John Cowan, Inc. v. Meyer

94 A. 18, 125 Md. 450, 1915 Md. LEXIS 227
CourtCourt of Appeals of Maryland
DecidedApril 7, 1915
StatusPublished
Cited by24 cases

This text of 94 A. 18 (John Cowan, Inc. v. Meyer) is published on Counsel Stack Legal Research, covering Court of Appeals of Maryland primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
John Cowan, Inc. v. Meyer, 94 A. 18, 125 Md. 450, 1915 Md. LEXIS 227 (Md. 1915).

Opinion

Thomas, J.,

delivered the opinion of the Court.

This suit is on the common counts, and a special count which alleges “that on or about the 19th day of August, 1912, the plaintiff contracted with the defendant to perform *456 all the work in excavating, at the Baltimore Fidelity Warehouse, corner of Iiillen and High streets, in the City of Baltimore, according to drawings and specifications prepared by Emory & Hussear, Architects, including all trenches and footing foundations, at and for the price for excavating and hauling of $1.35 per yard. Said work to be done within forty working days from the date of said contract,” and that “The plaintiff has performed all of said work, and done all of the hauling provided for in said contract in accordance with the terms of said contract, and has fulfilled and done all things required to be done by him thereunder, together With extra work ordered by the defendant, but the defendant has not paid in full amount of $9,981.45, which it agreed to pay, and there remains overdue and unpaid the sum of $2,181.45.” There was filed with the declaration an account in which the defendant is charged with the cost of digging 7,350 cubic yards of dirt at $1.35, amounting to $9,922.50, and a number of small items bringing the total charges to $9,981.45, against which there is a credit of “By cash, $7,-800.00,” leaving a balance of $2,181.45.

The defendant pleaded that it “never promised” and that “it was never indebted as alleg'ed,” and, for a third plea, that the plaintiff was indebted to the defendant in an amount greater than the plaintiff’s claim, etc. The seventh count of the plea of set-off charges “that on or about the 19th of August, 1912, the plaintiff contracted with the defendant to do certain excavating at the corner of Hillen and High streets, in the City of Baltimore, in accordance with certain plans and specifications, 'and all hauling at and for the sum of $1.35 per cubic yard; part of said work to be done in the manner following: ‘Beginning at the north end of the building and working toward the front to a distance of one hundred and twenty-five feet (125’) to a depth required, including all trenches and footing foundations, same to be completed in twenty working days from the said 19th day of August, 1912.’ And the said plaintiff further agreed, to com *457 píete the whole work in forty working days. And the said plaintiff further agreed with this defendant to pay to it the sum of ninety-five dollars ($95.00) per day as liquidated damages for each and every day thereafter exceeding either the twenty days or forty days time limit,” and “that the plaintiff did not complete that portion of the work which under the terms of the said agreement was to have been completed in twenty working days, but on the contrary exceeded the time limit by twenty-nine working days. And the defendant claims $2,755.00, which amount the defendant is willing to set off against the plaintiff’s claim, and prays judgment for the excess.”

The plaintiff joined issue on the first and second pleas and replied to the third plea that he never promised, etc., as alleged.

It appears from the evidence that a number of contractors, including the defendant, bid for the work of erecting, for the Baltimore Fidelity Warehouse Company, a large warehouse on the comer of Ilillen and High streets according to drawings (blue prints) and specifications prepared by Emory- & Nussear, architects, and that the plaintiff, a sub-contractor, submitted to the contractors bids for the work of excavating for the building in accordance with those drawings and specifications. The contract was awarded by the Warehouse Company to the defendant on the 17th of August, 1912. The building was to be two hundred and fifty feet long, and the contract between the defendant and the Warehouse Company provided that it should be completed within six months from the 17th day of August, and that the defendant should pay to the Warehouse Company a fixed sum per day for each and every day the completion of the building was delayed beyond that time, as liquidated damages, etc. It does not appear from the record what sum per day the defendant agreed to pay, but it is stated in the briefs' of counsel for the appellant and appellee that the amount was $95.00. The record contains the following extracts from the specifications, which *458 are said to be the only provisions relating to tbe necessary excavations:

