Janke Construction Co., Inc. v. Vulcan Materials Co.

386 F. Supp. 687, 16 U.C.C. Rep. Serv. (West) 937, 1974 U.S. Dist. LEXIS 6207
CourtDistrict Court, W.D. Wisconsin
DecidedOctober 21, 1974
Docket71-C-131
StatusPublished
Cited by13 cases

This text of 386 F. Supp. 687 (Janke Construction Co., Inc. v. Vulcan Materials Co.) is published on Counsel Stack Legal Research, covering District Court, W.D. Wisconsin primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Janke Construction Co., Inc. v. Vulcan Materials Co., 386 F. Supp. 687, 16 U.C.C. Rep. Serv. (West) 937, 1974 U.S. Dist. LEXIS 6207 (W.D. Wis. 1974).

Opinion

OPINION AND ORDER

ROSENSTEIN, District Judge.

In this action, plaintiff, a general contractor, alleges that defendant, a producer of construction materials, including reinforced concrete pipe, agreed to provide plaintiff with pipe and fittings at a per unit cost, for a marine construction project at the University of Wisconsin at Milwaukee, Wisconsin; that defendant expressly warranted and represented to plaintiff that defendant’s products would meet the specifications required for that project; that plaintiff, in reliance thereon, used defendant’s prices in bidding on the marine project and was awarded the contract; that following the award, defendant proposed to provide plaintiff with pipe and fittings which did not meet the specifications and which were rejected by the project engineers; and that plaintiff was thereby compelled to purchase the specified materials from another supplier at a higher cost, sustaining damages of $40,442.40.

*689 Jurisdiction is based on diversity of citizenship and the parties do not contest that Wisconsin law applies. The case was tried to this Court without a jury, briefs were submitted, and the matter is now ripe for disposition.

Plaintiff, a Wisconsin corporation with its principal offices near Wausau, Wisconsin, has been engaged in various types of construction work, including highway, sewer, airport and marine projects. Defendant, a New Jersey corporation, operates quarries and has sand, gravel, aggregate, and redi-mix concrete plants in several states. In 1970, it also operated a concrete pipe plant located in Illinois which produced only AWWA (American Water Works Association) Specification 0302 pipe.

In February 1970, the State Bureau of Engineering, on behalf of the Regents of the University of Wisconsin, publicly invited submission of sealed bids for the construction of condenser water transmission lines, lake piping and a pumping station for the University of Wisconsin-Milwaukee campus. The project was intended to provide the University with its own cooling system. The bids were to be opened at 2:00 P. M., on March 10, 1970, in Madison, Wisconsin.

The general construction, land, marine, and electrical work portions of the project were to be bid on separately, each portion requiring a separate lump sum bid. The marine portion of the work included the furnishing and installation of water intake and return lines into Lake Michigan. The materials required for marine piping included concrete subaqueous pipe in full compliance with either AWWA Specification C300 or AWWA Specification C301. The main contract also contained an “or equal” clause, permitting use of non-specified materials of equal quality to those specified if they were considered equally acceptable to and approved by the project engineers.

Plaintiff, intending to bid on the marine work, obtained price quotations from suppliers of the various materials required for that portion of the project. On March 5, 1970, Jerry Janke, then vice-president of plaintiff, received by telephone from a Vulcan representative price quotations for the various concrete pipe items to be used in the marine work. Janke made a memorandum of the prices quoted, but did not inquire during this conversation whether defendant proposed to supply C300 or C301 pipe, nor did the caller specify the quality or type of pipe Vulcan intended to furnish. 1 Defendant’s prices were $40,000 below that quoted by Interpace, another subaqueous concrete pipe supplier.

On the evening of March 9, 1970, Jerry Janke and his brother, James Janke, owner of plaintiff, checked in at a Madison hotel for the purpose of submitting their bid the next day. Around midnight they were visited in their hotel room by Alex Barry, then general manager of Vulcan’s Wisconsin operation, and Peter W. Fox, a salesman for defendant’s sand, gravel, crushed limestone, and redi-mix concrete.

