Weitz Co. v. Hands, Inc.

882 N.W.2d 659, 294 Neb. 215
CourtNebraska Supreme Court
DecidedJuly 22, 2016
DocketS-15-581
StatusPublished
Cited by11 cases

This text of 882 N.W.2d 659 (Weitz Co. v. Hands, Inc.) is published on Counsel Stack Legal Research, covering Nebraska Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Weitz Co. v. Hands, Inc., 882 N.W.2d 659, 294 Neb. 215 (Neb. 2016).

Opinion

Nebraska Supreme Court Online Library www.nebraska.gov/apps-courts-epub/ 07/22/2016 09:07 AM CDT

- 215 - Nebraska Supreme Court A dvance Sheets 294 Nebraska R eports WEITZ CO. v. HANDS, INC. Cite as 294 Neb. 215

Weitz Company, LLC, v. H ands, Inc., doing business as H & S Plumbing and H eating, appellant. ___ N.W.2d ___

Filed July 22, 2016. No. S-15-581.

1. Equity: Estoppel. Although a party can raise estoppel claims in both legal and equitable actions, estoppel doctrines have their roots in equity. 2. Equity: Appeal and Error. In reviewing judgments and orders dispos- ing of claims sounding in equity, an appellate court decides factual questions de novo on the record and reaches independent conclusions on questions of fact and law. But when credible evidence is in conflict on material issues of fact, an appellate court considers and may give weight to the fact that the trial court observed the witnesses and accepted one version of the facts over another. 3. Forbearance: Estoppel. A claim of promissory estoppel requires a plaintiff to show: (1) a promise that the promisor should have reason- ably expected to induce the plaintiff’s action or forbearance, (2) the promise did in fact induce the plaintiff’s action or forbearance, and (3) injustice can only be avoided by enforcing the promise. 4. ____: ____. A plaintiff claiming promissory estoppel need not show a promise definite enough to support a unilateral contract, but it must be definite enough to show that the plaintiff’s reliance on it was reasonable and foreseeable. 5. Contracts. Usages of trade are strong evidence of the foreseeability of reliance on a promise. 6. Estoppel. Evidence that a promisee had little time to act on the promise shows that the promisee’s reliance was foreseeable. 7. Contracts: Contractors and Subcontractors. A general contractor can reasonably rely on a subcontractor’s bid even if the general contractor and subcontractor contemplate signing a formal subcontract with addi- tional standard terms after the bidding process ends. - 216 - Nebraska Supreme Court A dvance Sheets 294 Nebraska R eports WEITZ CO. v. HANDS, INC. Cite as 294 Neb. 215

8. Contractors and Subcontractors. A general contractor cannot demand that a subcontractor agree to unusual and onerous terms while still hold- ing the subcontractor to its original bid. 9. ____. If a subcontractor’s bid is so low that a mistake should be appar- ent, a general contractor cannot reasonably rely on the bid. 10. Estoppel: Damages. No single measure of damages applies in every promissory estoppel case. 11. ____: ____. The damages that the promisor ought to pay under promis- sory estoppel are those that justice requires. 12. Damages: Proof. A plaintiff’s burden is to prove his or her damages to a reasonable certainty, not beyond all reasonable doubt. 13. Election of Remedies. The election of remedies doctrine is an affirma- tive defense. 14. Pleadings. A party must specifically plead an affirmative defense for the court to consider it.

Appeal from the District Court for Douglas County: Joseph S. Troia, Judge. Affirmed. Brian S. Kruse, of Rembolt Ludtke, L.L.P., for appellant. Gregory C. Scaglione, Kristin M.V. Krueger, and Patrice D. Ott, of Koley Jessen, P.C., L.L.O., for appellee. Heavican, C.J., Wright, Connolly, Cassel, Stacy, and K elch, JJ. Connolly, J. I. SUMMARY The Weitz Company, LLC (Weitz), a general contractor, received an invitation to bid on a planned nursing facility. Hands, Inc., doing business as H & S Plumbing and Heating (H&S), submitted a bid to Weitz for the plumbing work, as well as the heating, ventilation, and air conditioning (HVAC) parts of the job. Weitz’ bid to the project owner incorporated the amount of H&S’ bid. After the owner awarded the project to Weitz, H&S refused to honor its bid. Weitz completed the project with different subcontractors at greater expense. At trial, Weitz sought to enforce H&S’ bid under promis- sory estoppel. The court determined that Weitz reasonably - 217 - Nebraska Supreme Court A dvance Sheets 294 Nebraska R eports WEITZ CO. v. HANDS, INC. Cite as 294 Neb. 215

