Debron Corporation v. National Homes Construction Corporation

493 F.2d 352
CourtCourt of Appeals for the Eighth Circuit
DecidedApril 3, 1974
Docket73-1504
StatusPublished
Cited by17 cases

This text of 493 F.2d 352 (Debron Corporation v. National Homes Construction Corporation) is published on Counsel Stack Legal Research, covering Court of Appeals for the Eighth Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Debron Corporation v. National Homes Construction Corporation, 493 F.2d 352 (8th Cir. 1974).

Opinion

LAY, Circuit Judge.

Debron Corporation appeals from the district court’s grant of a judgment notwithstanding the verdict after a jury awarded it damages against National Homes Construction Corporation, arising from the latter’s failure to perform as a subcontractor. National Homes Construction Corporation, a steel erector, was the only subcontractor to submit a bid to the Debron Corporation, a general contractor, for the steel erection of a building in Buffalo, New York. Debron used that bid as part of its total bid with the owner for the main construction project. After Debron was awarded the main contract, National Homes withdrew its bid. National Homes did not perform and Debron was required to obtain performance of the subcontract from a third party at an increased cost. Before trial, Debron voluntarily dismissed its count for breach of contract and submitted its proof solely on the theory of promissory estoppel, *354 i. e., that it justifiably relied to its detriment on the subcontractor’s bid and therefore National Homes was obligated to perform. The trial court submitted the case to a jury and a verdict was returned in favor of Debron in the amount of $97,691. The trial court granted a judgment notwithstanding the verdict in favor of National Homes, holding that Debron had substantially changed the terms of the offer originally made by National Homes, and that the doctrine of promissory estoppel' did not apply because the plaintiff failed to meet its burden of proof that it had relied upon the original quotation submitted. We reverse and remand the case with directions to reinstate the verdict.

Facts

Debron is engaged in the steel fabrication business. In the latter part of 1970, Debron decided to submit a bid to the New York State University Construction Fund on the fabrication and erection of the structural steel for the new medical science building of the State University of New York at Buffalo. Accordingly, in order to prepare its own bid, Debron sought estimates from several steel erectors. National Homes was the only steel erector to express interest in the project.

In December, 1970, Jim Orr, Vice President and General Manager of the Steel Erectors Division of National Homes, requested Debron to send him the plans and specifications for the Buffalo job so that he could prepare an estimate. These plans were sent to Orr on December 22, 1970.

On January 7, 1971, Orr traveled to the Debron plant in St. Louis to review the plans for the Buffalo job with De-bron personnel. On January 11, 1971, Orr telephoned Mr. Muehlenbrock of De-bron to submit a unit price bid on the erection of the structural steel and steel deck for the Buffalo job. The basic price of Orr’s bid was $128 per ton for the erection of the structural steel and $14 per hundred square feet for the steel deck. Muehlenbrock made a contemporaneous notation of the substance of the phone call. Orr did not at any time reduce his bid to writing; however, Orr’s files contained an estimate sheet in his own handwriting which conformed to Muehlenbrock’s notes. Orr’s estimate sheet read in part as follows:

"Bid price of $128 per ton was accepted with the provision that we furnish bond and possibly make an allowance for steel delivered to the job site."
"Total tonnage 3,700 @ $128 per ton 473,600 Decking 1572 squares @ $14 22,008 Total job approx. 495,608"

It was orally agreed by both parties at the time of the January 11 phone call that Debron would use National Homes’ bid in the preparation of Debron’s own bid and that if Debron were awarded the main contract, it would use National Homes as its steel erection subcontractor.

Debron thereafter submitted its overall bid to the Construction Fund. According to Debron, the difference in the steel erection price submitted by Orr, $495,608, and that submitted by Debron to the Construction Fund, $519,080, reflects only the standard profit mark-up customarily applied by a general contractor.

On January 13, 1971, Debron was declared the low bidder. Immediately after learning that he was the low bidder, Muehlenbrock advised Orr of that fact. On January 15, 1971, Muehlenbrock advised the Construction Fund that National Homes would be Debron’s steel erection subcontractor.