While it is not clear whether the visit was only social or included some discussion of Vulcan’s ability to furnish the pipe for the project, all parties present at that visit agree that there was no reference to the particular specifications or type of pipe that Vulcan proposed to supply. The next day, shortly prior to submitting his bid, James Janke met Barry in the hallway of the State Office Building. Janke was concerned because of the disparity in the prices quoted by Vulcan and Interpace. He requested and received assurance from Barry that Vulcan could furnish the pipe for the project. During that meeting Barry *690 also placed a telephone call to someone at Vulcan who confirmed his statement.

According to Barry, Janke merely inquired at this meeting whether Vulcan could reduce its quoted prices on the pipe, and his telephone call to Vulcan’s vice-president was made only to confirm his statement that prices would not be reduced.

Janke, who had relied upon Vulcan’s quoted pipe prices in calculating his prime bid, thereupon submitted it and was subsequently awarded the contract.

Within the week after the bid opening plaintiff received a written quotation fro Vulcan setting forth the same prices that were quoted to Jerry Janke over the telephone on March 5, but stating that the quotation was for AWWA C302 pipe. The writing is dated March 6, but it is not known when it was mailed.

The record does not indicate the date when plaintiff discovered that defendant was offering to supply C302 pipe and not the pipe listed in the specifications. However, between March 10 and March 23, James Janke met three times in Milwaukee and in Madison with the engineers for the State of Wisconsin, a representative from the University, Alex Barry, and Art Littva of Vulcan’s engineering department in an effort to persuade the State to accept the C302 pipe. Littva then sent Janke specifications and shop drawings showing use of the C302 pipe on the marine project, and requested Janke to submit them under the “or equal clause.” The plans were submitted as requested, and were rejected by the State’s consulting engineers as not approved.

In response to James Janke’s inquiry as to why the pipe did not meet specifications the engineers stated that the pipe was not AWWA C300 or C301 as specified; was not steel cylinder type; was not designed for an internal pressure of 5 psi; and did not have a beam strength equal to the pipe specified.

The engineers subsequently requested Janke to submit shop drawings using design conditions and materials as specified, stating that time was critical to the completion of the project. Plaintiff was then forced to buy the specified pipe from Interpace at a cost of $197,093.50, which was $39,942.40 over the $157,101.10 it would have paid for Vulcan’s pipe in accordance with the latter’s quotation. James Janke considered $150 to $200 per day to be the reasonable and fair value of his time spent in attending the meetings at Madison and Milwaukee with the state engineers on Vulcan’s pipe.

The record discloses that the University of Wisconsin-Milwaukee project was first opened for bidding on May 21, 1969, but at that time it had to be bid on as an entire unit. Plaintiff had bid as a subcontractor with a prime contractor on the marine portion, using Vulcan’s prices in preparing its bid.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Skebba v. Kasch
2006 WI App 232 (Court of Appeals of Wisconsin, 2006)
McWilliams v. American Medical International, Inc.
960 F. Supp. 1547 (N.D. Alabama, 1997)
Neiss v. Ehlers
899 P.2d 700 (Court of Appeals of Oregon, 1995)
Lohse v. Atlantic Richfield Co.
389 N.W.2d 352 (North Dakota Supreme Court, 1986)
Maurice Electrical Supply Co. v. Anderson Safeway Guard Rail Corp.
632 F. Supp. 1082 (District of Columbia, 1986)
Kiely v. St. Germain
670 P.2d 764 (Supreme Court of Colorado, 1983)
Gerson Electric Construction Co. v. Honeywell, Inc.
453 N.E.2d 726 (Appellate Court of Illinois, 1983)
Klinke v. Famous Recipe Fried Chicken, Inc.
616 P.2d 644 (Washington Supreme Court, 1980)
Klinke v. Famous Recipe Fried Chicken, Inc.
600 P.2d 1034 (Court of Appeals of Washington, 1979)
Ivey's Plumbing & Electric Co. v. Petrochem Maintenance, Inc.
463 F. Supp. 543 (N.D. Mississippi, 1978)

Cite This Page — Counsel Stack

Bluebook (online)
386 F. Supp. 687, 16 U.C.C. Rep. Serv. (West) 937, 1974 U.S. Dist. LEXIS 6207, Counsel Stack Legal Research, https://law.counselstack.com/opinion/janke-construction-co-inc-v-vulcan-materials-co-wiwd-1974.