Stitzer v. United States ex rel. Vaughans

182 F. 513, 105 C.C.A. 51
CourtCourt of Appeals for the Third Circuit
DecidedNovember 22, 1910
DocketNo. 1,405
StatusPublished
Cited by13 cases

This text of 182 F. 513 (Stitzer v. United States ex rel. Vaughans) is published on Counsel Stack Legal Research, covering Court of Appeals for the Third Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Stitzer v. United States ex rel. Vaughans, 182 F. 513, 105 C.C.A. 51 (3d Cir. 1910).

Opinion

CROSS, District Judge.

The suit below was instituted in the name of the'United States, to the use of William E. Vaughan, against James Herbert Stitzer and the Title Guaranty & Surety Company, to recover upon a bond given under the act of Congress approved August 13, 1894 (chapter' 280, 28 Stat. 278 [U. S. Comp. St. 1901, p. 2523]), as amended by an act approved February 24, 1905 (chapter 778, 33 Stat. 811 [U. S. Comp. St. Supp. 1909, p. 948]).

On September 19, 1908, Stitzer entered into a written contract with tlie United States to do certain work at Ft. Mifflin, Pa. On the same-day Stitzer, as principal, and the Title Guaranty & Surety Company, as surety, executed and delivered to the United States, pursuant to the above-mentioned act, a joint and several bond in the penal sum of $738, conditioned that Stitzer should perform the work mentioned in his said [515]*515contract, and should “promptly make full payments to all persbns supplying him or them with labor and materials in the prosecution of the work provided for in the aforesaid contract.” On September 39, 1908, Stitzer, by a written contract between him and William R. Vaughan, the use plaintiff, subcontracted to Vaughan the carpenter work mentioned in Stitzer’s contract with the United States. The work under Stitzer’s contract was completed March 35, 1909, and the United States settled with him on July 30th of that year. Stitzer having failed to pay Vaughan, he on October 31st next ensuing instituted suit in the court below to recover the amount of his claim upon the bond above mentioned. The question involved herein is whether a person who has supplied labor and materials to a contractor with the United States has the right to bring an independent action on the bond given under the act of Congress above referred to, before the expiration of six months from the completion and final settlement of the contract. The trial judge submitted the questions of fact involved in the case to the jury, who returned a verdict for the plaintiff, reserving, however, the defendant’s request to charge that under all the evidence the verdict must be for the defendants. Subsequently the defendants moved for judgment non obstante veredicto. This motion, after argument, was denied, and a judgment entered upon the verdict for the sum of $634.33. The statute in question, so far as pertinent, is as follows:

“That hereafter any person or persons entering into a formal contract with the United States for the construction of any public building, or the prosecution and completion of any public work, or for repairs upon any public building or public work, shall be required, before commencing such work, to execute the usual penal bond, with good and sufficient sureties, with the additional obligation that such contractor or contractors shall promptly make payments to all persons supplying him or them with labor and materials in the prosecution of the work provided for in such contract; and any person, company or corporation who has furnished labor or materials used in the construction or repair of any public building or public work, and payment for which has not been made, shall have the right to intervene and be made a party to any action instituted by the United States on the bond of the contractor, and to have .their rights and claims adjudicated in such action and judgment rendered thereon, subject, however, to the priority of the claim and judgment of the United States. If the full amount of the liability of the surety on said bond is sufficient to pay the full amount of said claims and demands, then, after paying the full amount due the United States, the remainder shall be distributed pro rata among said intervenors. If no suit should be brought by the United States within six months from the completion and final settlement of said contract, then the person or persons supplying the contractor with labor and materials shall, upon application therefor, and furnishing affidavit to the Department under the direction of which said work has been prosecuted that labor or materials for the prosecution of such work has been supplied by him or them, and payment for which has not been made, be furnished with a certified copy of said contract and bond, upon which he or they shall have a right of action, and shall be, and are, hereby authorized to bring suit in the name of the United States in the circuit court of the United States in the district in which said contract was to be performed and executed, irrespective of the amount in controversy in such suit, and not elsewhere, for his or their use and benefit, against said contractor and his sureties, and to prosecute the same to final judgment and execution; provided, that where suit is instituted by any of such creditors on the bond of the contractor, it shall not'be commenced until after the complete performance of said contract and final settlement thereof, and shall be commenced within one year after the performance and final settlement of said contract, and not later; and provided further, that where suit is so instituted by a creditor or by creditors, only one action shall [516]*516be brought and any creditor may file bis claim in sucb action and be made party thereto within one year from the completion of the work under said contract, and not later.”

The learned judge below, in his opinion in denying the motion for judgment non obstante veredicto, said:

“And for the purpose of this case it may also be assumed — but without deciding the point — that an independent action by the subcontractor should have been deferred until six months had elapsed from July 20th, the date of final settlement. But it still remains to inquire whether the defendants are in a position to take advantage of this defect in procedure, and in my opinion their objection should not be allowed to prevail. The defendants are setting up what is essentially a statute of limitation. It differs only from the ordinary statutes in the unessential particular that by it a time is fixed before which suit may not be brought, while by- their provisions a time is fixed after which such action may not be entertained. But it is well settled that the defendant cannot take advantage of a statute of limitations unless in some way it is formally set up as a defense.”

In this we think he erred. He treated the statute in question as a statute of limitation and concluded that, because it had not been pleaded; it had been waived. He cites authorities to show, what is undoubtedly the law, that a failure to plead such a statute constitutes a waiver thereof, but none to show that a statute, like the one in question, is, in any sense, a statute of limitation, or one which like that statute must be pleaded. To call the statute in question a limitation is not only a misnomer, but an absolute misconception of the purpose of the act, which was to give any person or persons, supplying labor and materials to a contractor with the government, a right of action, where before none existed. The act- was not intended to, and does not, bar any cause of action, but rather creates one. The lapse of six months was a condition precedent to the plaintiff’s right to sue. In other words, a conditional cause of action only was conferred. Such cause of action was created by the statute and must be instituted pursuant to the terms and conditions of the statute, and not otherwise. No party prior to the expiration of six months from the conpletion and final settlement of a. contract, except the United States, was thereby authorized to sue upon the bond.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
182 F. 513, 105 C.C.A. 51, Counsel Stack Legal Research, https://law.counselstack.com/opinion/stitzer-v-united-states-ex-rel-vaughans-ca3-1910.