Dial Block Co. v. Mastro Masonry

863 A.2d 373, 374 N.J. Super. 13
CourtNew Jersey Superior Court Appellate Division
DecidedDecember 30, 2004
StatusPublished
Cited by5 cases

This text of 863 A.2d 373 (Dial Block Co. v. Mastro Masonry) is published on Counsel Stack Legal Research, covering New Jersey Superior Court Appellate Division primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Dial Block Co. v. Mastro Masonry, 863 A.2d 373, 374 N.J. Super. 13 (N.J. Ct. App. 2004).

Opinion

863 A.2d 373 (2004)
374 N.J. Super. 13

DIAL BLOCK COMPANY, INC., Plaintiff-Appellant,
v.
MASTRO MASONRY CONTRACTORS, Defendant, and
Ernest Bock & Sons, Inc.; XL Specialty Insurance Company, Defendants-Respondents, and
Ernest Bock & Sons, Inc., a Pennsylvania Corporation, Defendant/Third-Party Plaintiff,
v.
Alfred LaPuma, Frank Falco and Joseph Russo, Third-Party Defendants.

Superior Court of New Jersey, Appellate Division.

Argued December 15, 2004.
Decided December 30, 2004.

*374 Christopher S. Lipari, argued the cause for appellant (Fitzgerald, McGroarty & Lipari, attorneys; Christopher S. Lipari, on the brief).

John F. Palladino, Atlantic City, argued the cause for respondent (Hankin Sandman Bradley & Palladino, attorneys; John F. Palladino, on the brief).

Before Judges BRAITHWAITE, LISA and WINKELSTEIN.

The opinion of the court was delivered by

WINKELSTEIN, J.A.D.

This case arises out of a contract to build the Atlantic County Special Services School and requires an interpretation of the New Jersey Public Works Bond Act, N.J.S.A. 2A:44-143 to -148 (the Bond Act), which protects laborers, subcontractors and material suppliers who work on public construction projects. Plaintiff is a material supplier that is owed money from Mastro Masonry Contractors, the project masonry subcontractor, for materials plaintiff supplied to Mastro for the project. Consequently, plaintiff sued Mastro, Ernest Bock and Sons, the general contractor, and XL Specialty Insurance Company, the company that issued the payment and performance bond for the project. Mastro is out of business and was never served with the complaint.

The primary issue on appeal concerns plaintiff's right to seek payment under the bond. To be so entitled, the Bond Act requires a person to either have a "direct contract" with the general contractor furnishing the bond, or otherwise provide the general contractor with written notice of the person's intent to become a beneficiary under the bond. Plaintiff acknowledges it did not provide Bock with written notice of its intent to become a beneficiary under the bond; but, plaintiff asserts that a joint checking agreement (the Agreement) it entered into with Bock and Mastro serves as the "direct contract" required by the Bond Act to qualify plaintiff as a beneficiary and assert a claim for payment under the bond.

On cross-motions for summary judgment, Judge William Todd found that the Agreement did not constitute a "direct contract" under the Bond Act. The judge also concluded that plaintiff failed to prove its claim for breach of contract against Bock. We agree and affirm.

The facts are not in dispute. In January 2001, Bock and the Atlantic County Special Services School District entered into a contract for the construction of the school. XL Specialty issued the payment and performance bond. In February 2001, Bock and Mastro executed a purchase order; Mastro was to provide labor, material, *375 and equipment "to complete all unit masonry and unit pavers." Mastro, in turn, requested a quote from plaintiff for materials and supplies for the job. As a condition to supplying the materials, plaintiff requested that the parties enter into a joint checking agreement, a "procedure frequently ... done ... with general contractors... subcontractors, and suppliers." In fact, plaintiff had such an agreement when working with Mastro on at least two previous jobs. A Bock representative prepared the Agreement. It said, in pertinent part:

In consideration that Dial Block Co., Inc (Supplier), will supply material to Mastro Masonry (Subcontractor), for installation at the Atlantic County Special Services School in accordance with the Subcontractor's Contract Agreement, Ernest Bock & Sons, Inc., (General Contractor), hereby agrees that the said materials will be paid for by check(s) made payable jointly to the Supplier and Subcontractor.
Total material cost is not to exceed $125,000.00.

Plaintiff's controller, Barry Pflum, understood that the Agreement did not obligate plaintiff to provide Mastro with materials, and neither Mastro nor Bock were required to order "each and every item from [plaintiff]." According to Pflum, the purpose of the $125,000 limit was to protect Bock's "interest and [Bock's] interest alone."

Approximately fourteen months later, Pflum wrote to Bock's vice president, Anthony DePascale, and informed him that the cost of materials supplied by plaintiff had "far exceeded" the $125,000 limit. By that time, plaintiff had already supplied Mastro with more than $300,000 in supplies. Pflum requested that the Agreement be amended to raise the cap to $500,000. DePascale rejected Pflum's request "due to cost overruns by Mastro Masonry on this project." DePascale acknowledged that Bock had "exceeded the initial joint check amount," but explained that Bock had done so because the company "felt it was in all of our best interest[s] to continue joint payments to minimize both our exposure." According to DePascale, Mastro had "committed to [Bock] that they will continue to make payments to their vendors given this circumstance." Finally, DePascale said: "It would be in your best interest to contact Mastro and make the necessary arrangements." Plaintiff continued to supply materials to Mastro.

In response to the letter, Pflum stated that if plaintiff did not receive the sum due under its regular payment schedule, $44,728.86, it would stop supplying materials to Mastro. Pflum also asked DePascale for the name, address, and telephone number of Bock's bonding company. When plaintiff did not receive the payment, it stopped "servicing" Mastro. On August 8, 2002, plaintiff asserted a claim under the bond for $65,840.73.

In total, Bock issued $347,602.53 in joint checks to plaintiff and Mastro. At some point, well after the $125,000 cap was reached, Bock stopped issuing joint checks and paid Mastro directly so Mastro could meet its payroll. Bock paid Mastro in full.

Against this factual background, we turn to whether the Agreement constituted a "direct contract" within the plain meaning of N.J.S.A. 2A:44-145. If it did, plaintiff could seek payment under the bond without otherwise notifying Bock that plaintiff was a beneficiary of the bond. That statute says, in part,

Any person who may be a beneficiary of the payment bond, as defined in this article, and who does not have a direct contract with the contractor furnishing *376 the bond shall, prior to commencing any work, provide written notice to the contractor by certified mail or otherwise, provided that he shall have proof of delivery of same, that said person is a beneficiary of the bond.
[N.J.S.A. 2A:44-145 (emphasis added).]

The motion judge determined that the Agreement was not a "direct contract." In a thorough and well-reasoned decision, he explained:

First question. What's a direct contract? That term, direct contract, is right there in the statute. It has to mean something. It's subject to interpretation. It's obviously not any contract, because if it was any contract it wouldn't need the word "direct." My sense is that ... a [joint checking agreement] like that at issue here is simply not enough.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Plains Builders, Inc. v. Steel Source, Inc.
408 S.W.3d 596 (Court of Appeals of Texas, 2013)
Diener Brick Co. v. Mastro Masonry Contractor
885 A.2d 1034 (Superior Court of Pennsylvania, 2005)
Gerhold Concrete Co. v. St. Paul Fire & Marine Insurance Co.
695 N.W.2d 665 (Nebraska Supreme Court, 2005)

Cite This Page — Counsel Stack

Bluebook (online)
863 A.2d 373, 374 N.J. Super. 13, Counsel Stack Legal Research, https://law.counselstack.com/opinion/dial-block-co-v-mastro-masonry-njsuperctappdiv-2004.