Girard Insurance & Trust Co v. Cooper

162 U.S. 529, 16 S. Ct. 879, 40 L. Ed. 1062, 1896 U.S. LEXIS 2231
CourtSupreme Court of the United States
DecidedApril 20, 1896
Docket164
StatusPublished
Cited by43 cases

This text of 162 U.S. 529 (Girard Insurance & Trust Co v. Cooper) is published on Counsel Stack Legal Research, covering Supreme Court of the United States primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Girard Insurance & Trust Co v. Cooper, 162 U.S. 529, 16 S. Ct. 879, 40 L. Ed. 1062, 1896 U.S. LEXIS 2231 (1896).

Opinion

Me. Justice Beown,

after stating the case, delivered the opinion of the court.

There can be no doubt of the correctness of the master’s finding with regard to the work done by Cooper & Son prior to June 3, 1891. This work was done under a contract made May 23, 1890, between Cooper & Son and Chadick, who was at the time general manager of the Choctaw Coal and Bail-way Company, and who, by authority of the board of directors, had arranged, with the Judiciary Committees of Congress for the location of the United States court at South McAles-ter, upon condition -that the company would provide the officers of the court, free of all cost, with suitable quarters. While the contract was not signed by Chadick, but by Cox, the architect, it was so signed under special authority from-Chadick, and it .provided that the work was tp be done to the satisfaction and under the supervision of the architect. Bills were rendered for this work, which were certified by the chief engineer and assistant manager of the company. Mr. Chadick *538 testified that the appellee’s claim for this work is just and correct, and in a letter of June 19, he says that he is unable to settle the amount due, but expects to be able to do so early in July. It is true that the company, in December, 1890, was put into' the hands of receivers; but, with full knowledge of all that was being done, they allowed the work to continue without interruption, until June 3, 1891, and were justly held to be liable for what had been done up to that time, according to the terms of the contract. A settlement appears to have, been had on- January 8, and some of the subsequent work was done without a prior order of the court, but no objection was ever made to it by the receivers upon that ground prior to June 3 when the work was stopped.

The principal matter in dispute relates to the proper interpretation of the order of October 13, 1891, referring the claim of Cooper & Son to the master,- “to ascertain the amount justly and equitably due as the true value of the work done and materials furnished,” and to the refusal of the master, under the terms of this order, to permit the appellants to prove the cost and value of the building, without reference to any contract. In this connection, the master found that the contract under which the work, was done was executed by agents of the receivers, having authority so to do, and under special direction and approval of the receivers themselves, and of the court; that the work was performed and materials furnished in reliance upon this contract; that the receivers knew of this, and with such knowledge approved of this work, received the benefit of it, and took possession of the hotel; and also that the work was done in strict accordance with the. plans and specifications. While the findings of the master in this, particular are not absolutely binding upon the court, there, is a presumption in their favor, and they will not be set aside or modified in the absence of some clear error or mistake. Camden v. Stuart, 144 U. S. 104, 118.

On June 3 the receivers ordered the work to be stopped, and a bill to be rendered for what had been done up to that time, saying that the receivers would “ then furnish you with-designs and directions as to the work to be done, and you *539 will name a gross sum for the performance of -the. same, which' we will submit to the court for their approval or disapproval.” The matter rested here until June 23, when, as the result of a conference between Mr. Oox, the architect, and Major Nelson, the master in chancery, the receiver addressed the following letter to Cooper & Son:

Gentlemen : We have been advised by Maj. William Nelson, master, of the following order of the United Stages court: ‘ You are hereby directed to finish up court-room, qll the offices on lower floor of hotel building, and also such rooms on the second floor as may be necessary, in accordance with estimates to be hereafter furnished.’ ”

