Eastover Stores, Inc. v. Minnix

150 A.2d 884, 219 Md. 658, 1959 Md. LEXIS 397
CourtCourt of Appeals of Maryland
DecidedMay 6, 1959
Docket[No. 180, September Term, 1958.]
StatusPublished
Cited by42 cases

This text of 150 A.2d 884 (Eastover Stores, Inc. v. Minnix) is published on Counsel Stack Legal Research, covering Court of Appeals of Maryland primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Eastover Stores, Inc. v. Minnix, 150 A.2d 884, 219 Md. 658, 1959 Md. LEXIS 397 (Md. 1959).

Opinion

Prescott, J.,

delivered the opinion of the Court.

The defendant owner of a shopping center has appealed from a decree against him, which enforced a mechanics’ lien filed by the plaintiff contractor. The chancellor summed up the facts as follows:

“This is a suit to enforce a mechanics’ lien filed on February 26, 1958, by the plaintiffs, general contractors, against the defendant owners for labor and materials furnished in the erection of a shopping center addition located in Oxon Hill Election District. The plaintiffs’ claim consists of the new contract price amounting to $1,055,591.68 plus various items claimed as extras, giving a total of $1,083,000.86, less payments of $902,029.96, leaving a balance of claim amounting to $180,970.90. In their answer, as amended, to the bill of complaint defendants have claimed set-offs by way of recoupment, totaling $161,090.69, and also ask that they be allowed to deduct $33,972.88, representing mechanics’ liens filed by sub-contractors who supplied labor and materials to the plaintiffs on this project.

“The transcript of testimony contains 419 pages and approximately 100 exhibits presented by both sides. In deciding the case it therefore becomes necessary to summarize the facts as briefly as practicable, and take up separately the claims of the respective parties.

“Mr. A. Lloyd Goode has for many years been engaged in real estate development, particularly with reference to shopping centers. The defendants were organized in connection with developing what is generally known as the Eastover Shopping Center. In 1955 Mr. Goode completed the larger portion of the project on a portion of the property here involved, located on the Indian Head Highway, near the District Line. Being experienced in the building business he himself completed the first portion of the project and did not build it through a contractor. The original portion of the shopping center, as well as the addition, was constructed upon filled ground, and testimony shows that considerable difficulty was experienced because of the seepage of water into *663 the stores constructed on the first portion of the development.

“During the latter part of 1955 or early months of 1956 Mr. Goode determined to build the extension in this case. This portion of the development was to be constructed over a low lying area in which fill dirt had been deposited, making allowance for a basement, which ultimately became the site of the C-3, or J. C. Penny store. At first he intended to build the extension and in preparation for that ordered the necessary structural steel from Dietrich Brothers, steel fabricators, in Baltimore. Dietrich accepted his order provided achitectural plans could be placed in his hands by June 1, 1956, and promised to deliver the steel about November, 1956, but did not guarantee delivery, steel then being in short supply due to a recent steel strike. The architectural drawings were not sent to Dietrich by June 1, but some of them were forwarded later in June. Goode then changed his order with Dietrich to a steel tonnage basis. Because of ill health he decided to seek bids from contractors for the construction of the extension rather than build it himself, based upon plans and specifications and other documents and addenda prepared by Louis H. Asbury and Associates, Architects. The invitations for bids produced the one submitted by the plaintiffs, which resulted in the contract between the parties, dated August 29, 1956. The bid or proposal submitted by the plaintiffs recited that the ‘undersigned bidder having carefully examined the plans, specifications, and other documents and addenda, visited the site and being familiar with all requirements of the site.’

“Embodied in the contract upon which the bid was submitted were included the general conditions of the contract, specifications, and drawings. The specifications contained Addendum No. 1, which states that:

‘Structural Steel has been purchased from Dietrich Brothers, Baltimore, Maryland, for two hundred, fifty-nine dollars and thirty cents ($259.30) per ton. Total tonnage may be obtained from Dietrich. Delivery is promised for November, 1956, but not guaranteed. Bidder should include cost of all structural steel in his proposal. Should increase in price occur *664 before delivery, Owners will pay any increased tonnage price.’

By Article 2 of the Contract it was provided:

‘The work to be performed under this Contract shall be commenced immediately and shall be substantially completed in 330 days.’

