West Bank Oil, Inc. v. Hartford Acc. and Indem. Co.

500 A.2d 32, 205 N.J. Super. 56
CourtNew Jersey Superior Court Appellate Division
DecidedOctober 22, 1985
DocketA-5190-83T2
StatusPublished
Cited by4 cases

This text of 500 A.2d 32 (West Bank Oil, Inc. v. Hartford Acc. and Indem. Co.) is published on Counsel Stack Legal Research, covering New Jersey Superior Court Appellate Division primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
West Bank Oil, Inc. v. Hartford Acc. and Indem. Co., 500 A.2d 32, 205 N.J. Super. 56 (N.J. Ct. App. 1985).

Opinion

205 N.J. Super. 56 (1985)
500 A.2d 32

WEST BANK OIL, INC., PLAINTIFF-APPELLANT,
v.
HARTFORD ACCIDENT & INDEMNITY COMPANY, DEFENDANT-THIRD PARTY PLAINTIFF-RESPONDENT,
v.
ROBERT R. PERNA AND MARJORIE PERNA, THIRD-PARTY DEFENDANTS.

A-5190-83T2.

Superior Court of New Jersey, Appellate Division.

Submitted September 25, 1985.
Decided October 22, 1985.

*57 Before Judges KING, SIMPSON and SCALERA.

Backes, Waldron & Hill, attorneys for appellant (Brenda F. Engel, of counsel and on the brief).

*58 Williams, Caliri, Miller & Otley, attorneys for respondent (Daniel Kinburn and David Golub, of counsel and on the brief).

The opinion of the court was delivered by KING, P.J.A.D.

This case involves $418,665 in claims under a performance bond issued on public paving contracts. The claimant, West Bank Oil, Inc. was a supplier of liquid asphalt to Cumberland Asphalt Company (Cumberland) which in turn sold its finished product to the paving contractor, Perna Excavating. West Bank's claim that it sold liquid asphalt to a contractor or subcontractor covered under the New Jersey Public Works' Bond Act, N.J.S.A. 2A:44-143, did not survive a motion for summary judgment. Judge Levy decided that West Bank supplied an ordinary materialman, not a contractor or subcontractor, and thus was not protected by the Bond Act. We agree that West Bank's customer was a material supplier and affirm the judgment in the bonding company's favor.

These are the undisputed facts. West Bank is a corporation whose principal business is selling asphalt. One of West Bank's customers was Cumberland Asphalt Company, a company founded by Bruce Eastmunt with a substantial amount of technical advice from West Bank employees. Cumberland made "hot mix" paving material, buying raw materials such as gravel, sand mix and asphalt from suppliers and then selling the finished "hot mix" to contractors doing paving work.

While Eastmunt ran Cumberland, West Bank supplied asphalt on a cash-on-delivery basis. In early 1981, Robert Perna, the principal of Perna Excavating, bought out Eastmunt. Perna had been buying his asphalt from Cumberland but had been unable to buy sufficient quantities because Cumberland's output was limited by its lack of a line of credit with West Bank. Cumberland received all of its asphalt from West Bank. Perna Excavating agreed to take "full responsibility" for Cumberland's *59 debts and West Bank agreed to extend credit to Cumberland. West Bank received a corporate guaranty from Perna Excavating, but Perna refused to give West Bank his personal guarantee on Cumberland's behalf.

Cumberland then changed its name to A & P Asphalt when Vincent Archetto joined Perna as a partner. West Bank asserts that Archetto bought into the company by buying out Eastmunt's shares in early 1981; this conflicts with the deposition statements of West Bank employees maintaining that Perna bought Eastmunt's interests and Archetto came along later. The relationship between West Bank and Cumberland, renamed A & P Asphalt[1], however, remained intact. Perna wrote to West Bank and informed it that Perna Excavating was responsible for Cumberland's debts. Perna was quite involved in Cumberland's operations and Cumberland's checks to West Bank were signed by him.

Perna Excavating was obligated to give the public entities it worked for detailed "producer's analysis of materials and job mix formula" information sheets on which Cumberland had to list the ingredients of the hot mix asphalt it supplied. Perna signed these sheets as Cumberland's president; he also signed them as a representative of Perna Excavating, the actual paving contractor.

