Middleton v. City of Emporia

186 P. 981, 106 Kan. 107, 1920 Kan. LEXIS 464
CourtSupreme Court of Kansas
DecidedJanuary 10, 1920
DocketNo. 22,411
StatusPublished
Cited by14 cases

This text of 186 P. 981 (Middleton v. City of Emporia) is published on Counsel Stack Legal Research, covering Supreme Court of Kansas primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Middleton v. City of Emporia, 186 P. 981, 106 Kan. 107, 1920 Kan. LEXIS 464 (kan 1920).

Opinions

The opinion of the court was delivered by

Johnston, C. J.:

The plaintiffs sued to recover from the city of Emporia the amount of a deposit which accompanied a bid they made for the extension and improvement of the waterworks system of the city. In its answer, the defendant asked judgment for $3,242.29, the difference between the amount of the deposit and the damages sustained by the city through the failure of the plaintiffs to carry out the contract resulting from the acceptance by the city of plaintiffs’ proposal. The court found against the plaintiffs and awarded judgment in favor of defendant on its cross petition in the sum of $3,242.29. From this judgment, plaintiffs appeal.

It appears that bonds of the city to the amount of $150,000 were voted by the electors for the improvement of its water[109]*109works system, and the firm of Black & Veatch, engineers of Kansas City, Mo., were authorized and employed by the city to make surveys, prepare plans and specifications for the work, and to supervise the construction of the plant. Plans and specifications were prepared by the engineers, including instructions to bidders, and proposals were invited. In response to the invitation, there were six bids received, ranging from $65,792.49 to $77,992.70. The plaintiffs’ bid was the lowest, and the next lowest bid was made by McCoy & Taylor, for the sum of $70,534.78. The proposal of plaintiffs, which was accompanied by a deposit of $1,500, was accepted by .the city on March 24, 1916. Each bidder was required to inclose with his bid a certified or cashier’s check to be left with the clerk as a guaranty 'of good faith, to be forfeited if he failed to enter into a formal contract and give the required bond for the faithful performance of the work. In relation to the deposit, it was stated:

“In default of the performance of any of the conditions on our part to be performed, the amount of a check which we have this day deposited with the city clerk, shall, at the option of the commissioners, be absolutely forfeited to the city of Emporia, but otherwise the check shall be returned to Middleton & Ludlow,” etc.

It was further stipulated that the bidder would enter into a contract within ten days from the acceptance of the bid and give a bond equal to sixty-five per cent of the amount of the bid, to secure the performance of the contract in accordance with the plans and specifications. On April 3, 1916, the plaintiffs notified the city commissioners that they were unable to give the required bond, but they expressed a willingness to do a small part of the work. After receiving this notice and on April 6, 1916, the mayor and commissioners declared a forfeiture of the deposit and directed that it be placed in the city treasury. On the same day, they proceeded to complete the letting. There was testimony to the effect that upon a consultation with the engineers, it was determined that as prices of material had advanced, there was no prospect that a lower bid than that of McCoy & Taylor, the next lowest bid which had been made, would be received by a readvertising and re-letting. It was the opinion of all that a postponement for another notice and letting, with the constantly increasing [110]*110prices, would cause the city to pay more for the improvement than the amount of the next lowest bid, and thereupon the bid of McCoy & Taylor was accepted. It appears that there was a marked advance in the prices of steel, cement, and lumber, after March 24, 1916, and these were the principal materials to be used in the work.

Although questioned, there can be no doubt of the power of the mayor and commissioners of the city to contract for such an improvement through a public letting, and this plan has been generally followed by municipalities of the state, time out of mind.. In some instances it is specifically required by statute, but no method is prescribed in contracts of the kind in question. It is not necessary that the statute should expressly provide for a public letting, or prescribe the manner for contracting for an improvement. The authority to the city to have the work done carries with it the discretion to have it done in any way in which it is practicable and convenient, and in acting under such authorization the city is entitled to contract and bind itself and to all the rights and remedies of private parties. (2 Dillon on Municipal Corporations, 5th ed., § 815.) In such a case the protection of the public is the first consideration, and probably no method employed better safeguards the public interest than a public letting after due advertisement.

