Percy J. Matherne Contractor, Inc. v. Grinnell Fire Protection System Co.

915 F. Supp. 818, 1995 U.S. Dist. LEXIS 20836, 1995 WL 803789
CourtDistrict Court, M.D. Louisiana
DecidedAugust 9, 1995
DocketCivil A. 94-04
StatusPublished
Cited by7 cases

This text of 915 F. Supp. 818 (Percy J. Matherne Contractor, Inc. v. Grinnell Fire Protection System Co.) is published on Counsel Stack Legal Research, covering District Court, M.D. Louisiana primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Percy J. Matherne Contractor, Inc. v. Grinnell Fire Protection System Co., 915 F. Supp. 818, 1995 U.S. Dist. LEXIS 20836, 1995 WL 803789 (M.D. La. 1995).

Opinion

ORDER ON MOTIONS FOR SUMMARY JUDGMENT

VANCE, District Judge.

This matter is before the Court on cross motions for summary judgment filed by defendant Grinnell Fire Protection Systems Co. (“Grinnell”) and plaintiff Percy Matherne Contractor, Inc. (“Matherne”). For the reasons stated below, the motion by Grinnell is denied, and the motion by Matherne is granted.

I. BACKGROUND

This is an action by a general contractor, Matherne, against a subcontractor, Grinnell, to recover damages as a result of Grinnell’s failure to perform according to its bid for the fabrication and installation of a sprinkler system. In late 1992, the St. James Parish School Board (“School Board”) invited bids for additions and renovations to Lutcher High School in Lutcher, Louisiana (the “Project”). General contractors’ bids were due on February 2, 1993 at 4:00 p.m. One of the items included in the Project was the fabrication and installation of a fire protection system.

Prior to the February 2,1993 deadline (the exact date is disputed), the School Board and its architects issued four addenda to the Project plans that altered the scope of certain portions of the Project. On February 2,1993 at 3:19 p.m., just before the 4:00 deadline, Grinnell submitted a bid to Matherne for the fire protection system in the amount of $79,-500. In preparing this bid, Grinnell states that it did not consider addenda numbers 3 and 4. It only took into consideration the original specifications and those contained in addenda numbers 1 and 2. Matherne received one other bid for the fire protection portion of the Project in the amount of $218,-094.

Plaintiff claims with supporting evidence that on the day the bids were due, Don Matherne noted that Grinnell’s oid was drastically below that of the other bidding subcontractor and had an employee call Grinnell to confirm the correctness of its bid. The Matherne employee, Mr. Leblanc, testified that he called Wallace LeBan of Grinnell to ask whether LeBan had seen all four adden *820 da and whether he had included the outside plumbing and sprinkler work in his price because Grinnell’s price was substantially lower than the only other bid. (Ex. 7, Affidavit of Don Matherne; Leblanc Depo. at 49, 52.) Further, Mr. Leblanc testified that he told LeBan that he would give him the opportunity to confirm Grinnell’s bid and asked LeBan to call him back. (Leblanc Depo. at 52.) Leblanc testified that he called LeBan back a few minutes later to find out if Math-erne could use its bid price. Id. at 53. Leblanc stated, “He told me he had seen all the addenda, his price was good, use the price. I hung up the phone, told Don, use the price.” Id. In his deposition, Mr. LeBan testified that he did not remember these phone calls or their content. LeBan Depo. at 60-63. However, Matheme’s phone records indicate that two calls were made between 3:25 and 3:45 on February 2,1993 to a phone number, which LeBan admitted was Grinnell’s phone number. Ex. 6 to Plaintiffs Motion, Phone Bill; LeBan Depo. at 59-60. Before 4:00 p.m. on February 2, 1993, Matherne submitted its general bid, which incorporated the $79,500 Grinnell bid, to the School Board.

Grinnell claims that on February 8,1995, it learned for the first time of the existence of addenda 3 and 4. It claims that upon learning of these addenda, it called Matherne to revoke its subcontract offer. LeBan testified that when he saw the two addenda, he called Don Matherne to tell him that these addenda would drastically increase the price Grinnell had previously quoted. LeBan Depo. at 68. Matherne replied that he had already given the bid to the School Board, that he had used Grinnell’s quote and that he could not change his price. Id. Indeed, Matherne’s bid to the School Board was irrevocable for thirty days. Ex. D to Defendant’s Motion, Advertisement for Bids. On February 24 or 25, LeBan told Don Matherne that the price would be increased to over $200,000. LeBan Depo. at 69. On March 2, 1995, LeBan wrote Math-erne that after reviewing all of the plans with addenda, the price would be $237,500. Ex. H to Defendant’s Motion.

