Southeast Culvert, Inc. v. Hardin Bros., LLC

718 S.E.2d 28, 312 Ga. App. 158, 2011 Fulton County D. Rep. 3109, 2011 Ga. App. LEXIS 858
CourtCourt of Appeals of Georgia
DecidedOctober 4, 2011
DocketA11A0833
StatusPublished

This text of 718 S.E.2d 28 (Southeast Culvert, Inc. v. Hardin Bros., LLC) is published on Counsel Stack Legal Research, covering Court of Appeals of Georgia primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Southeast Culvert, Inc. v. Hardin Bros., LLC, 718 S.E.2d 28, 312 Ga. App. 158, 2011 Fulton County D. Rep. 3109, 2011 Ga. App. LEXIS 858 (Ga. Ct. App. 2011).

Opinion

Doyle, Judge.

In an action for foreclosure on a materialman’s lien, Southeast Culvert, Inc. (“Southeast”), a building materials supplier, appeals from the trial court’s grant of summary judgment to Hardin Brothers, LLC (“Hardin”), a property owner and general contractor. Specifically, Southeast contends that the trial court erred by (1) improperly applying OCGA § 44-14-361.5, and (2) overlooking a factual dispute in the record. Discerning no error, we affirm.

Summary judgment is proper when there is no genuine issue of material fact and the movant is entitled to judgment as a matter of law. OCGA § 9-11-56 (c). A de novo standard of review applies to an appeal from a grant of summary judgment, and we view the evidence, and all reasonable conclusions and inferences drawn from it, in the light most favorable to the nonmovant. 1

So viewed, the record shows that in April 2007, Hardin obtained a land disturbance permit for a construction project in Forsyth County. In May 2007, Hardin hired Sterling Concepts Grading, Inc. (“Sterling”), to perform clearing, grading, and underground pipe installation. At the same time, Sterling subcontracted with Cousins Excavation, LLC (“Cousins”), to complete the pipe installation. 2

Southeast supplied piping materials to Cousins, with its first delivery occurring on June 5, 2007, and Cousins began work at the site on or around that date. In June 2007, Southeast invoiced Cousins for $48,912.70 worth of material Southeast had delivered. On June 28, 2007, Hardin filed a Notice of Commencement pursuant to OCGA § 44-14-361.5 (b).

In October 2007, Southeast received its first payment of $10,000 from Cousins toward the June 2007 invoice. In December 2007, Southeast delivered more materials to the site and received addi *159 tional partial payment from Cousins toward the June invoice. By March 2008, Cousins’s outstanding balance was $32,122.66, and on June 12, 2008, Southeast filed a materialman’s claim of lien beginning in March 2008 for the outstanding balance pursuant to OCGA § 44-14-361.5. Southeast never filed a Notice to Contractor.

Hardin, the property owner and general contractor, responded to the action and moved for summary judgment on the ground that Southeast had failed to provide a Notice to Contractor as required by the lien statute. The trial court granted the motion, and this appeal followed.

1. Southeast contends that the trial court misapplied OCGA § 44-14-361.5 by concluding that Southeast’s obligation to provide a Notice to Contractor was applicable despite the fact that Hardin’s Notice of Commencement was not filed within 15 days of commencing work, as required by the Code section. We disagree.

OCGA § 44-14-361.5 provides as follows, in relevant part:

(a) To make good [certain materialman] hens . . . , any person having a right to a lien who does not have privity of contract with the contractor and is providing . . . materials for the improvement of property shall, within 30 days from the filing of the Notice of Commencement or 30 days following the first delivery of labor, services, or materials to the property, whichever is later, give a written Notice to Contractor ... to the owner or the agent of the owner and to the contractor for a project on which there has been filed with the clerk of the superior court a Notice of Commencement. . . .
(b) Not later than 15 days after the contractor physically commences work on the property, a Notice of Commencement shall be filed by the owner, the agent of the owner, or by the contractor with the clerk of the superior court in the county in which the project is located. . . .
(d) The failure to file a Notice of Commencement shall render the provisions of this Code section inapplicable. . . . 3

The lien statute is in derogation of common law and must therefore “be strictly construed in favor of the property owner and against the materialman.” 4

Southeast relies on subsection (d) of OCGA § 44-14-361.5, which relieves it of its obligation to provide a Notice to Contractor if there *160 has been a “failure to file a Notice of Commencement.” Here, the work began at the site on or around the time of Southeast’s first delivery on June 5, 2007, and the Notice of Commencement was filed on June 28, 2007, approximately eight days after the statutory fifteen-day filing period expired. This Court has held that “OCGA § 44-14-361.5 (a) and (d) do not require the filing of a Notice of Commencement within the 15-day deadline as a general condition to [the requirement to provide] a Notice to Contractor.” 5 Accordingly, we agree with the trial court’s conclusion that the eight-day delay in filing the Notice of Commencement did not relieve Southeastern of its obligation to provide a Notice to Contractor. It is undisputed that this was “a project on which there ha[d] been filed with the clerk of the superior court a Notice of Commencement,” so the notice requirement in subsection (a) was applicable to Southeast. 6 The reference in subsection (d) to the failure to file a Notice of Commencement “applies when there has been a total failure to file a Notice of Commencement at the time when a materialman must give a written Notice to Contractor to perfect its lien under subsection (a).” 7 There was no such total failure to file a Notice of Commencement here, merely an untimely filing. Nothing in subsection (d) creates a timeliness component, 8 and absent a clear legislative directive, we decline to do so here in light of the requirement to construe the Code section strictly. 9

2. Southeast also contends that the trial court erred by granting summary judgment despite a factual issue as to whether the Notice of Commencement contained a fatal defect, which would relieve Southeast’s obligation to provide a Notice to Contractor. We disagree.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Beacon Medical Products, LLC v. Travelers Casualty & Surety Co. of America
665 S.E.2d 710 (Court of Appeals of Georgia, 2008)
Matjoulis v. Integon General Ins. Corp.
486 S.E.2d 684 (Court of Appeals of Georgia, 1997)
Rey Coliman Contractors, Inc. v. PCL Construction Services, Inc.
676 S.E.2d 298 (Court of Appeals of Georgia, 2009)
NORTHSIDE BUILDING SUPPLY COMPANY v. Foures
411 S.E.2d 87 (Court of Appeals of Georgia, 1991)
General Electric Co. v. North Point Ministries, Inc.
657 S.E.2d 297 (Court of Appeals of Georgia, 2008)
Zepp v. Brannen
658 S.E.2d 567 (Supreme Court of Georgia, 2008)

Cite This Page — Counsel Stack

Bluebook (online)
718 S.E.2d 28, 312 Ga. App. 158, 2011 Fulton County D. Rep. 3109, 2011 Ga. App. LEXIS 858, Counsel Stack Legal Research, https://law.counselstack.com/opinion/southeast-culvert-inc-v-hardin-bros-llc-gactapp-2011.