Warner Co. v. Leedom Construction Co.

97 A.2d 884, 48 Del. 58, 9 Terry 58, 1953 Del. LEXIS 69
CourtSupreme Court of Delaware
DecidedJune 13, 1953
Docket1
StatusPublished
Cited by17 cases

This text of 97 A.2d 884 (Warner Co. v. Leedom Construction Co.) is published on Counsel Stack Legal Research, covering Supreme Court of Delaware primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Warner Co. v. Leedom Construction Co., 97 A.2d 884, 48 Del. 58, 9 Terry 58, 1953 Del. LEXIS 69 (Del. 1953).

Opinion

Southerland, C. J.:

This appeal involves the construction and effect of the provision of the Delaware mechanics’ lien law requiring apportionment of a joint lien claimed upon two or more structures.

The facts are these:

Some time in 1949 appellee Leedom Construction Company began the work of constructing a residential building development upon a tract of land in New Castle County owned hy it. Franklin Builders, Incorporated, was the general contractor; and Masonsteel Construction Company was a subcontractor engaged to install, among other things, the concrete cellars, foundations and sidewalks. Warner Company, whose business is the *60 sale of concrete and other materials for construction purposes, was engaged by the Masonsteel Construction Company to supply concrete and other materials required by the latter. These parties will be referred to as Leedom, Franklin, Masonsteel and Warner.

Beginning on September 19, 1949, and ending on November 28, 1950, Warner supplied to the building project large quantities of concrete and other materials. These materials were incorporated into a large number of the houses that were built in the development. The materials were sold on open account and supplied as ordered from time to time. Franklin’s method of development was to build several houses at a time and as these were sold to build others, depending upon the demand. Franklin’s President testified: “We built them as we sold them.” The materials were delivered to the site of the development but usually not to any particular lot or structure. The material in a single delivery was frequently incorporated into two or more structures, and no record was kept — in many cases no record could be kept — of the quantity or identity of the materials used in a particular structure.

The materials furnished by Warner were incorporated into eighty-seven houses and appurtenant pavements. About two-thirds of the houses had been sold at the time when the present suit was filed.

Masonsteel was apparently in financial difficulties shortly after undertaking its work upon the project. In June, 1950, its unpaid balance with Warner was so large that an arrangement was effected under the terms of which future supplies were paid for by Franklin. The parties are not in accord as to the interpretation to be put upon the new arrangement; but in the view we take of the matter this dispute is unimportant. It is sufficient to note that the balance due is attributable to materials delivered prior to June 20,1950.

On November 28, 1950, when Warner made its last delivery of materials to the project, there was due to it from Masonsteel *61 the sum of $16,318.25. Masonsteel was then apparently insolvent, and on February 12, 1951, Warner filed in the Superior Court a complaint and statement of claim in a mechanics’ lien proceeding, asserting a lien upon all the eighty-seven structures above referred to. The statement of claim averred that all of the materials supplied by it had been furnished upon the credit of all the structures and premises on which the lien was asserted, and that the entire claim was due upon the structures and premises considered as a unit, that is, a continuous, single building development. Alternatively, Warner averred that if apportionment of the claim was required, it had in fact made such apportionment, as appeared from an exhibit attached to the statement of claim.

Leedom answered, setting up several defenses, only one of which we need consider. This is the defense that Warner had failed to set forth the amount claimed to be due upon each such structure, as required by the mechanics’ lien statute. The court below upheld this defense and dismissed the action.

The pertinent provisions of the statute are as follows:

“It shall and may be lawful for any person or persons having performed or furnished work and labor or material or both, to «an amount exceeding twenty-five dollars in or for the erection, alteration, or repair of any house, building or structure, in pursuance of any contract, express or implied, with the owners of such house, building, or structure, or with the agent of such owner, or with any contractor who shall have contracted for the erection, alteration, or repair of the same, and for the furnishing of the whole or any part of the materials therefor, including any person who shall have performed or furnished work and labor or material, or both, for or at such house, building, or structure, under a contract with or order from any subcontractor, to obtain a hen upon such building, house or structure and upon the ground upon which the same may be situated, or erected, subject, however, to the following restrictions, limitations and qualifications, that is to say:”