“Excavation—Excavate for all foundation walls, piers, cappings to piles, etc., as may be shown or required. The earth taken from such excavations shall be used for leveling and filling in up to basement floor slab, and shall be filled in and well wetted and rammed in place around all walls, piers, etc., as the work progresses. Where necessary this contractor shall furnish and ram in place additional fill of good and substantial quality, and shall remove from the premises all superfluous earth, rubbish, debris, etc.
“Bailing—Bail and pump out all soil and water that may collect in the excavations from drains, springs, rain, or otherwise, and see that the excavations are well drained before any mason work is done in them.
' “Note—Bidders shall visit site before submitting estimate on this work, and shall acquaint themselves with existing conditions. The work of this contract shall be so conducted and executed that it will not interfere in any way with the business of the Owner in and about the premises, and no street shall be blocked or so obstructed as to impede traffic.
“Piling—This Oontraetor shall furnish and properly place in position all piles necessary to properly support the building so that no settlement shall occur, all as shown and called for on drawings and in these specifications. Piles shall be of concrete, etc.”

The plaintiff having submitted a bid to the defendant for the work of excavating for the building, the defendant, on the day it entered into the contract with the Warehouse Company, sent for the plaintiff, and the plaintiff and defendant entered into the following contract, in the form of an offer by the former and an acceptance by the latter :

“Baltimore, August 19, 1912.

Mess. John Cowan, Inc.

Gentlemen:—

I hereby propose to do all the excavating at the Bal *459 timore Fidelity Warehouse, corner Hillen and High Sts., according to drawings and specifications prepared by Emory & Mussear, Architects, as follows:

Beginning at the north end of the building and working toward the front to a distance of 125 feet and to the depth required, including all trenches and footing foundations, same to be completed in twenty working-days from above date. I also further propose to complete the entire excavation necessary for the building-within forty working days from above date.

The price for excavating and hauling away same-to be One Dollar and Thirty-jive Gents ($1.35) per yard.

I also further agree that if at any time you should see fit to put a steam shovel on the works I will haul the dirt away after being loaded on my wagons by the-steam shovel for the sum of One Dollar

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Gonsalves v. Bingel
5 A.3d 768 (Court of Special Appeals of Maryland, 2010)
Barrie School v. Patch
933 A.2d 382 (Court of Appeals of Maryland, 2007)
Willard Packaging Company, Inc. v. Javier
899 A.2d 940 (Court of Special Appeals of Maryland, 2006)
Howarth v. Feeney, 86-3543 (1992)
Superior Court of Rhode Island, 1992
Holloway v. Faw, Casson & Co.
552 A.2d 1311 (Court of Special Appeals of Maryland, 1989)
Schrier v. Beltway Alarm Co.
533 A.2d 1316 (Court of Special Appeals of Maryland, 1987)
Traylor v. Grafton
332 A.2d 651 (Court of Appeals of Maryland, 1975)
Massachusetts Indemnity & Life Insurance v. Dresser
306 A.2d 213 (Court of Appeals of Maryland, 1973)
Siler v. Marshall
247 A.2d 385 (Court of Appeals of Maryland, 1968)
Eastover Stores, Inc. v. Minnix
150 A.2d 884 (Court of Appeals of Maryland, 1959)
Alois v. Waldman
149 A.2d 406 (Court of Appeals of Maryland, 1959)
Compania De Astral, S. A. v. Boston Metals Co.
107 A.2d 357 (Court of Appeals of Maryland, 1954)
Matthews v. Kernewood, Inc.
40 A.2d 522 (Court of Appeals of Maryland, 1945)
Tahir Erk v. Glenn L. Martin Co.
143 F.2d 232 (Fourth Circuit, 1944)
Foster v. Hudson Valley Lumber Co.
37 F. Supp. 381 (D. Maryland, 1941)
Fidelity Deposit Co. of Maryland v. Jones
75 S.W.2d 1057 (Court of Appeals of Kentucky (pre-1976), 1934)
Duplex Envelope Co. v. Baltimore Post Co.
163 A. 688 (Court of Appeals of Maryland, 1933)
Wischhusen v. Spirits Co.
163 A. 685 (Court of Appeals of Maryland, 1933)
Wischhusen v. American Medicinal Spirits Co.
163 Md. 565 (Court of Appeals of Maryland, 1933)
Hammaker v. Schleigh
147 A. 790 (Court of Appeals of Maryland, 1929)

Cite This Page — Counsel Stack

Bluebook (online)
94 A. 18, 125 Md. 450, 1915 Md. LEXIS 227, Counsel Stack Legal Research, https://law.counselstack.com/opinion/john-cowan-inc-v-meyer-md-1915.