Shortly thereafter Orr met with Muehlenbrock in Buffalo to review plans for coordination of the job between De-bron and National Homes. At this conference, Orr reaffirmed National Homes’ bid as made by telephone on January 11, 1971. The parties then met with the construction Fund where Orr was introduced as Debron’s subcontractor for the steel erection job. Orr testified that he attended the meeting because he thought he was the subcontractor on the job and all subcontractors had to be approved by the Construction Fund. Orr told his supervisor, Mr. Bur *355 ton, Executive Vice President of National Homes, that he was attending the meeting in Buffalo and subsequently furnished Burton with a copy of the minutes of the meeting for Burton’s files.

On February 1, 1971, Orr notified De-bron that National Homes had been approved under the Buffalo plan as an equal opportunity employer, as required by the Construction Fund.

During late January and early February, Debron personnel communicated with Orr by telephone several times to discuss details of the job. On February 8, 1971, Orr went to the Debron plant in St. Louis to review further details. At that time, according to Debron’s evidence, Orr and Debron agreed that even though the original specifications called for the work to begin on May 1, 1971, the actual erection of the steel need not start before July 1, 1971, because the job would only require fourteen weeks and did not need to be completed before November 1.

During February, March and April, Debron placed orders with steel mills for the furnishing of the steel. During this time period, Debron also forwarded to Orr all solicitations it received from field painters, renters of field toilets, etc., regarding the Buffalo job. During the same time period, Orr himself contacted Buffalo labor unions and equipment suppliers. On February 22, 1971, Debron sent Orr a letter regarding safety requirements imposed by the Buffalo ironworkers’ union and a letter regarding the accidental interruption of utilities on the project.

On February 25, 1971, the Construction Fund sent Debron a letter of intent, authorizing Debron to proceed with the job. This letter of intent specified National Homes as the steel erector.

On March 3, 1971, Debron informed National Homes that it could proceed with its planning and preparation work for the project to commence in late June of 1971. National Homes was informed that a formal purchase order for this work was being processed and would be forwarded shortly.

On March 18, 1971, Debron signed a contract with the Construction Fund and executed two bonds to the Fund. The Construction Fund did not sign the contract until May 27, apparently because of an unexpected soil problem that arose with the foundation contractor. Debron was advised of this problem and immediately notified Orr. Orr agreed that based on the July 1 starting date previously discussed, the schedule could still be met and it was decided that Debron and National Homes would continue to prepare for that starting date.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Weitz Co. v. Hands, Inc.
882 N.W.2d 659 (Nebraska Supreme Court, 2016)
I & R Mechanical, Inc. v. Hazelton Manufacturing Co.
817 N.E.2d 799 (Massachusetts Appeals Court, 2004)
Pavel Enterprises, Inc. v. AS Johnson Co., Inc.
674 A.2d 521 (Court of Appeals of Maryland, 1996)
MBA, Inc. v. VNU Amvest, Inc. (In Re MBA, Inc.)
51 B.R. 966 (E.D. Virginia, 1985)
Hoel-Steffen Construction Co. v. United States
684 F.2d 843 (Court of Claims, 1982)
Burst v. Adolph Coors Co.
650 F.2d 930 (Eighth Circuit, 1981)
Burst v. Adolph Coors Company
650 F.2d 930 (Eighth Circuit, 1981)
Burst v. Adolph Coors Co.
503 F. Supp. 19 (E.D. Missouri, 1980)
Lyon Metal Products, Inc. v. Hagerman Construction Corp.
391 N.E.2d 1152 (Indiana Court of Appeals, 1979)
Loranger Construction Corp. v. E. F. Hauserman Co.
384 N.E.2d 176 (Massachusetts Supreme Judicial Court, 1978)
Loranger Construction Corp. v. E. F. Hauserman Co.
374 N.E.2d 306 (Massachusetts Appeals Court, 1978)
Janke Construction Co., Inc. v. Vulcan Materials Co.
386 F. Supp. 687 (W.D. Wisconsin, 1974)

Cite This Page — Counsel Stack

Bluebook (online)
493 F.2d 352, Counsel Stack Legal Research, https://law.counselstack.com/opinion/debron-corporation-v-national-homes-construction-corporation-ca8-1974.