Morley Const. Co. v. Maryland Casualty Co.

84 F.2d 522, 1936 U.S. App. LEXIS 4522
CourtCourt of Appeals for the Eighth Circuit
DecidedJune 22, 1936
DocketNo. 10477
StatusPublished
Cited by4 cases

This text of 84 F.2d 522 (Morley Const. Co. v. Maryland Casualty Co.) is published on Counsel Stack Legal Research, covering Court of Appeals for the Eighth Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Morley Const. Co. v. Maryland Casualty Co., 84 F.2d 522, 1936 U.S. App. LEXIS 4522 (8th Cir. 1936).

Opinion

BOOTH, Circuit Judge.

This is a suit in equity brought by the Maryland Casualty Company against the Morley Construction Company and the Merchants Bank of Kansas City, Mo. Diverse citizenship is alleged and admitted.

It appears that plaintiff executed a surety bond for defendant Morley Construction Company in connection with a construction contract entered into between said Morley Construction Company and the United States. The bond, dated on or about July 28, 1932, was in the standard form of performance bonds.

The term “defendant” hereinafter used means the Morley Construction Company.

[523]*523Plaintiff seeks by its complaint the following relief: (1) Exoneration by the defendant from payment of any bills for labor and materials furnished under said construction contract; (2) subrogation to defendant’s claim against the United States by reason of certain payments alleged to have been made by plaintiff to creditors of the Morley Construction Company; (3) specific performance of a certain contract (Exhibit A) entered into between plaintiff and said defendant subsequent to the making of said bond.

As to Specific Performance of Exhibit A.

It appears that in carrying out the construction contract, the defendant, Morley Construction Company, became involved in financial difficulties, and an agreement (Exhibit A, set out in the margin1) was entered into between it and the Maryland Casualty Company, whereby the Casualty Company agreed to advance to the Construction Company the sum of $5,000 to be placed in a joint account. The Casualty Company also agreed: “Fifth: The Maryland Casualty Company further agrees to [524]*524place on deposit in said' account to the credit of the Morley Construction Company moneys to pay off plasterers’ claims which have not been paid by D. Giamberardino & Sons who employed said plasterers and also sufficient money to complete the Giamberardino plastering contract if the amount to be paid to complete said contract is deemed reasonable and satisfactory.”

The Construction Company also agreed to place a certain amount in a joint account.

The Casualty Company did not fulfill all of the covenants assumed by it in the agreement. On cross-examination, the witness Herbert F. Morley, president of the Morley Construction Company, testified as follows:

“Q. I see where the petition states that they agreed to pay off plasterers’ claims and also sufficient money to complete the plastering contract. Could you tell the Court the sum total of those two items, that is, the expense of this plastering contract, that is, those that had not been paid, and also sufficient to complete the plastering contract? What is the total of that, if you know? A. Well, they paid $10,700 and some odd dollars. They paid $5,000.-00 and they paid $5,740.00 toward the completion of the plastering contract. * * *
“Demand was made on the Maryland by the witness for them to pay the plastering. The new subcontractor was the Hudson Plastering Corporation. The final bill for this plastering was $15,000 of which $7,500 was unpaid. When the witness requested Kelly to give him money to pay the first payment at the end of the first month’s work by the Hudson Plastering Company, Kelly advised him to pay it out of the funds of the joint account.
“Q. Well, did he say anything as to whether he would or wouldn’t carry out his contract? A. Not at that time, no, sir.
“Q. Did he at any other time? A. Yes, sir.
“Q. What was it he said? A. Well, when the next month’s payment came due, the first month’s payment amounted to approximately $7,500 and request was made that the money be advanced and he advised that I pay it and take care of it out of the funds of the joint account. The next month’s account came due and left a balance of $2,500 on the previous month, together with about $6,000 from the ensuing month, and he suggested that I take care of that out of the funds in the joint account, and there wasn’t enough money available for that, so in order to keep the plastering contractor on the job and have him finish up, I did finally pay him $2,500 out of the joint account and whether at that time or within a few days after that, when I discussed it with him again, Mr. Kelly made the remark that the Maryland Casualty Company was not going to put any more money into that account or that job.

“(The witness made no further demand upon Kelly for payment).”

The witness Kelly, an attorney employed in the office of the Casualty Company at Buffalo, N. Y., testified as follows: “In addition to the $í0,700 the Maryland agreed to take care of the disputed plastering claims if the Veterans’ Administration ruled that it was necessary to pay them. They were never paid because it was ruled that the Veterans’ would stand on the receipts as given by the employees. The letter to the Veterans’ Administration, Plaintiff’s Exhibit 4, the witness thought had been dictated by B. D. Morley, and Mr. Cushwa. At the time, Herbert Morley and the witness discussed the payment of the plasterers’ bills. There was an estimate coming due on the job and the witness said to Mr. Morley, ‘Are you going to pay that part on the plaster contract out of the estimate, just as we understood,’ and Morley did so. That Morley did ask him to pay the Hudson claims and he told him to pay it out of the estimate coming due.”

The court found as to this matter as follows:

“It was further stipulated in this written agreement that the Casualty Company, in addition to the $5,000 to be deposited by it in the joint account, would advance to the defendant and deposit in the said account a sufficient sum of money to pay off all plasterers’ claims unpaid and a further sufficient sum of money to complete the plastering. * * *

“Pursuant to the agreement referred to in finding-of fact No. 2, the Casualty Company and the Construction Company deposited $5,000 each in the joint account and the Casualty Company made a further deposit in the joint account of $5,700 but it did not deposit in the joint account a sufficient -sum • of money to complete the plastering contract.”

[525]*525As conclusions of law the court found: “Plaintiff is not entitled to a decree of specific performance of the agreement referred to in finding of fact No. 2. * * * ”

We cannot agree with this conclusion of the trial court.

Acquiescence by defendant in a modification of the contract, Exhibit A, which modification was thereafter carried out, deprives the conduct of the plaintiff of any taint of inequity. Becker v. Becker, 250 Ill. 117, 95 N.E. 70, Ann.Cas.1912B, 275; Langley v. Devlin, 95 Wash. 171, 163 P. 395, 4 A.L.R. 32.

Such acquiescence, we think, was shown by the evidence in the case at har.

We do not wish it to be thought that we are departing from the well-established rules regarding the granting of the remedy of specific performance. Such is not our intention.

This court, in Shubert v. Woodward, 167 F. 47, at page 54, has said: “The specific performance of a contract by a court of equity is not a matter of right. It rests in the discretion of the court, not in its arbitrary whimsical will, but in its sound judicial discretion informed and directed by the established principles, rules, and practice of equity jurisprudence. Hennessey v.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

United States ex rel. Atkins v. Reiten
191 F. Supp. 864 (D. Alaska, 1961)

Cite This Page — Counsel Stack

Bluebook (online)
84 F.2d 522, 1936 U.S. App. LEXIS 4522, Counsel Stack Legal Research, https://law.counselstack.com/opinion/morley-const-co-v-maryland-casualty-co-ca8-1936.