Reisterstown Lumber Co. v. Tsao

574 A.2d 307, 319 Md. 623, 1990 Md. LEXIS 90
CourtCourt of Appeals of Maryland
DecidedJune 1, 1990
Docket99 September Term, 1989
StatusPublished
Cited by11 cases

This text of 574 A.2d 307 (Reisterstown Lumber Co. v. Tsao) is published on Counsel Stack Legal Research, covering Court of Appeals of Maryland primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Reisterstown Lumber Co. v. Tsao, 574 A.2d 307, 319 Md. 623, 1990 Md. LEXIS 90 (Md. 1990).

Opinion

RODOWSKY, Judge.

In this case the Court must decide whether the “residential exception” to the mechanics’ lien law contained in *625 Maryland Code (1974, 1988 Repl.Vol.), § 9-104 of the Real Property Article (RP), applies when homeowners contract to have a single family dwelling built on their land with the intent to make it their residence, but, during the course of construction, decide to place the house on the market for sale. 1

Appellant, The Reisterstown Lumber Company (RLC), supplied materials for a house being constructed for the appellees, Iky and Josephine P-Y Tsao. 2 RLC sought a mechanics’ lien for balances owed to RLC by the contractor, L.W. Marino, Inc. (Marino). The Tsaos invoked § 9-104(a)(2). Section 9-104(a) provides:

“(a) Notice required to entitle subcontractor to lien. —(1) A subcontractor doing work or furnishing materials or both for or about a building other than a single family dwelling being erected on the owner’s land for his own residence is not entitled to a lien under this subtitle unless, within 90 days after doing the work or furnishing the materials, the subcontractor gives written notice of an intention to claim a lien substantially in the form specified in subsection (b) of this section.
“(2) A subcontractor doing work or furnishing materials or both for or about a single family dwelling being erected on the owner’s land for his own residence is not entitled to a lien under this subtitle unless, within 90 days after doing work or furnishing materials for or about that single family dwelling, the subcontractor gives written notice of an intention to claim a lien in accordance with subsection (a)(1) of this section and the owner has not made full payment to the contractor prior to receiving the notice.”

In the circuit court RLC argued that the residential exception did not apply because the house was not “being *626 erected” on the land of the owner “for his own residence.” The trial court’s analysis was that the phrase “being erected ... for his own residence” could relate to an owner’s intention in three possible ways: (1) intent when the construction contract was signed, (2) the dominant intent over the total period of construction, and (3) intent when the subcontractor furnished materials for which the lien is sought.

The trial court concluded that the underlying purpose of the exception was furthered by focusing on “the total transaction” rather than “any isolated portion thereof.” Viewing the intent of the appellees from the total transaction perspective the court found that the “primary and driving motivation” was to construct a building as the Tsaos’ residence.

RLC appealed and this Court issued the writ of certiorari on its own motion prior to consideration by the Court of Special Appeals.

The facts of the case are that on October 9, 1986, the Tsaos contracted with Marino for the construction of a single family dwelling on their land. At that time they intended to reside in the house upon its completion. Marino began construction in January 1987 and, after experiencing financial difficulty and failing fully to complete the house, ceased work in January of 1988.

The Tsaos had obtained a construction loan. The lender made periodic advances at scheduled points of progress toward completion of the work. The lender’s checks for each draw were issued to the Tsaos who endorsed the checks to Marino.

RLC began supplying Marino with materials for use in the construction of the house in January 1987, and RLC made its last delivery in December 1987. RLC’s bills to Marino were to be paid within thirty days. Marino timely paid each of RLC’s bills rendered for deliveries through June 1987, a total of $44,995.75. Marino, however, failed to pay at all for materials that RLC delivered beginning in *627 July and thereafter. The unpaid purchase prices (excluding late charges) of materials delivered to Marino, by month, are:

July 1987 $ 9,392.18

August 1987 1,900.36

September 1987 2,010.69

October 1987 1,039.17

December 1987 545.51

Total $14,887.91

The house was framed and under roof by March 2, 1987. At approximately that time the Tsaos first noticed that a cemetery was visible from their second floor bedroom window. Their cultural and religious beliefs proscribe residing in direct view of a cemetery. They decided, “in the summer of 1987,” per the trial judge’s finding of fact, to sell the house when construction was complete. In October of 1987 the Tsaos listed the house with a real estate broker.

In late November 1987 the final draw was paid to Mari-no. 3 On March 2, 1988, RLC served its notice of an intention to claim a mechanics’ lien. RLC filed suit to enforce the mechanics’ lien on May 20, 1988.

The trial judge found that no contract of sale was ever presented for the house which remained vacant until the Tsaos occupied it. In late June or early July 1988, they took the house off the market. They moved into the house in August 1988 and have resided there to date.

The current mechanics’ lien statute was enacted by Ch. 349 of the Acts of 1976 as an emergency measure following the decision in Barry Properties, Inc. v. The Fick Bros. Roofing Co., 277 Md. 15, 353 A.2d 222 (1976), which had invalidated prehearing seizure features of the prior law, Md.Code (1974, 1975 Cum.Supp.), RP §§ 9-101 through 9-113. This Court has said, speaking of the prior law, that it should be liberally construed in favor of lien claimants. See *628 Clark Certified Concrete Co. v. Lindberg, 216 Md. 576, 582, 141 A.2d 685, 688 (1958); Johnson v. Metcalfe, 209 Md. 537, 543, 121 A.2d 825, 828 (1956); T. Dan Kolker, Inc. v. Shure, 209 Md. 290, 296, 121 A.2d 223, 226 (1956). But we are here concerned particularly with the residential exception which was added to the current statute by Ch. 251 of the Acts of 1982. That exception’s clear purpose is to protect from double payment the owner of a “single family dwelling being erected on the owner’s land for his own residence.”

RLC’s initial argument rests on § 9 — 104(f)(3) which was added to the current law as part of Ch. 251 of the Acts of 1982. As so amended § 9-104(f) reads:

“Payments by owner to contractor after notice; limitation on lien against certain single family

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Arfaa v. Martino
946 A.2d 995 (Court of Appeals of Maryland, 2008)
Martino v. Arfaa
906 A.2d 945 (Court of Special Appeals of Maryland, 2006)
Ridge Heating, Air Conditioning and Plumbing, Inc. v. Brennen
783 A.2d 691 (Court of Appeals of Maryland, 2001)
Ridge Heating, Air Conditioning & Plumbing, Inc. v. Brennen
762 A.2d 161 (Court of Special Appeals of Maryland, 2000)
WINKLER CONSTRUCTION CO. INC. v. Jerome
734 A.2d 212 (Court of Appeals of Maryland, 1999)
York Roofing, Inc. v. Adcock
634 A.2d 39 (Court of Appeals of Maryland, 1993)

Cite This Page — Counsel Stack

Bluebook (online)
574 A.2d 307, 319 Md. 623, 1990 Md. LEXIS 90, Counsel Stack Legal Research, https://law.counselstack.com/opinion/reisterstown-lumber-co-v-tsao-md-1990.