Pepper Burns Insulation, Incorporated v. Artco Corporation

970 F.2d 1340, 38 Cont. Cas. Fed. 76,362, 1992 U.S. App. LEXIS 15625
CourtCourt of Appeals for the Fourth Circuit
DecidedJuly 10, 1992
Docket91-2178
StatusPublished
Cited by1 cases

This text of 970 F.2d 1340 (Pepper Burns Insulation, Incorporated v. Artco Corporation) is published on Counsel Stack Legal Research, covering Court of Appeals for the Fourth Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Pepper Burns Insulation, Incorporated v. Artco Corporation, 970 F.2d 1340, 38 Cont. Cas. Fed. 76,362, 1992 U.S. App. LEXIS 15625 (4th Cir. 1992).

Opinion

970 F.2d 1340

38 Cont.Cas.Fed. (CCH) P 76,362

PEPPER BURNS INSULATION, INCORPORATED, Plaintiff-Appellee,
and
United States of America, for the Benefit and Use of Pepper
Burns Insulation, Incorporated, Plaintiff,
v.
ARTCO CORPORATION, A Georgia Corporation, Defendant-Appellant,
and
Pyramid Contracting Limited; James P. McClain; Sharon L.
Jelovchan, Defendants.

No. 91-2178.

United States Court of Appeals,
Fourth Circuit.

Argued March 3, 1992.
Decided July 10, 1992.

George Lucus Lewis, Adams, Gardner & Ellis, P.C., Savannah, Ga., argued (Perry Y. Newson, Hafer, Day & Wilson, P.A., Raleigh, N.C., on brief), for defendant-appellant.

Julie A. Davis, Allen Holt Gwyn, Jr., Patton, Boggs & Blow, Greensboro, N.C., argued, for plaintiff-appellee.

Before RUSSELL and LUTTIG, Circuit Judges, and SIMONS, Senior District Judge for the District of South Carolina, sitting by designation.

OPINION

DONALD RUSSELL, Circuit Judge:

This is an appeal from the district court's order granting summary judgment to Pepper Burns Insulation, Inc., a second-tier subcontractor on a federal construction project. Pepper Burns had brought suit against Artco Contracting, Inc., the general contractor on the federal project, to collect under a Miller Act1 payment bond for work completed but unpaid. Artco moved for summary judgment on the grounds that Pepper Burns failed to meet the statutory prerequisites for maintaining an action. Section 2(a) of the Miller Act requires that notice of a claim be given to the bonded contractor within ninety days of the completion of work. Section 2(b) requires that suit be filed within one year of the completion. We find that Pepper Burns failed to timely give the required notice to Artco. Accordingly, we reverse the district court's order granting Pepper Burns summary judgment and remand for entry of an order dismissing the case against Artco.

I.

The parties do not dispute the facts of this case. In March 1987, Artco received a contract from the U.S. Army Corps of Engineers to construct the SOCOM Operations Complex2 at Fort Bragg, North Carolina. In accordance with section 1(a) of the Miller Act, 40 U.S.C. § 270a(a), Artco executed a payment bond for the protection of subcontractors and others furnishing labor and/or material to the project.

Artco hired Pyramid Contracting, Ltd. as a subcontractor. Pyramid, in turn, hired Pepper Burns as a second-tier subcontractor to install flooring. According to an agreement entered into between Pyramid and Pepper Burns dated June 2, 1987, Pepper Burns was to receive $59,466.00 for its work on the project.

Pepper Burns completed its work on July 27, 1989,3 and submitted invoices to Pyramid for payment. Pyramid paid $40,519.40, leaving a balance due of $18,946.60. No dispute existed between the parties concerning completion of the work or the quality of work or materials supplied. After unsuccessful attempts to collect from Pyramid, Pepper Burns then sought recovery of the unpaid balance from Artco under the payment bond.

Section 2(a) of the Miller Act requires that the party seeking recovery on a payment bond "giv[e] written notice to said contractor within ninety days from the date on which such person did or performed the last of the labor or furnished or supplied the last of the material for which such claim is made...." 40 U.S.C. § 270b(a). Therefore, on October 20, 1989, less than 90 days after July 27, Pepper Burns mailed the required notice to Artco of its claim on the bond. Artco received the notice several days later on October 31. Pepper Burns then filed suit against Artco on July 27, 1990.4 Artco initially moved to dismiss the case, alleging that Pepper Burns failed to file its complaint within the one year period required by the Miller Act section 2(b). 40 U.S.C. § 270b(b). The district court denied the motion, holding the filing timely under the statute. Pepper Burns then moved for summary judgment. Artco cross-moved for summary judgment on the alternative grounds that Pepper Burns failed to give notice to Artco within ninety days or that Pepper Burns failed to file its complaint within one year. The district court granted summary judgment for Pepper Burns, again holding Pepper Burns' notice and filing timely under section 2 of the Miller Act.

Artco appeals the decision, contending that the district court erred in not granting Artco summary judgment.

II.

We consider this case de novo under the familiar standard for reviewing motions for summary judgment. See Anderson v. Liberty Lobby, Inc., 477 U.S. 242, 106 S.Ct. 2505, 91 L.Ed.2d 202 (1986).

Although Artco raises two claims on appeal, we find it necessary only to consider its notice claim in order to dispose of this case. The parties do not dispute that notice was mailed by Pepper Burns on October 20, within the statutory ninety-day period, but not actually received by Artco until October 31, outside the statutory window. Thus, we must decide whether mailing or receipt satisfies the notice requirement of § 270b(a).

Section 270b(a) states in part:

Every person who has furnished labor or material in the prosecution of the work provided for in such [federal] contract, in respect of which a payment bond is furnished under section[ ] 270a ... and who has not been paid in full therefor ..., shall have the right to sue on such payment bond ...: Provided, however, That any person having direct contractual relationship with a subcontractor but no contractual relationship express or implied with the contractor furnishing said payment bond shall have a right of action upon the said payment bond upon giving written notice to said contractor within ninety days from the date on which such person did or performed the last of the labor or furnished or supplied the last of the material for which such claim is made....

40 U.S.C. § 270b(a) (emphasis in original). The statute clearly requires timely notice as a condition precedent to the right to maintain suit on a payment bond. Our decision turns on the meaning of "giving written notice." We can then determine if the properly given notice was timely.

The issue presented here is one of first impression for our Court. We look to other Miller Act decisions for rules of general construction.5 Generally, "the Miller Act should receive a liberal construction to effectuate its protective purposes." United States ex rel. Sherman v. Carter, 353 U.S. 210, 216, 77 S.Ct. 793, 796, 1 L.Ed.2d 776 (1957). The Act was intended to protect from non-payment those who furnish labor and materials in federal construction projects. Id.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
970 F.2d 1340, 38 Cont. Cas. Fed. 76,362, 1992 U.S. App. LEXIS 15625, Counsel Stack Legal Research, https://law.counselstack.com/opinion/pepper-burns-insulation-incorporated-v-artco-corporation-ca4-1992.