Ami Operating Partners Ltd. Partnership v. Jad Enterprises, Inc.

551 A.2d 888, 77 Md. App. 654, 1989 Md. App. LEXIS 14
CourtCourt of Special Appeals of Maryland
DecidedJanuary 9, 1989
Docket544, September Term, 1988
StatusPublished
Cited by1 cases

This text of 551 A.2d 888 (Ami Operating Partners Ltd. Partnership v. Jad Enterprises, Inc.) is published on Counsel Stack Legal Research, covering Court of Special Appeals of Maryland primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Ami Operating Partners Ltd. Partnership v. Jad Enterprises, Inc., 551 A.2d 888, 77 Md. App. 654, 1989 Md. App. LEXIS 14 (Md. Ct. App. 1989).

Opinion

WILNER, Judge.

The Circuit Court for Anne Arundel County declared that appellee (Fairmount) was entitled to a mechanics’ lien in the amount of $50,664.75 on certain property comprising the Holiday Inn at Baltimore-Washington International Airport. The related business entities that own, lease, and manage that hotel, to whom we shall collectively refer as AMI, appeal that decision, complaining that:

*659 I. The Maryland mechanics’ lien law is unconstitutional because it
(1) deprives owners of their property without due process of law; and
(2) allows the State to engage in a “taking” of private property for a private use.
II. The trial court erred in
(1) admitting into evidence certain invoices produced for the first time at trial;
(2) determining that December 19, 1986, was the date of last delivery;
(3) considering certain “unsigned” invoices; and
(4) awarding pre-judgment interest.

We find no merit in AMI’s first complaint or in parts (2), (3), and (4) of its second complaint. We do find partial merit in argument 11(1), however, and shall therefore remand the case for an appropriate amendment to the judgment.

Background

In the spring of 1986, AMI hired Prime Construction Company, a sister company of AMI, to do certain renovation work at the hotel. Prime subcontracted a portion of that work to MJY General Contractors, which, in turn, through an oral agreement, purchased building materials from Fair-mount.

From July through December of 1986, Fairmount allegedly supplied MJY with goods having a value of $75,147.40. In September and October, MJY paid Fairmount a total of $9,000. In December, Fairmount received a third payment of $24,750 in the form of a check drawn by Prime and made payable to both Fairmount and MJY. Later that month, MJY walked off the job and apparently “disappeared,” leaving $41,397.40 of its debt to Fairmount unpaid.

On March 18, 1987, Fairmount gave AMI written notice of its intention to claim a mechanics’ lien. When that threat proved unavailing, it proceeded to file a petition for the lien. On August 21, 1987, the court entered an interlocutory *660 order establishing a lien in the amount claimed—$41,397.40. AMI responded with a motion to dismiss the petition on the ground that the mechanics’ lien law is unconstitutional. After a full evidentiary hearing, the court denied AMI’s motion and entered a final order establishing a lien in the amount of $50,664.75—$41,397.40 in principal debt found to be due and $9,267.35 in pre-judgment interest.

I. Constitutionality

AMI mounts a dual attack on the validity of the law, complaining, first, that it deprives an owner of his property without due process of law and, second, that it results in an unconstitutional “taking” of property. We reject both challenges.

(1) Due Process

In Barry Properties v. Fick Bros., 277 Md. 15, 353 A.2d 222 (1976), the Court of Appeals evaluated Maryland’s former mechanics’ lien law in light of the due process considerations of the 14th Amendment and Article 24 of the Maryland Declaration of Rights. The Court determined that because, under that law, a lien attached as soon as work was performed or material supplied, the law “permitted] an owner to be deprived of a significant property interest without notice or a prior hearing, and thus [was] unconstitutional____” Id. at 31, 353 A.2d 222 (footnote omitted). Therefore, the Court “excis[ed] that portion of the statute which purported] to create a lien from the time work [was] performed or materials furnished to the time a lien is established by judicial determination in a proceeding sufficient with respect to due process” and explained that “there can be no existing lien on property until and unless the claimant prevails either in a suit to enforce the claimed lien or some other appropriate proceeding providing notice and a hearing.” Id. at 37, 353 A.2d 222.

As a result of Barry Properties, the Legislature, which was in session when the case was decided, promptly rewrote the law in a manner “designed to avoid the procedural due process denial found in the former statute.” Tyson v. *661 Masten Lumber & Supply, 44 Md.App. 293, 295, 408 A.2d 1051 (1979), cert. denied 287 Md. 758 (1980). Despite AMI's assertions to the contrary, we believe that the Legislature has succeeded in that endeavor.

As we explained in Tyson, under the current law, a lien does not attach automatically upon the performance of work or the supply of materials. The supplying of work or materials merely entitles the supplier to seek a lien for the value of that work or materials, if the other conditions set forth in the law are met. One of those conditions, relevant here, is that, if the supplier is a subcontractor having no direct contract with the owner, he must give written notice to the owner, within 90 days after last supplying his work or materials, of his intention to claim a lien.

Even when the claimant satisfies the various eligibility requirements, however, a lien is not automatically created. The lien can be created only by a court, and then only after the owner has had an opportunity to contest both the claim itself and the claimant’s entitlement to a lien. The claimant’s petition must be supported both by affidavit and by all documents constituting the basis of the lien (Md.Real Prop. Code Ann. § 9-105); the petition must be initially reviewed by the court and found at least facially sufficient (§ 9-106(a)); and the court must then afford the owner an opportunity to answer the petition and present evidence in his behalf. Only in conformance with those requirements and procedures may a lien be established.

To AMI, this is not enough. It urges that, because an owner is not in privity with subcontractors and may not even be aware of their existence until after they have supplied work or materials, the owner may still end up having to pay twice for the same work. Ignorant of the subcontractor, he may innocently pay his general contractor and then, if the general contractor fails to pay the subcontractor, have to pay the subcontractor himself. As subcontractors have up to 90 days from the date they last supplied work or materials to give notice to the owner, a dishonest general contractor can abscond with the owner’s money *662 before the owner is even made aware that subcontractors are on the job, or who they are.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Gem Plumbing & Heating Co., Inc. v. Rossi
867 A.2d 796 (Supreme Court of Rhode Island, 2005)

Cite This Page — Counsel Stack

Bluebook (online)
551 A.2d 888, 77 Md. App. 654, 1989 Md. App. LEXIS 14, Counsel Stack Legal Research, https://law.counselstack.com/opinion/ami-operating-partners-ltd-partnership-v-jad-enterprises-inc-mdctspecapp-1989.