State, Through Office of Governor v. LW EATON CONST. CO.
This text of 392 So. 2d 477 (State, Through Office of Governor v. LW EATON CONST. CO.) is published on Counsel Stack Legal Research, covering Louisiana Court of Appeal primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.
Opinion
STATE of Louisiana, THROUGH the OFFICE OF the GOVERNOR, Division of Administration and the Facility Planning and Control Department,
v.
L. W. EATON CONSTRUCTION COMPANY, INC. et al.
Court of Appeal of Louisiana, First Circuit.
Joseph S. Cage, Jr., Robert Lee, Monroe, for plaintiff-appellant, State of Louisiana, through office of the Governor, Etc.
Frank P. Simoneaux, Baton Rouge, for defendant-appellee, L. W. Eaton Const. Co., Inc.
John N. Samaha, Baton Rouge, for defendant-appellee, American Arbitration Ass'n, Inc.
Before LOTTINGER, EDWARDS and PONDER, JJ.
*478 LOTTINGER, Judge.
One issue is before us in these two injunction proceedings, which have been consolidated on appeal: Was the public bid law (La.R.S. 38:2211 et seq.) violated when the State awarded the contract for construction of the School of Veterinary Medicine on the Louisiana State University campus in Baton Rouge?
The State first sought, but failed to obtain, a preliminary injunction to enjoin arbitration proceedings commenced by the defendant, L. W. Eaton Construction Company, after construction of the school was completed. While the appeal from the trial court's refusal to grant the preliminary injunction was pending in this court, the hearing for a permanent injunction took place. The State was again unsuccessful in the lower court, and a second appeal was taken.[1] In both proceedings, the State claimed the contract containing the arbitration provision was absolutely null because Eaton employees learned of impending plan changes the day before bids were submitted. The State contended that Eaton's knowledge of the plan changes, regardless of whether Eaton relied on such knowledge, violated the bid law provision requiring that any addendum modifying the plans and specifications within 72 hours prior to bid opening necessitated a one-week delay in bid opening. La.R.S. 38:2211(B). The State also claimed that Eaton violated the provision of the bid law requiring that bids be submitted "according to the contract, plans and specifications as advertised. La. R.S. 38:2211(A), emphasis ours.[2]
In both proceedings, Eaton asserted that the contract was validly confected in conformance with the bid law. The company also claimed the State should be estopped from asserting the contract's invalidity because the State eventually accepted the change in steel size and later accepted the entire project.
Because the issues in both proceedings are identical, we consolidated these cases on appeal. Both proceedings will be handled in this opinion, but separate judgments will be rendered.
THE FACTS
On February 27, 1973, Eaton submitted a $15.8 million bid on the vet school job, some $400,000 less than the next to lowest bidder. The day before the bids were submitted, Robert Cleveland, a structural engineer for the architect on the job, informed Eaton's principal estimator that the plans and specifications for reinforcing steel bars probably would be changed. As advertised prior to bidding, the plans and specifications called for grade A-40 steel. The change would allow suppliers to furnish grade A-60 steel. Because the A-60 steel had a stronger tensile strength than the A-40 steel, use of the stronger steel allowed the size of some of the bars to be reduced. The reduction in circumference resulted in a reduction in the weight and the price of the steel used on the job.
When a state inspector discovered the smaller sized steel about a year after construction commenced, the State sought a credit for the reduced steel. Eaton vigorously protested allowance of a credit for the smaller and cheaper steel, claiming that the credit had been reflected in its bid on the job. Later, however, Eaton reluctantly agreed to allow a $15,650.00 credit for the reduced amount of steel. A change order officially approving the stronger but smaller sized steel was issued after the credit was given to the State, and the job proceeded to completion. Both sides in this litigation agree that the steel used on the job is as good as or better than that specified originally in the plans and specifications. The State accepted the building as substantially complete in May, 1978, and the school is now occupied.
*479 In June, 1978, under the arbitration clause in the contract, Eaton filed a demand for arbitration with the second defendant in this case, the American Arbitration Association, seeking $6.7 million in an upward equitable adjustment to the contract price. The State then filed this suit to enjoin the arbitration proceedings on the ground that the contract containing the arbitration provision was null and void because of the alleged bid law violation.
At the hearing on the preliminary injunction and in additional testimony at the permanent injunction hearing, Eaton's executive vice president, David H. Broussard, testified that Eaton placed no reliance on the information it received from the structural engineer on the day before the bids were submitted. Mr. Broussard's testimony and Eaton's documentary evidence indicate that Eaton's final bid was calculated on the price of A-40 steel as per the plans and specifications as advertised. The evidence shows that the change in the size and price of the steel was not officially approved by the structural engineer until after Eaton learned that it would be awarded the contract on the job. The preponderance of the testimony indicates that Eaton's employees relied in good faith on the apparent authority of the structural engineer to change the steel size after bidding, but that Eaton did not rely on the purported plan changes in submitting its bid.
Additionally, Eaton employees testified that they were under the impression that other contractors and subcontractors had been notified of the probable plan change in steel specifications. However, the vice president and estimator of one of the other contractors who bid on the job could not specifically recall whether he was informed of the impending plan change prior to bidding. Conspicuously missing from the record in this regard is the testimony of the structural engineer who purportedly informed Eaton and perhaps other contractors of the planned change in specifications. Our opinion in this case, however, does not turn on whether Eaton alone received the prebid information.
The State places much emphasis on the fact that Eaton changed its position concerning its reliance on the information received by the structural engineer on the day prior to bidding. When the State sought the credit for the smaller steel, Eaton contended that the bid price reflected the smaller steelan indication that Eaton had placed reliance on the structural engineer's information. In these two proceedings, however, Eaton is claiming that it did not rely on the structural engineer's statement when it made the bid on the job. Eaton's inconsistent positions were explained in detail by Mr. Broussard during his lengthy testimony on the stand. Broussard admitted that he had not fully investigated his files when the State sought the credit and that he truly believed at that time that no credit was due. Upon further investigation in preparation for the injunction proceedings, Broussard discovered that Eaton's bid had been based on the A-40 steel as provided in the plans and specifications. The trial judge believed Mr. Broussard's explanation and expressly so stated. Our thorough review of the record convinces us that the trial court correctly decided the factual issues in this case.
Free access — add to your briefcase to read the full text and ask questions with AI
Related
Cite This Page — Counsel Stack
392 So. 2d 477, Counsel Stack Legal Research, https://law.counselstack.com/opinion/state-through-office-of-governor-v-lw-eaton-const-co-lactapp-1980.