*62 After prescribing certain conditions respecting the times within which statements of claims must be filed and specifying the matters that must be set forth therein, the statute provides:

“Any judgment obtained upon such claim, as hereinafter provided, shall become a lien upon such building, house or structure, and upon the ground upon which the same is situated, erected or constructed, and shall relate back to the day upon which said work and labor was begun, or the furnishing of said material was commenced. In every case in which one claim for work and labor or materials shall be filed by the same person or persons against two or more buildings, houses, or structures owned by the same person or persons, for building, altering or repairing two or more buildings or structures owned by the same person or persons, the claimant shall, at the time of filing such joint claim, designate the amount which he claims to be due to him on each of such buildings, houses or structures.” 1935 Code, Par. 3324. 1

The principal question before us is whether the requirement of apportionment embodied in the last quoted sentence is applicable to the case at bar; that is, whether apportionment is required of materials furnished to separate houses in a building development constructed as a unit or as a series of units.

Leedom contends that the statute is mandatory in all cases and must he complied with, else the claimant obtains no hen. Warner replies that the statute should be liberally construed in favor of the claimant; that the entire building development, for the purpose of the mechanics’ lien law, constitutes one entire unit to which materials were furnished under one contract applicable to the development as an entirety; and that the requirement of apportionment is inapplicable to such a case and a single lien on the entire development may be obtained.

*63 Although not stated in that form, Warner’s contention is in effect that the statutory provision for apportionment is directory and not mandatory. Is this construction acceptable?

The statute is mandatory in form. It says that “in every case” in which a lien is claimed on two or more structures, “the claimant shall, at the time of filing such joint claim, designate the amount” claimed to be due upon each structure.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Waggoner v. Laster
581 A.2d 1127 (Supreme Court of Delaware, 1990)
Steel Suppliers, Inc. v. Ehret, Inc.
486 A.2d 32 (Superior Court of Delaware, 1984)
Wilmington Trust Company v. Branmar, Inc.
353 A.2d 212 (Superior Court of Delaware, 1976)
Ramsey v. DiSabatino
347 A.2d 659 (Superior Court of Delaware, 1975)
Silverside Home Mart, Inc. v. Hall
345 A.2d 427 (Superior Court of Delaware, 1975)
Harrogate Construction Co. v. Joseph Haas Co.
250 A.2d 376 (Superior Court of Delaware, 1969)
Erect-Rite Construction Co. v. DeChellis
193 A.2d 545 (Superior Court of Delaware, 1963)
Whittington v. Segal
193 A.2d 534 (Superior Court of Delaware, 1963)
State Ex Rel. State Highway Department v. 62.96247 Acres of Land
193 A.2d 799 (Superior Court of Delaware, 1963)
Charles G. Taylor & Sons, Inc. v. Brentwood Construction Co.
189 A.2d 414 (Superior Court of Delaware, 1963)
Lightburn v. Delaware Power & Light Company
158 A.2d 919 (Supreme Court of Delaware, 1960)
McHugh Electric Co. v. Hessler Realty & Development Co.
129 A.2d 654 (Supreme Court of Delaware, 1957)
In Re Estate of Klingaman
128 A.2d 311 (Supreme Court of Delaware, 1957)
Di Mondi v. S. & S. Builders, Inc.
124 A.2d 725 (Supreme Court of Delaware, 1956)
Poole v. Oak Lane Manor, Inc.
118 A.2d 925 (Superior Court of Delaware, 1955)
Paladinetti v. Oak Lane Manor, Inc.
116 A.2d 173 (Superior Court of Delaware, 1955)
Oscar George, Inc. v. Potts
115 A.2d 479 (Supreme Court of Delaware, 1955)

Cite This Page — Counsel Stack

Bluebook (online)
97 A.2d 884, 48 Del. 58, 9 Terry 58, 1953 Del. LEXIS 69, Counsel Stack Legal Research, https://law.counselstack.com/opinion/warner-co-v-leedom-construction-co-del-1953.