It is argued that a contract relation did not exist between the plaintiffs and the city; that is, that the acceptance of plaintiffs’ bid did not constitute a contract. Every element necessary to a complete contract existed; the city asked for proposals, based on definite plans and specifications, which were furnished to every bidder; and plaintiffs made a proposal which the city formally accepted. The invitation for proposals and the proposals themselves were only negotiations or steps taken towards a contract, but when the acceptance of a proposal was made by the city, a binding contract was concluded. This was more than a step in the negotiations, and more than an agreement to enter into a contract. The notice and specifications stipulated that a formal contract should be executed and security given for faithful performance, but everything was definitely provided for in the agreement resulting from the acceptance. It is true that the writing would re[111]*111duce the terms of the agreement to a more concise and convenient form, and at the end of such a writing a reference is ordinarily made to the plans and specifications in order that all the terms and conditions specified shall be embraced in the contract. Cases may be found where, because of a statute or an express stipulation, a contract is not complete until it is committed to writing and formally signed, or has had the approval of some person indorsed thereon, or where there is a manifest intention that a writing is a condition precedent to the taking effect of the contract. (Edge Moor Bridge Works v. Bristol, 170 Mass. 528; 6 R. C. L. 618.) . Here there are no such provisions or restrictions and, in the absence of these or something of the kind, a binding agreement may be made by a proposal and acceptance. In Denton v. City of Atchison, 34 Kan. 438, 8 Pac. 750, it was said:

“A city advertised for proposals for the building of certain sidewalks according to plahs and specifications on file in the oifice of the city engineer, and in response thereto a contractor made a proposal to build the walks at a certain price in accordance with such plans and specifications, and under the direction and to the acceptance of the city engineer, which proposal was duly accepted by the mayor and council of the city. Held, That the proposal of the contractor being definite and the acceptance by the city being unqualified, they together constituted a contract between the parties, and that the plans and specifications referred to in the proposal became a part of such contract.”

The deposit was required, as we have seen, to secure bona 'fide bids, and so that the bidder would enter into a formal contract with a sufficient bond to guarantee full performance of the contract within the time and on the terms specified. It is immaterial whether the deposit so made is regarded as a forfeiture or liquidated damages.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Unified School District No. 446 v. Sandoval
286 P.3d 542 (Supreme Court of Kansas, 2012)
Sigg v. Coltrane
253 P.3d 781 (Court of Appeals of Kansas, 2010)
Ayalla v. Southridge Presbyterian Church
152 P.3d 670 (Court of Appeals of Kansas, 2007)
R. D. Andersen Construction Co. v. City of Topeka
612 P.2d 595 (Supreme Court of Kansas, 1980)
Geo. C. Christopher & Son, Inc. v. Kansas Paint & Color Co.
523 P.2d 709 (Supreme Court of Kansas, 1974)
Phillips & Easton Supply Co. v. Eleanor International, Inc.
512 P.2d 379 (Supreme Court of Kansas, 1973)
Schull Construction Co. v. Board of Regents of Education
113 N.W.2d 663 (South Dakota Supreme Court, 1962)
Miles v. City of Wichita
267 P.2d 943 (Supreme Court of Kansas, 1954)
Power Service Corporation v. Joslin
175 F.2d 698 (Ninth Circuit, 1949)
Marquette Gravel & Construction Co. v. Bengtson
274 P. 253 (Supreme Court of Kansas, 1929)
Botts v. City of Valley Center
257 P. 226 (Supreme Court of Kansas, 1927)
United States Fidelity & Guaranty Co. v. City of Pittsburg
225 P. 83 (Supreme Court of Kansas, 1924)

Cite This Page — Counsel Stack

Bluebook (online)
186 P. 981, 106 Kan. 107, 1920 Kan. LEXIS 464, Counsel Stack Legal Research, https://law.counselstack.com/opinion/middleton-v-city-of-emporia-kan-1920.