Power Service Corporation v. Joslin

175 F.2d 698, 1949 U.S. App. LEXIS 3662
CourtCourt of Appeals for the Ninth Circuit
DecidedJune 21, 1949
Docket11992
StatusPublished
Cited by14 cases

This text of 175 F.2d 698 (Power Service Corporation v. Joslin) is published on Counsel Stack Legal Research, covering Court of Appeals for the Ninth Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Power Service Corporation v. Joslin, 175 F.2d 698, 1949 U.S. App. LEXIS 3662 (9th Cir. 1949).

Opinion

POPE, Circuit Judge.

Appellant, a Minnesota corporation, sued appellee, a citizen of California, upon a contract whereby appellant, as subcontractor, undertook to erect and install three boilers in a government ordnance plant in Kansas where appellee was himself subcontractor for installation of plumbing, heating and ventilating facilities. Under the contract appellant, to whom we shall refer as the Corporation, was to perform all necessary work as called for by the plans and specifications, all within a period of 120 days. Joslin, the appellee, was to furnish all materials and equipment required. The Corporation claimed damages on account of Joslin’s alleged breach of contract in failing to furnish materials required on time, with resultant loss to the Corporation. The trial court, sitting without a jury, awarded the Corporation damages in the amount of $3753.15. On this appeal it asserts that the damages thus awarded are inadequate and that the court failed to apply the proper measure of damages, contending that under the evidence it should have recovered $34,343.00. These damages, it asserts, were suffered because completion of the job required 39 days extra time, due to the claimed default of Joslin.

Joslin asserts that if the contract were as alleged by the Corporation, the damages could be no more than nominal, but contends that the terms of the contract were such that there was no breach of its terms, and no right to recover damages.

We are therefore confronted, initially, with Joslin’s claim that the contract by its terms does not permit recovery of damages for delay in furnishing materials. If his position with respect to the provisions of the contract is sound, a consideration of the question raised by the Corporation with respect to the measure of damages will be unnecessary.

The specifications which formed a part of the proposed contract upon which the Corporation was the low bidder contained a paragraph numbered 1-05 (e) which provided that: “In case time for completion of the work is increased due to any of the causes specified herein it is distinctly understood and agreed that the subcon-structor [the Corporation] will accept the additional time in which to complete his subcontract in full satisfaction of any delays encountered, and the Constructor [Joslin] will not be liable for any costs or expenses incurred by the subconstructor as a result of the increased time for completion of the subcontract.”

The same specifications required the Corporation to commence work under the subcontract within five calendar days after the date of receipt by it of notice to proceed and thereafter to prosecute the work to completion within 120 days. The bid form executed by the Corporation contained its agreement to execute the form of contract, which, with the specifications had been prescribed by the War Department, within two days after such forms were presented for signature. The bids, which were for a lump sum, were opened July 8, 1944 and the Corporation was the low bidder. The bid was received at Joslin’s Kansas City, Missouri, office, and was there accepted on July 11, 1944. Notice to proceed with the work was given the same day by letter which the Corporation received July 13, 1944.

Joslin claims that the moment the bid was accepted and notice to proceed given, the rights of the parties had become fixed, and a complete contract made, and that the paragraph of the specifications above quoted, excluded any right to damages for delay. The Corporation claims that this provision was eliminated or modified by the later insertion of a rider on the signature page of the formal contract. That came about in the following manner.

By letter dated July 14, 1944 the general contractor for the Sunflower Ordnance Works (generally referred to in the record as the Architect-Engineer-Manager) transmitted to the Corporation a written contract in the form specified in the call for bids with request that it be executed and returned. But, although it did promptly enter upon the performance of the work, the Corporation declined to execute the formal contract pending its continued efforts to persuade Joslin to attach a rider to the subcontract or to make supplemental *700 commitments by letter relating to the matter of reimbursing the Corporation for increased costs occasioned by delay in furnishing certain materials'.

This attitude on the part of the Corporation arose out of the fact that shortly after it had been awarded the subcontract it discovered that some portion of the materials for the three boilers, which are referred to in the record as “water wall tubes and headers” 1 were not on hand or presently available for installation.

The work called for by the contract had originally been arranged for in 1942 when the general contract for the erection of the ordnance plant had been made. The plant was to have three power houses, but when two had been completed, work was stopped on the third. Subsequently, and at the time the bids here referred to were called for, it had been decided to complete the third power house and the subcontract, upon which the corporation bid, was for the erection of the three boilers in this third power house, designated as “Power House No. 1”. When the work was suspended, materials for the three boilers had been collected and stored on or near the site. One paragraph of the specifications recited: “Nearly all of the materials required for the work has been stored in power house No. 1 or in warehouses adjacent thereto.” The specifications further required the successful bidder, immediately after starting work, to compile a list of materials required, check this against the quantities on hand, and report shortages to Joslin.

At the time the bid was presented, neither the Corporation nor Joslin knew what, if any, shortages in this material existed. After the Corporation received the notice to proceed, it did not make a complete list of the materials on hand, but on July 26, 1944 wrote to Joslin as follows: “In connection with our subcontract for complete erection of boilers in Power House No. 1, Sunflower Ordnance Works, Johnson County, Kansas, we wish to advise of a major shortage of materials which will delay the progress of our work beyond our contract schedule.

“This material consists of water-wall tubes for all three of the boilers which we are to erect. In order for us to complete our work in the one hundred twenty day period required, it will be necessary for us to have delivered to the job sufficient tubes for one boiler 'by August 1, 1944; sufficient tubes for a second boiler by August 8th, 1944, and the balance of the tubes for the third boiler by August 15th, 1944.”

On August 8, 1944 the Corporation requested permission to append a proviso on the signature sheet of the formal contract relating to reimbursement of such increased cost as might be occasioned by non-availability of tubes. This was not acceptable to Joslin. Again on August 22 the Corporation requested Joslin to write it a letter in effect acknowledging the Corporation’s right to present a claim for increased costs resulting from delay in the delivery of the materials.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

BMW of North America, LLC v. Mini Works, LLC
166 F. Supp. 3d 976 (D. Arizona, 2010)
Horsfield Construction, Inc. v. Dubuque County
653 N.W.2d 563 (Supreme Court of Iowa, 2002)
Fitzsimmons v. Jackson
51 B.R. 600 (Ninth Circuit, 1985)
Empire MacHinery Co. v. Litton Business Telephone Systems
566 P.2d 1044 (Court of Appeals of Arizona, 1977)
United States v. Mansion House Center No. Redev. Co.
426 F. Supp. 479 (E.D. Missouri, 1977)
Edwards v. Peavey Co.
549 P.2d 1082 (Montana Supreme Court, 1976)
Edwards v. Peavey Company
Montana Supreme Court, 1976
Canaras v. Lift Truck Services, Inc.
322 A.2d 866 (Court of Appeals of Maryland, 1974)
Eastover Stores, Inc. v. Minnix
150 A.2d 884 (Court of Appeals of Maryland, 1959)
United States ex rel. Soper v. Calvada, Inc.
155 F. Supp. 744 (N.D. New York, 1952)
Aermotive Equipment Corp. v. United States
99 F. Supp. 958 (W.D. Missouri, 1951)

Cite This Page — Counsel Stack

Bluebook (online)
175 F.2d 698, 1949 U.S. App. LEXIS 3662, Counsel Stack Legal Research, https://law.counselstack.com/opinion/power-service-corporation-v-joslin-ca9-1949.