Central Atlanta Tractor Sales, Inc. v. Athena Development, LLC

657 S.E.2d 290, 289 Ga. App. 355, 2008 Fulton County D. Rep. 316, 2008 Ga. App. LEXIS 87
CourtCourt of Appeals of Georgia
DecidedJanuary 29, 2008
DocketA07A1699
StatusPublished
Cited by2 cases

This text of 657 S.E.2d 290 (Central Atlanta Tractor Sales, Inc. v. Athena Development, LLC) is published on Counsel Stack Legal Research, covering Court of Appeals of Georgia primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Central Atlanta Tractor Sales, Inc. v. Athena Development, LLC, 657 S.E.2d 290, 289 Ga. App. 355, 2008 Fulton County D. Rep. 316, 2008 Ga. App. LEXIS 87 (Ga. Ct. App. 2008).

Opinion

MlKELL, Judge.

Central Atlanta Tractor Sales, Inc. (“CATS”) sued Athena Development, LLC a/k/a Athena Development Group, LLC (“Athena”) and Accredited Surety & Casualty Company, Inc. a/k/a Accredited Surety and Casualty, Inc. (“Accredited Surety”), to recover on the bond which discharged CATS’s lien on Athena’s real property. The trial court granted Athena’s and Accredited Surety’s motion for summary judgment, and CATS appeals. We affirm because CATS could not recover on the bond in view of CATS’s failure to preserve its lien rights.

Summary judgment is proper when there is no genuine issue of material fact and the movant is entitled to judgment as a matter of law. A de novo standard of review applies to an appeal from a grant of summary judgment, and we view the *356 evidence, and all reasonable conclusions and inferences drawn from it, in the light most favorable to the nonmovant. 1

So viewed, the evidence shows that in 2003, Athena, as owner, entered into an agreement with West Georgia Excavation, Inc. (‘WGE”), as contractor, to perform construction work on The Summit at Lost Mountain Project in Powder Springs. CATS supplied equipment to WGE, which WGE employed in its work on the project. WGE did no work on the project on or after February 16, 2004, which was the date WGE returned the last piece of CATS’s equipment. As averred by CATS’s vice-president, amounts owed by WGE to CATS for the use of the equipment became due on February 18,2004, after the equipment was inspected.

On March 12, 2004, CATS filed a claim of lien against the project in the amount of $101,090.75 on account of equipment furnished at the instance of WGE. CATS sued WGE on February 16, 2005, to recover on the claim. On or about July 28, 2005, Athena, as principal, and Accredited Surety, as surety, provided a bond in accordance with OCGA § 44-14-364 to discharge CATS’s lien on the project. After obtaining a default judgment against WGE, CATS filed this suit on April 26, 2006, to recover on the bond.

If a lien release bond is properly obtained and recorded under OCGA § 44-14-364, “the bond stands in the place of the real property as security for the lien claimant.” 2 Thus,

the principal and the surety on the bond are entitled to raise any defense that would have been available as a defense to the lien foreclosure. This ruling means that the lien claimant must first seek to recover monies owed from the contractor, the party with whom it has a contract, before seeking to recover from the property owner, with whom the supplier has no contractual relationship. 3

At issue is whether CATS pursued its claim in a timely fashion against its contractor, WGE, by “commenc[ing] an action against the contractor to recover the amount of the claim within 12 months of when the claim became due.” 4 CATS contends that its February 16, 2005 action was timely because its claim against WGE became due on *357 February 18, 2004, the date CATS inspected its equipment for damage. Athena and Accredited Surety argue that CATS’s action was untimely because the lien law does not allow for an inspection period in determining the due date of CATS’s claim. We agree with Athena and Accredited Surety.

OCGA § 44-14-361.1 (a) (3) provides that in order for a lien to be valid the claimant must commence “an action for the recovery of the amount of the party’s claim within 12 months from the time the same shall become due.” 5 As a rule, the 12-month period contemplated by OCGA § 44-14-361.1 (a) (3) begins on the date that the last materials were furnished. 6 CATS contends that it did not supply materials but supplied equipment under a rental agreement. CATS argues that sums due under a rental contract cannot be determined until the equipment is returned and inspected for damage whereas the amount due a supplier of materials is known when the material is unloaded. Therefore, CATS maintains, its claim against WGE was not due for purposes of OCGA § 44-14-361.1 (a) (3) until the date of inspection. Keeping in mind that“[t]heintentofOCGA§ 44-14-361.1 as to timely filing of liens is to establish a time certain beyond which liens cannot be filed, for the protection of the contracting parties and innocent third parties,” 7 and that the statute “is to be strictly construed against the materialman,” 8 we disagree with CATS for three reasons.

First, although CATS claims it should be treated differently than a material supplier because it supplied equipment, CATS was a material supplier for purposes of the lien law. OCGA § 44-14-360 (3) defines “materials” to include “equipment used in making improvements to the real estate, to the extent of the reasonable value or the contracted rental price, whichever is greater.” The lien provided by OCGA § 44-14-361 (a) arises as to “property for which [the lien claimants] furnish labor, services, or materials.” It follows that CATS was required to furnish its equipment for the improvement of the project in order for its lien to arise. After the equipment had been returned to CATS and was awaiting inspection, the equipment was not being furnished for the improvement of the project. 9

*358 Second, if CATS’s claim is considered to be due on the date of inspection rather than on the last date the equipment was furnished for the improvement of the project, this would create an unwarranted inconsistency in subsections (a) (2) and (a) (3) of OCGA§ 44-16-361.1:

There are two critical dates for the enforcement of mechanics’ liens. One is that the claim of lien must be filed within three months after, as it relates to this case, “the material [or machinery] is furnished.” OCGA § 44-14-361.1 (a) (2).

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cook Sales, Inc. v. Concrete Enterprises, LLC
Court of Appeals of Georgia, 2020
D. C. Ecker Construction, Inc. v. Ponce Investment, LLC
670 S.E.2d 526 (Court of Appeals of Georgia, 2008)

Cite This Page — Counsel Stack

Bluebook (online)
657 S.E.2d 290, 289 Ga. App. 355, 2008 Fulton County D. Rep. 316, 2008 Ga. App. LEXIS 87, Counsel Stack Legal Research, https://law.counselstack.com/opinion/central-atlanta-tractor-sales-inc-v-athena-development-llc-gactapp-2008.