Richards Construction Company v. Air Conditioning Company of Hawaii

318 F.2d 410, 1963 U.S. App. LEXIS 5173
CourtCourt of Appeals for the Ninth Circuit
DecidedMay 27, 1963
Docket17748
StatusPublished
Cited by13 cases

This text of 318 F.2d 410 (Richards Construction Company v. Air Conditioning Company of Hawaii) is published on Counsel Stack Legal Research, covering Court of Appeals for the Ninth Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Richards Construction Company v. Air Conditioning Company of Hawaii, 318 F.2d 410, 1963 U.S. App. LEXIS 5173 (9th Cir. 1963).

Opinion

DUNIWAY, Circuit Judge.

This is an action for breach of contract. Defendants, appellants here, are Richards Construction Company—Kaneohe Bay Project, a general partnership, its members, and its bonding company. The construction company became the general contractor for the construction of certain housing units at the United States Marine Corps Air Station at Kaneohe Bay, Oahu, Hawaii. Appellee, plaintiff in the trial court, is a subcontractor. Jurisdiction rests upon diversity of citizenship, upon the Miller Act (40 U.S.C. § 270b) and upon 28 U.S.C. §§ 1352 and 1331.

The action was tried by the court, and it made detailed findings, upon which no serious attack is made by appellants. Our statement of facts is taken largely from the findings. Invitations for bids to construct the project were distributed on December 4, 1957, calling for bids to be opened on January 31, 1958. Appellant (as used hereafter this term means the general partnership) was interested in bidding. On January 20, 1958, it advertised for bids from subcontractors. Its address in California was given, and it was also stated that a representative of appellant would be at the Surfrider Hotel, Honolulu, on January 28, 29, 30 and 31. In response to this advertisement appellee filed a bid on the sheet metal work for the project with the General Contractors Association of Hawaii on January 30, and on that day or the next, telephoned the bid to Richards, appellant’s general manager, at the Surf-rider. The amount of the bid was $48,-733. This was the lowest bid appellant had received for the work, 1 and Richards reconfirmed it by phone to appellee, stating that he was using appellee’s figure in appellant’s bid for the job. Richards then reduced appellant’s bid for the whole job by the difference between $83,-000, the next lowest bid received on which Richards had figured the job, and appellee’s bid, and submitted a bid for the whole project on January 31. Ap *412 pellant became the low bidder and was awarded the general contract, for $8,794,-085.

The 31st was a Friday. Appellee, on Sunday, February 2, having learned that Richards was the successful bidder, rechecked its figures and discovered that its estimator had made an error, calculating the bid upon galvanized sheet metal instead of zinc alloy, which was called for. This made a substantial difference in appellee’s material costs. On February 3, appellee attempted to reach Richards at the Surfrider, but he had returned to the mainland. Appellee made no attempt to reach appellant in California. Appellee’s bid was made with the knowledge and expectation that appellant would use it, and it was not expressly made revocable, nor was the time during which it would remain open limited in any way.

Nothing more occurred until a month later, when Richards returned to Hawaii. On March 6, appellee’s sheet metal foreman told Richards that appellee had made the mistake described above, and that appellee would like to withdraw the figures. Richards “blew up.” Next day, he saw Quealy, appellee’s general manager, who said appellee would not do the job at the bid price. On March 11, appellant, by letter, formally accepted appellee’s bid at the $48,733 figure. On March 25, appellee replied that it was under no contractual duty to proceed, and that its offer had been withdrawn.

There followed, beginning about April 1, negotiations looking to the use of copper on the job, with the permission of the Navy, at a price of $96,000. Appellant, on July 14, wrote to the Navy suggesting such a change, which was refused. There then followed some hard bargaining between the parties, characterized, as the court found, by mutual misrepresentations and deceptions, by means of which appellant tried to get appellee

down to the lowest possible figure for the job as originally specified, and appellee tried to get the highest price it could. The court found that the two men directly involved had been no more frank with it than they had been with each other. At any rate, the negotiations continued from mid-July well into September, and the parties finally agreed on a price of $62,000. 2 Appellant then prepared, and on September 29 both parties signed, a contract at that price. The contract made no reference to the previous bid or its acceptance; the only work called for was that on which appellee had originally bid $48,733.

Richards at no time intended to pay the full $62,000. His intention was to pay only so much as would keep appellee at work until the job was done, and, if possible, no more than the original bid price. Appellee completed the job, satisfactorily. It was necessary for appellant to pay $50,582 to keep appellee from realizing, before it completed the job, that it would not get the $62,000. At that point, appellant stopped paying. Appellee then brought this action for the balance of the $62,000, plus one small item of extra work, and appellant counterclaimed for $1,849, which, it says, it overpaid to appellee.

The trial court first found and concluded that there was a binding contract between the parties to do the work for $48,-733. It found that appellee knew that appellant wanted the bid to use as a basis for its own bid to the Navy, and that appellant did- so use it. This, said the court, was a sufficient change of position, to appellant’s detriment, to be a consideration for, and a substitute for acceptance of, the offer embodied in appellee’s bid. The court relied upon Restatement, Contracts, § 45 and comment 6, and § 90 (1932), and such cases as Drennan v. Star Paving Co., 1958, 51 Cal.2d 409, 333 P.2d 757. The parties *413 agree with this conclusion, and we therefore accept it without considering whether all of the reasoning of the court was correct. We doubt the applicability of § 45 of the Restatement, which deals with an offer for a unilateral contract. We do not know whether the Supreme Court of Hawaii would, in a case such as this, follow § 90, or the California case relied upon. (Compare the views of Learned Hand in James Baird Co. v. Gimbel Bros., 2 Cir., 1933, 64 F.2d 344) We prefer to leave these questions to that court, and to rest our decision upon the parties’ acquiescence in the decision that there was a binding contract between them.

While we think that the evidence would also support a finding that appellant should have known that appellee’s bid was probably arrived at by mistake (see footnote 1, supra), the court did not so find. Rather, it found, and we think the evidence, which is conflicting, supports the finding, that appellant did not know of the mistake until Richards was told about it on March 6.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
318 F.2d 410, 1963 U.S. App. LEXIS 5173, Counsel Stack Legal Research, https://law.counselstack.com/opinion/richards-construction-company-v-air-conditioning-company-of-hawaii-ca9-1963.