Valentini v. City of Adrian
Opinions
In this case the plaintiff, a sewer contractor, brought suit against the defendant city for damages claimed to have been caused by the excessive cost of constructing a sewer for the city, on account of the city’s having misrepresented the character of subsoil conditions, known to the defendant city, namely, quicksand and excessive water. Plaintiff claimed this resulted in his low construction bid for the project and that the unexpected subsoil conditions caused delay, and greatly increased the cost of constructing the sewer. The defendant city filed a cross claim for damages claimed by it to have resulted from plaintiff’s delay, for failure to entirely complete the project; and for the anticipated cost to the city of completing the project.
Issues were joined, considerable testimony taken before a jury, and the court submitted the respective claims of the parties to the jury under appropriate [532] instructions, to decide the disputed questions of fact. The jury returned a verdict for the plaintiff in the sum of $115,741.15, but did not announce any verdict on the cross claim of the city. However, we may assume that the jury, in rendering its verdict of $115,-741.15 for the plaintiff, followed the instruction of the court in that regard, concerning which neither party claims error. The court had charged the jury:
“Now briefly, in summary, you should * * * first determine whether or not the plaintiff is entitled to any damages on his declaration, and if so, how much.
“You should next determine whether or not defendant is entitled to any damages on its claim for damages, and if so, how much.
“Either of these determinations may come out to a figure of zero or nothing. After making these 2 determinations you should subtract the 2 figures, even though 1 figure may be a zero, and allow to the party suffering the most damages, if any, the amount of the difference, if any. * * *
“If you find that neither party is entitled to damages, you will return and announce to the court, your foreman or forewoman speaking, ‘We find no cause of action for either party.’ ”
The defendant city (cross plaintiff) has appealed from the judgment entered for the plaintiff.
Previous to 1950 the city had employed consulting engineers and obtained a master plan for a municipal sewer system. A part of the plan was the construction of an addition to the sewer system of about 8,-600 feet across what is known as the Sunnyside area, terminating at the city disposal plant. There had' previously been 2 sewers built in this area.
In 1950 the city solicited bids for the construction of said additional sewer across the Sunnyside area. The plaintiff obtained from the city’s consulting engineers and examined a copy of the proposed plans [533] and specifications and spent some time examining the job, but did not make borings or otherwise examine subsoil conditions. The city’s proposed plans and specifications which were on file included the following statements:
“Construction Conditions. It is required that each bidder will examine the drawings and specifications for this work and make a personal examination of the site of the proposed work and its surroundings. * * #
- “Subsoil Conditions. Borings have been made and logs thereof are recorded on the drawings.Footnotes
79 N.W.2d 885 (Valentini v. City of Adrian) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.