and foreseeably relied on H&S’ bid, and it therefore estopped H&S from reneging. The court measured Weitz’ damages as the difference between H&S’ bid and the amount Weitz paid to substitute subcontractors. H&S appeals. We affirm the judg- ment and the amount of damages. II. BACKGROUND 1. Weitz Is Invited to Bid In 2011, the Evangelical Lutheran Good Samaritan Society (Good Samaritan) invited four “prequalified General Contractors,” including Weitz, to bid on a proposed nursing facility in Beatrice, Nebraska. Good Samaritan chose the four prequalified general contractors based on “prior relationships” recommendations from its architect and its own research. Good Samaritan is a “big player” in the retirement living market. Weitz is a “dominant contractor” in the same market. Alan Kennedy, a Weitz executive, said that Weitz had sought to build a relationship with Good Samaritan that would lead to “negotiated work,” meaning that Good Samaritan would work with Weitz without inviting other general contractors to bid. Kennedy testified that negotiated work is “one of the best places to be as a contractor.” When Good Samaritan invited Weitz to bid on the Beatrice project, Weitz knew of another potential project with Good Samaritan in Sarpy County, Nebraska. Good Samaritan’s “Invitation to Bid” stated that it would not consider bids received after 2 p.m. on August 30, 2011 (bid day). The invitation incorporated certain “Instructions to Bidders,” which provided that Good Samaritan and its architect could object to a general contractor’s proposed sub- contractors. The invitation stated that “[n]o bids may be with- drawn for a period of 60 days after opening of bids.” If a gen- eral contractor refused to enter into a contract, the instructions provided to bidders state that the general contractor would forfeit its bid security as liquidated damages. A bid security is a bond that “assures the owner that [it] can rely upon the - 218 - Nebraska Supreme Court A dvance Sheets 294 Nebraska R eports WEITZ CO. v. HANDS, INC. Cite as 294 Neb. 215

bids.” But Good Samaritan did not ask for bid securities, because it prequalified the general contractors. 2. Bid -Day M adness Before bid day, Weitz assigned “lead person[s]” to the dif- ferent categories of work on the project, referred to as “tick- ets.” The ticket leaders reviewed the project specifications and created a “scope checklist” that described the work for each ticket. Weitz prepared scope checklists because subcontractors sometimes excluded certain work from their bid. On bid day, Weitz assembled its people in a conference room to collect and organize the hundreds of bids from sub- contractors. Ticket leaders called out the bids after comparing them with the scope checklist. Weitz then added the numbers to a “bid day spreadsheet.” Subcontractors in the mechanical, engineering, and plumb- ing fields typically submit their bids within 15 minutes of the deadline. As a result, Weitz is often “at the wire turning in [its] number to an owner.” Brian Mahlendorf, a project executive for Weitz, oversaw Weitz’ bid for the Good Samaritan project. Mahlendorf said that Weitz received H&S’ bid “less than 15 minutes or so” before the 2 p.m. deadline. Kennedy, who had been involved in “well over a hundred bids,” testified that it was “customary for general contractors to rely on bids submitted by subcontractors” and that subcon- tractors submit bids because they want the job. Mahlendorf, who had more than 20 years of experience in the construction industry, testified that it was customary for Weitz to rely on subcontractors’ bids, that subcontractors knew that Weitz relied on their bids, and that subcontractors submitted bids because they wanted to procure work.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Morris v. Dall
320 Neb. 122 (Nebraska Supreme Court, 2025)
Page v. Siedband
Nebraska Court of Appeals, 2023
Mumin v. Chef Lee, Taste of New Orleans
Nebraska Court of Appeals, 2023
30 Metropolitan Place v. Dana Partnership
Nebraska Court of Appeals, 2023
Brian C. Podwinski
D. Nebraska, 2021
Homebuyers Inc. v. Watkins
Nebraska Court of Appeals, 2019
deNourie & Yost Homes v. Frost
893 N.W.2d 669 (Nebraska Supreme Court, 2017)

Cite This Page — Counsel Stack

Bluebook (online)
882 N.W.2d 659, 294 Neb. 215, Counsel Stack Legal Research, https://law.counselstack.com/opinion/weitz-co-v-hands-inc-neb-2016.