Judge.
This Court granted Cook Sales, Inc. (“Cook Sales”)’s request for an interlocutory appeal from the trial court’s order denying its motion to dismiss Concrete Enterprises, LLC (“Concrete Enterprises”)’s complaint for lien foreclosure. Concrete Enterprises, a materialman, sought to foreclose on its lien on property owned by Cook Sales for work that Concrete Enterprises performed on the property as a subcontractor for the non-party, Watford Steel Buildings (“Watford”). Cook Sales argues that the trial court erred in denying its motion to dismiss because Concrete Enterprises’s notice of its lien action was not timely filed, as required by OCGA § 44-14-361.1 (a) (3). We agree, and therefore reverse.
This Court reviews the denial of a motion to dismiss under the de novo standard of review. See McReynolds v. Krebs, 307 Ga. App. 330, 332 (1) (705 SE2d 214) (2010).
The record shows that Watford hired Concrete Enterprises to act as a subcontractor to make improvements to Cook Sales’s property. On December 19, 2017, Concrete Enterprises invoiced Watford for labor and services it performed on Cook Service’s property. Watford failed to pay the invoice. On February 27, 2018, Concrete Enterprises sent notice of a claim of materialman’s lien to Watford and sent a notice of claim of lien to Cook Sales.
On March 28, 2018, Concrete Enterprises filed a complaint seeking to recover the unpaid balance from Watford in Cook County Superior Court. Watford was served on July 12, 2018. Once served, Concrete Enterprises filed a Notice of Lien Action with Lowndes County Superior Court Clerk on July 16, 2018, 110 days after Concrete Enterprises commenced the action in Cook County against Watford. Concrete Enterprises obtained a default judgment against Watford in the lien action for $72,569.21.
On January 7, 2019, Concrete Enterprises then filed the instant action for lien foreclosure against Cook Sales in the Superior Court of Lowndes County. The
complaint sought a special lien against Cook Sales’s property for the amount of money that Watford owed Concrete Enterprises. Cook Sales filed a motion to dismiss, arguing that Concrete Enterprises’s claims were time-barred due to its failure to timely comply with the strict notice requirements of OCGA § 44-14-361.1. Following a hearing, the trial court denied the motion to dismiss, but granted Cook Sales a certificate of immediate review. This Court then granted Cook Sales’s application for discretionary appeal.
Cook Sales argues that the trial court erred in denying its motion to dismiss because Concrete Enterprises did not timely comply with the notice filing requirement of OCGA § 44-14-361.1 (a) (3). See Abacus, Inc. v. Hebron Baptist Church, Inc., 201 Ga. App. 376, 376 (411 SE2d 113) (1991) (failure to timely file notice of suit renders lien unenforceable). For the following reasons, we reverse.
At issue is this case is whether, under the legislature’s 2009 amendment to OCGA § 44-14-361.1 (a) (3), the calculation of the deadline to file a notice of lien action in the superior court begins on the date the lien action was filed or on the date that service of process is perfected against a defendant.1
1 OCGA § 44-14-361.1 has been amended several times. See Ga. Laws 2000, p. 1589, §2 (applying the former version of OCGA § 44-14-361.1 (a) (3)); Ga. Laws 2008, Act 766, §2, effective March 31, 2009 (applying the new version of OCGA §
When it enacted OCGA § 44-14-361.1, the Georgia legislature
created a detailed statutory scheme for regulating liens filed by materialmen who furnish supplies and materials for building, repairing, or improving property. To perfect a lien, the provisions of OCGA § 44-
14-361.1 (a) (1) through (3), as summarized below, require a materialman who has substantially complied with his contract to: (a) file a claim of lien in the county where the property is located within [90 days] of furnishing the materials; (b) send a copy of the lien claim to the property owner; (c) commence an action against the contractor to recover the amount of the claim within [365 days] of when the claim became due; and (d) [within 30 days of commencing the action,] file a notice of the action with the superior court clerk of the county where the lien was filed so that the clerk can enter information about the lawsuit in county records.
(Footnote omitted). Washington Intern. Ins. Co. v. Hughes Supply Co., 271 Ga. App. 50 (609 SE2d 99) (2004). See OCGA § 44-14-361.1 (a) (1) - (3). If a materialmen fails to comply with these requirements, “the lien shall not be effective or enforceable.” OCGA § 44-14-361.1 (a).2 Further,
44-14-361.1 (a) (3)); Ga. Laws 2010, Act 618, §1, effective July 1, 2010 (same); Laws 2019, Act 321, §44, effective May 12, 2019 (same).
2 Accord Central Atlanta Tractor Sales, Inc. v. Athena Dev., LLC, 289 Ga. App.
355, 357 (657 SE2d 290) (2008) (“[T]he intent of OCGA § 44-14-361.1 as to timely filing of liens is to establish a time certain beyond which liens cannot be filed, for the protection of the contracting parties and innocent third parties . . . [accordingly,] the
the materialman’s statute requires strict compliance. Before a materialman’s lien can be allowed, the lien claimant must show compliance with all conditions of the statute. Filing the notice of commencement of the action is a prerequisite to the enforceability of the lien, and at the time the lienholder fails to file the notice, the lien becomes unenforceable.
(Citations omitted.) Gwinnett-Club Associations, LP v. Southern Electric Supply Co., Inc., 242 Ga. App. 507 (529 SE2d 636) (2000).3 When interpreting a statute,
we are mindful that the “golden rule” of statutory construction requires that we follow the literal languageof the statute unless doing so produces contradiction, absurdity or such an inconvenience as to insure that the legislature meant something else. If the statutory language is plain and does not lead to absurd results, we must construe the statute according to its terms without further inquiry. Moreover, in construing language in any one part of a statute, a court should consider the entire scheme of
statute is to be strictly construed against the materialmen”) (punctuation and footnote omitted).
3 “The rationale is that there is usually no contract between the owner and supplier. Instead, a materialman’s lien effectively permits the transfer of liability from the person who actually contracted with the materialman for materials to be used in improving real estate to the owner of the improved property.” (Citation and punctuation omitted.) Founders Kitchen & Bath, Inc. v. Alexander, 334 Ga. App. 389, 381 (779 SE2d 668) (2015).
the statute and attempt to gather the legislative intent from the statute as a whole.
(Citations and punctuation omitted.) Beacon Medical Products, LLC v. Travelers Cas. and Sur. Co. of America, 292 Ga. App. 617, 619 (1) (665 SE2d 710) (2008). Accord Robertson v. Ridge Environmental, LLC, 319 Ga. App. 570, 571 (1) (737 SE2d 578) (2013).
With these principles in mind, we turn to the statutory provision at issue. Prior to 2009, OCGA § 44-14-361.1 (2000) provided in relevant part:
Free access — add to your briefcase to read the full text and ask questions with AI
Cook Sales, Inc. v. Concrete Enterprises, LLC (Cook Sales, Inc. v. Concrete Enterprises, LLC) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.