In the meantime, and in consequence of the same conference,. Chadick instructed the architect, Mr. Cox, to make the plans and specifications of what was required for the accommodation of the court, and send them up to Muscogee for the inspection of Major Nelson, the master. He sent them there on June 6. The master appears to have submitted them to the judge and marshal, who approved of them, and directed the work to be done, though no order of court was entered to that effect, and no Question of. price was considered, this matter being left to the receivers. Upon the return of these plans and specifications to Mr. Cox, the architect, he drew up a contract in compliance with them, sent one copy to Mr. Cooper, with specifications annexed, and another copy to Mr. Chad-ick’s office. Cooper & Son, who appear to have already seen the plans and. specifications, addressed Mr. Chadick a letter under date of June 24, agreeing to do the work for $10,250. Chadick testified that his recollection was’ that the receivers accepted the proposition, though he seems never to have formally answered the letter. But however this may be, a contract was drawn up bearing date July Y, and signed by Cooper & Son, and by Cox, as supervising architect, not at the foot of the contract itself, but at the end of the specifications, which followed the contract. Mr. Cox testified that Chadick ordered the work to go ahead, and knowing the amount, he inserted it in the contract; that Mr. Chadick came *540 to the building after this, told him what the court wanted and approved of, and ordered him to go ahead with it. In the same connection, Chadick testified that the contract was drawn up by Cox and submitted to him ; that he approved it, not formally, because Mr. Gowen was not there, but looked it over and thought it was just and right. Mr. Cox was the supervising architect, appointed first by the manager and continued by the receivers, and all the contracts for buildings and specifications for buildings before this had been drawn by him.. This was in the ordinary line of his business and duty. “I knew that Mr. Cooper was working upon this building in reliance on this contract and in accordance with its terms; I supposed these specifications would govern the settlement of it; Mr. Gowen knew of this contract at the time.; he was present when it was given to me in the early part of July!” Mr. Cooper also testified that he made his bid in compliance with directions.from Mr. Chadick ; that he, Chadick, accepted it and told him to go to work, which he did, and completed the work according to the contract, plans and specifications furnished him by Mr. Cox. It further appears that after the contract was completed a bill was made out showing an amount due of $11,092.74, and that Mr. Cox certified to the correctness of the account.

In this connection Mr. Gowen, the principal witness for the appellants, states that, shortly after his appointment, permission was asked of the court to enter into a contract for the roofing of the building, and an order procured to that effect, and that he concurred in the making of a contract for this work; that he gave, the matter no further consideration until March, when his attention was called to the -fact that the inside work was still going on; that he then called Mr.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Pocchia v. Prudential Insurance
74 F. Supp. 2d 240 (E.D. New York, 1999)
Aini v. Sun Taiyang Co., Ltd.
964 F. Supp. 762 (S.D. New York, 1997)
Noland Co. v. Nelson-Roanoke Corp.
360 S.E.2d 852 (Supreme Court of Virginia, 1987)
Superior Oil Co. v. Udall
409 F.2d 1115 (D.C. Circuit, 1969)
Woodbury v. United States
192 F. Supp. 924 (D. Oregon, 1961)
Vandenbergh v. Allied Van Lines, Inc.
351 P.2d 537 (Montana Supreme Court, 1960)
Julius Hyman & Co. v. Velsicol Corp.
233 P.2d 977 (Supreme Court of Colorado, 1951)
Higby v. Hooper
221 P.2d 1043 (Montana Supreme Court, 1950)
Means v. Dierks
180 F.2d 306 (Tenth Circuit, 1950)
Power Service Corporation v. Joslin
175 F.2d 698 (Ninth Circuit, 1949)
Clubb v. Hetzel
198 P.2d 142 (Supreme Court of Kansas, 1948)
Caten v. Salt City Movers & Storage Co.
149 F.2d 428 (Second Circuit, 1945)
Thompson v. Baltimore & OR Co.
59 F. Supp. 21 (E.D. Missouri, 1945)
J. P. C. Petroleum Corp. v. Vulcan Steel Tank Corp.
118 F.2d 713 (Tenth Circuit, 1941)
Adams County v. Northern Pac. Ry. Co.
115 F.2d 768 (Ninth Circuit, 1940)

Cite This Page — Counsel Stack

Bluebook (online)
162 U.S. 529, 16 S. Ct. 879, 40 L. Ed. 1062, 1896 U.S. LEXIS 2231, Counsel Stack Legal Research, https://law.counselstack.com/opinion/girard-insurance-trust-co-v-cooper-scotus-1896.