Charles G. Taylor & Sons, Inc. v. Brentwood Construction Co.

189 A.2d 414, 56 Del. 8, 6 Storey 8, 1963 Del. Super. LEXIS 129
CourtSuperior Court of Delaware
DecidedMarch 14, 1963
Docket1089
StatusPublished
Cited by4 cases

This text of 189 A.2d 414 (Charles G. Taylor & Sons, Inc. v. Brentwood Construction Co.) is published on Counsel Stack Legal Research, covering Superior Court of Delaware primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Charles G. Taylor & Sons, Inc. v. Brentwood Construction Co., 189 A.2d 414, 56 Del. 8, 6 Storey 8, 1963 Del. Super. LEXIS 129 (Del. Ct. App. 1963).

Opinion

Lynch, Judge.

Plaintiff sued in a mechanics’ lien proceeding. By its statement of claim it sought to recover $969.00 from the general contractor and impose a mechanics’ lien on the property of Mr. and Mrs. Michael M. Monte Bell.

Brentwood Construction Company, the general contractor, went bankrupt and only Mr. and Mrs. Monte Bell defended. They filed an answer and excepted to the statement of claim. They asserted in their First Affirmative Defense that the statement of claim did not state a claim against them; likewise they asserted in their Sixth Affirmative Defense that the statement of claim fails “to set forth a Bill of Particulars showing the kind and amount of labor done or materials furnished as required by Title 25, Del. C. § 2712 (b) (4) ”. Generally speaking, .their answers put the plaintiff on “strict proof” of the allegations of proof.

I take up first defendants’ contention that the statement of claim is defective.

Defendants point out that the statement of claim sought to enforce a mechanics’ lien for materials furnished in connection with the construction of a building on the property of the defendant, Michael Monte Bell, being Lot No. 1, Block Q, Sharpley; they argue that the relevant paragraphs of the statement of claim are as follows:

“4. The materials hereafter referred to were fur-inshed by Charles G. Taylor & Sons, Inc. in and for the erection and construction and upon the credit of the build- *10 inig or structure pursuant to and upon the order of the said Brentwood Construction Company, general contractor, who had a contract with Mr. & Mrs. Michael M. Monte Bell, owners or reputed owners.
“5. The amount claimed to be due to Charles G. Taylor & Sons, Inc., is NINE HUNDRED SIXTY-NINE DOLLARS ($969.00), with lawful interest on same from June 15, 1961, and is for hardwood floors in and for the erection and construction of said building or structure and on the credit of the same. A Bill of Particulars of the kind and amount of materials furnished is annexed hereto.
“6. The time when the furnishing of materials was commenced was May 26, 1961, and the time when the furnishing of materials was finished was June 15, 1961.
“8. The materials were furnished on the credit of said building or structure.”

Defendants argue there is not one word in this statement of claim indicating that any amount is claimed to be due for labor furnished by the plaintiff in connection with the construction of the building in question.

Defendants asserted Title 25, Del. C. § 2712(b) requires that a statement of claim seeking to establish a lien for the labor rendered to set forth the following:

“(4) The amount claimed to be due, the nature and kind of the labor done or materials furnished, with a bill of particulars annexed, showing the kind and amount of labor done or materials furnished;
“(5) The time when the doing of the labor or the furnishing of the material was commenced;
“(6) The time when the doing of the labor or the furnishing of the material was finished; * * *
*11 “(8) That the labor was. done or the materials were-furnished on the credit of said structure.”

Defendants further argue that the statement of claim fails to even mention “labor” and so it cannot comply with the specific statutory requirements.

All evidence admitted at the trial relating to labor preformed by plaintiff was received subject to defendants’ objection; defendants urge such evidence must now be stricken from the record. Defendants’ argument is along these lines: plaintiff is not entitled to a mechanics’ lien for any labor furnished or for any overhead and profit; plaintiff’s witness admitted that the profit and overhead item on the plaintiff's invoice had an element of labor in it; (Tr. 27, 35) and say defendants, plaintiff failed, however, to offer any evidence tending to show -the amount of overhead and profit which was attributable to labor or which was attributable to materials. The conclusion advanced by defendants is that plaintiff is, therefore, not entitled to recover any portion of the overhead and profit. They say that the only claim properly before this Court is one for materials furnished.

Plaintiff notes that the Bill of Particulars attached to its statement of claim shows:

“complete contract of job .............-....... $969.00

work started May 26, 1961

work finished June 15, 1961”

It is plaintiff’s contention that the lien statement, as a whole, indicates that the claim is for both labor and material, and it argues the “strict construction” doctrine as to the Mechanics’ Lien Statute was abandoned by our Supreme Court in Warner Co. v. Leedom Constr. Co. 9 Terry 58, 97 A.2d 884 (1953).

*12 Plaintiff cites 57 C.J.S. Mechanics’ Liens § 150, where it is stated:

“* * *. in determining its sufficiency, the lien statement must be construed as a whole, and an exhibit, as well as the affidavit verifying the claim, may be deemed a part of the statement for this purpose.”

I agree with this statement of law and adopt it as applicable to the case at bar.

Defendants cite Mayor and Council of Wilmington v. Recony Sales & Engineering Corporation, 5 Storey 129, 185 A.2d 68 (1962) and attempt to argue from this case, and contend it gives them some comfort. In my opinion, however, it gives them no solace. I find and hold that plaintiff’s statement of claim is sufficient under our present rules of pleading and that its purpose shows it was to recover for an entire contract to lay hardwood floors, which would, I am sure, include material and labor incident thereto.

I entertain considerable concern as to whether plaintiff properly proved its claim. It was clear that plaintiff’s witness Taylor did not show an entire familiarity with the work done or otherwise comply with the usual type of proof in cases of this character. No proper testimony was offered or adduced by plaintiff in support of its statement of claim in the sense of showing what was done. The deficiencies are argued at length in defendants’ brief.

Taylor testified as to the contract between plaintiff and Brentwood Construction Company but on cross examination didn’t help his case and in light of defendants’ its case. Primarily plaintiff relied on copies of invoices evidence I am constrained to hold plaintiff failed to prove which it says it had submitted to Brentwood Construction *13 Company. No effort was made to adduce its records show-nig book entries on the job.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Reliable Collection Agency, Ltd. v. Aquarius Industries, Inc.
535 P.2d 129 (Hawaii Supreme Court, 1975)
G. R. Sponaugle & Sons, Inc. v. McKnight Construction Co.
304 A.2d 339 (Superior Court of Delaware, 1973)
Erect-Rite Construction Co. v. DeChellis
193 A.2d 545 (Superior Court of Delaware, 1963)

Cite This Page — Counsel Stack

Bluebook (online)
189 A.2d 414, 56 Del. 8, 6 Storey 8, 1963 Del. Super. LEXIS 129, Counsel Stack Legal Research, https://law.counselstack.com/opinion/charles-g-taylor-sons-inc-v-brentwood-construction-co-delsuperct-1963.