Dante Finnochi, West Bank's vice-president, said that Perna would request "mix designs" from West Bank when bidding a State or municipal paving contract. A mix design gives a breakdown of the materials found in a paving "mix" and was required by the entity requesting bids as part of a contractor's total bid. Finnochi said that West Bank salesmen would complete the mix designs and give them to Perna to submit with his bid. He said that a contractor engaged in paving work in this State is required to use one of five grades of mix, I-2 through *60 I-6, on a given stratum of a road. He also said that Cumberland occasionally, though rarely, had one of its own employees on a Perna Excavating jobsite. He noted that Cumberland never delivered its mix to jobsites because it did not own trucks.

Perna Excavating was awarded five paving contracts in Southern New Jersey, which it completed between May 1982 and January 1983. West Bank supplied Cumberland with the "AC-20" asphalt ingredient necessary for the "hot mix" sold to Perna for the five jobs; Cumberland amassed a debt with West Bank of $418,665.66 which remains unpaid. For each of the five projects, defendant Hartford Accident and Indemnity Company (Hartford) issued the bonds required by N.J.S.A. 2A:44-143 guaranteeing Perna Excavating's payment of all its "subcontractors, materialsmen, laborers, persons, firms or corporations" for work done and materials supplied.

After the completion of each contract, West Bank wrote to Hartford, advising it of the sums owed by Cumberland, "a subcontractor of Perna under the contract." Hartford denied liability to West Bank under the bonds.

The New Jersey Bond Act, N.J.S.A. 2A:44-143, says in pertinent part

When public buildings or other public works or improvements are about to be constructed, erected, altered or repaired under contract, at the expense of the state or any county, municipality or school district thereof, the board, officer, or agent contracting on behalf of the state, county, municipality or school district, shall require the usual bond, as provided for by law, with good and sufficient sureties, with an additional obligation for the payment by the contractor, and by all subcontractors, for all labor performed or materials, provisions, provender or other supplies, teams, fuels, oils, implements or machinery used or consumed in, upon, for or about the construction, erection, alteration or repair of such buildings, works or improvements.

N.J.S.A. 2A:44-145 says that someone owed money for labor, material or provisions may bring an action against the surety "80 days after the acceptance" by the public entity of the work performed.

The scope of N.J.S.A. 2A:44-143's coverage was discussed in Morris Co. Industrial Park v. Thomas Nichol Co., 35 N.J. 522 *61 (1961). The Court addressed the contention that the Bond Act covered "any claimant who furnishes materials or labor actually used in the completion of the public work, even where such materials are supplied to another materialman and to one far removed from privity of contract with the general contractor or a subcontractor." Morris Co., supra, at 528. The Court rejected this contention, saying

All this language in the lien law evidences to us without question that the Legislature has limited a right of lien to a materialman supplying either the general contractor or a subcontractor. The words are clear and express and our attention has not been called to any decision anywhere to support plaintiff's broader view.
To turn to the bond act, somewhat different language is used, but we feel constrained to say that it has to be similarly limited. Section 143, previously quoted in full (N.J.S.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Dial Block Co. v. Mastro Masonry
863 A.2d 373 (New Jersey Superior Court App Division, 2004)
Township of Parsippany-Troy Hills v. Lisbon Contractors, Inc.
696 A.2d 1129 (New Jersey Superior Court App Division, 1997)
Sharp v. Zoning Bd. of App., Easton, No. Cv91 028 50 52s (Mar. 31, 1994)
1994 Conn. Super. Ct. 3200 (Connecticut Superior Court, 1994)
Unadilla Silo Co. v. Hess Bros.
586 A.2d 226 (Supreme Court of New Jersey, 1991)

Cite This Page — Counsel Stack

Bluebook (online)
500 A.2d 32, 205 N.J. Super. 56, Counsel Stack Legal Research, https://law.counselstack.com/opinion/west-bank-oil-inc-v-hartford-acc-and-indem-co-njsuperctappdiv-1985.