There was no stipulation as to liquidated damages, if any.

“The general conditions of the contract, in Article 18 dealing with delays and extension of time, states that:

‘If the Contractor be delayed at any time in the progress of the work by any act or neglect of the Owner or the Architect, or of any employee of either, or by any separate Contractor employed by the Owner, or by changes ordered in the work, or by strikes, lockouts, fire, unusual delay in transportation unavoidable casualties or any causes beyond the Contractor’s control, or by delay authorized by the Architect pending arbitration, or by any cause which the Architect shall decide to justify the delay, then the time of completion shall be extended for such reasonable time as the Architect may decide.
‘No such extension shall be made for delay occurring more than seven days before claim therefor is made in writing to the Architect. In the case of a continuing cause of delay, only one claim is necessary.’ ”

I

After the appellees’ bid had been received and examined, the owners signed and forwarded, in accordance with the specifications, a formal written agreement, dated August 29, 1956, for execution by the appellees. This instrument is called a “contract proposal” by the appellees, who claim that it contained provisions not suggested or included in the invitation to bid or the appellees’ bid proposal. The bond that the appellees were required to furnish was obtained on September 12, and thereafter, on September 19, two copies of *665 the agreement were executed on behalf of the appellees and mailed to the owners. This agreement, as above stated, provided that the “work performed under this contract shall be commenced immediately and shall be substantially completed in 330 days.”

A dispute arose in the trial below as to whether August 29, 1956, the date named in the written agreement, or September 19, 1956, the date when it was executed by the appellees, should prevail in computing the starting date for the 330-day period. The chancellor concluded that under the authority of District of Columbia v. Camden Iron Works, 181 U. S. 453, 461, 1 the appellees could show by parol evidence that the contract, though dated August 29, 1956, on its face, was in fact not executed and delivered until September 19, 1956, and it took effect only from such date of delivery. The appellants, in their original brief, did “not challenge the validity of this rule,” but contended the real issue was not to determine “when

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Falls Garden Condominium Ass'n v. Falls Homeowners Ass'n
107 A.3d 1183 (Court of Appeals of Maryland, 2015)
Erie Insurance Exchange v. Estate of Reeside
28 A.3d 54 (Court of Special Appeals of Maryland, 2011)
Cochran v. Norkunas
919 A.2d 700 (Court of Appeals of Maryland, 2007)
Lubore v. RPM Associates, Inc.
674 A.2d 547 (Court of Special Appeals of Maryland, 1996)
Dormay Construction Corp. v. Doric Co.
156 A.2d 632 (Court of Appeals of Maryland, 1992)
Ami Operating Partners Ltd. Partnership v. Jad Enterprises, Inc.
551 A.2d 888 (Court of Special Appeals of Maryland, 1989)
ADMIRAL BUILDERS SAVINGS AND LOAN ASS'N v. South River Landing, Inc.
502 A.2d 1096 (Court of Special Appeals of Maryland, 1986)
United States v. District of Columbia
596 F. Supp. 725 (D. Maryland, 1984)
St. Paul Fire & Marine Insurance v. Molloy
433 A.2d 1135 (Court of Appeals of Maryland, 1981)
Creamer v. Helferstay
422 A.2d 395 (Court of Special Appeals of Maryland, 1980)
St. Paul Fire & Marine Insurance v. Molloy
420 A.2d 994 (Court of Special Appeals of Maryland, 1980)
Fram Corp. v. Davis
401 A.2d 1269 (Supreme Court of Rhode Island, 1979)
Burroughs Corp. v. Chesapeake Petroleum & Supply Co.
384 A.2d 734 (Court of Appeals of Maryland, 1978)
Canaras v. Lift Truck Services, Inc.
322 A.2d 866 (Court of Appeals of Maryland, 1974)
Delmarva Drilling Co. v. Tuckahoe Shopping Center, Inc.
302 A.2d 37 (Court of Appeals of Maryland, 1973)
Short v. Sunflower Plastic Pipe, Inc.
500 P.2d 39 (Supreme Court of Kansas, 1972)

Cite This Page — Counsel Stack

Bluebook (online)
150 A.2d 884, 219 Md. 658, 1959 Md. LEXIS 397, Counsel Stack Legal Research, https://law.counselstack.com/opinion/eastover-stores-inc-v-minnix-md-1959.