Matherne’s bid to the School Board on February 2, 1993 was the lowest among the general contractors; however, even its bid was above the School Board’s budget. On February 6, 1993, Matherne met with the School Board’s architects to discuss ways to reduce costs and get the Project within the budget. The School Board requested an opinion from the Attorney General concerning whether the adoption of post-bid modifications would violate the Louisiana Public Bid Law, La.R.S. 38:2211, et seq. Specifically, it asked whether it “could make changes to the construction contract in an amount approximately 8% less than the lowest bid and award the contract to the previous low bidder without the necessity of throwing out all bids and readvertising.” Att. 1 to Plaintiffs Motion, Opinion of Attorney General (“AG. Opinion”) at 1. The Attorney General issued an opinion that such post-bid modifications would not violate the Public Bid Law. Id.

The School Board voted to accept Math-erne’s bid with the changes on March 2, 1993. Matherne and the School Board signed a contract on March 23,1993, with an effective date of March 9, 1993, for a price of $7,790,-957, a reduction from Matherne’s original bid of $8,500,000. The savings were effected by two means — the School Board elected part of the alternates that were contained in the original bids, and it made certain “post-bid changes” in design by a “change order” executed contemporaneously with its contract. On March 24, 1993, Matherne transmitted a standard form agreement to Grinnell for the sprinkler system work at its bid price of $79,500. The agreement incorporated the post-bid changes and addenda 3 and 4. On April 7, 1993, Grinnell returned the contract to Matherne, stating that it was unable to accept that contract price for the scope of work involved in the Project. Thereafter, Matherne contracted with Superior Sprinkler Corporation to perform the fire protection system work for $192,985. Matherne filed this litigation to recover the difference between the $79,500 bid and the substitute contract price of $192,985.

Grinnell contends that it is entitled to summary judgment dismissing plaintiffs claim against it on three theories. First, Grinnell claims that the contract between the School Board and Matherne is absolutely *821 null because the parties violated Louisiana’s Public Bid Law by issuing addendum number 4 on the same day that the bids were due and by engaging in significant post-bid negotiations and alterations. Second, Grin-nell alleges that Matherne had no contract with Grinnell because Grinnell timely withdrew its bid before the School Board accepted Matheme’s bid. Thirdly, Grinnell claims that there was never a contract between Grinnell and Matherne because the agreement Matherne forwarded to Grinnell on March 24, 1993 constituted a counter-offer containing terms substantially different than the terms upon which Grinnell’s bid was based.

Matherne’s motion for summary judgment alleges several alternative theories of recovery against Grinnell that are based in contract, quasi-contract and negligence. Because the Court finds that Matherne states a claim for detrimental reliance under La.Civ. Code art.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Weitz Co. v. Hands, Inc.
882 N.W.2d 659 (Nebraska Supreme Court, 2016)
Water Craft Management, L.L.C. v. Mercury Marine
361 F. Supp. 2d 518 (M.D. Louisiana, 2004)
JCD Marketing Co. v. Bass Hotels and Resorts, Inc.
812 So. 2d 834 (Louisiana Court of Appeal, 2002)
Barriere Const. v. Terrebonne Consol. Gvt.
754 So. 2d 1123 (Louisiana Court of Appeal, 2000)
Hard Rock Const. v. Parish of Jefferson
688 So. 2d 134 (Louisiana Court of Appeal, 1997)
Percy J Matherne v. Grinnell Fire
102 F.3d 550 (Fifth Circuit, 1996)

Cite This Page — Counsel Stack

Bluebook (online)
915 F. Supp. 818, 1995 U.S. Dist. LEXIS 20836, 1995 WL 803789, Counsel Stack Legal Research, https://law.counselstack.com/opinion/percy-j-matherne-contractor-inc-v-grinnell-fire-protection-system-co-lamd-1995.