Hunt Construction Group, Inc. v. Construction Services, Inc.

375 F. Supp. 2d 612, 2005 U.S. Dist. LEXIS 13908, 2005 WL 1590656
CourtDistrict Court, E.D. Michigan
DecidedJune 30, 2005
DocketCIV. 02-40126
StatusPublished
Cited by2 cases

This text of 375 F. Supp. 2d 612 (Hunt Construction Group, Inc. v. Construction Services, Inc.) is published on Counsel Stack Legal Research, covering District Court, E.D. Michigan primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Hunt Construction Group, Inc. v. Construction Services, Inc., 375 F. Supp. 2d 612, 2005 U.S. Dist. LEXIS 13908, 2005 WL 1590656 (E.D. Mich. 2005).

Opinion

*614 MEMORANDUM OPINION AND ORDER DENYING DEFENDANT CSTS MOTION FOR SUMMARY JUDGMENT AND GRANTING IN PART AND DENYING IN PART PLAINTIFF HUNT’S MOTION FOR SUMMARY JUDGMENT

GADOLA, District Judge.

I. INTRODUCTION

This action involves a contract dispute between two corporations: Plaintiff Hunt Construction Group, Incorporated, and Defendant Construction Services, Incorporated. The parties bring claims against each other for contractual and quasi-contractual remedies. Before the Court are two motions and their voluminous exhibits: (1) Defendant CSI’s motion for summary judgment on Plaintiffs complaint, and (2) Plaintiff Hunt’s motion for summary judgment on Defendant’s counterclaims. The Court held a hearing on these motions on September 15, 2004. Based on the plain language of the subcontract agreement and various releases, the Court will deny Defendant CSI’s motion for summary judgment on Plaintiffs complaint and will grant in part and deny in part Plaintiffs motion for summary judgment on Defendant CSI’s counterclaims.

II. BACKGROUND

This action arises out of the construction of the Midfield Terminal Project at Detroit Metropolitan Airport. Plaintiff Hunt Construction Group, Incorporated (“Plaintiff Hunt”) was the general contractor on the project. Plaintiff Hunt entered into a subcontract with Defendant Construction Services, Incorporated (“Defendant CSI”) for certain ornamental metal work, such as the column covers and wall covers throughout the terminal, as well as for glass railings and other work. The subcontract agreement, a document of over 40 pages, essentially provided that Defendant CSI agreed to supply and install various items for a fixed price of $14,405,052.00. The agreement was executed by both parties: Defendant CSI signed the contract on April 24, 2000 and Plaintiff Hunt signed the contract on May 8, 2000.

The work by Defendant CSI was not finished by the deadline. The parties dispute the causes of the delay. Plaintiff Hunt, the general contractor, terminated Defendant CSI for default and subsequently completed some of the work that Defendant CSI had agreed to complete.

Plaintiff Hunt brought suit against Defendant CSI alleging various breaches of the subcontract agreement, including Defendant CSI’s alleged failure to supply materials, failure to complete the work, failure by Defendant CSI to pay sub-subcontractors and suppliers, failure to meet work schedules and “turnover milestones,” failure to submit required reports, failure to provide on-site supervision and staffing, and failure to clean its work area. See Complaint. Defendant CSI now seeks summary judgment on all counts in Plaintiff Hunt’s complaint.

Defendant CSI also filed a counterclaim in this action. The counterclaim seeks damages for the following counts: that Hunt had “superior knowledge” of the project that it did not disclose, quantum me-ruit, breach of warranty of specifications, breach of duty to issue equitable adjustment, breach of contract, total excess cost claim, and declaratory judgment. Plaintiff Hunt seeks summary judgment on all counts in Defendant CSI’s counterclaim.

III.LEGAL STANDARD FOR SUMMARY JUDGMENT

Rule 56(c) of the Federal Rules of Civil Procedure provides that summary judgment “shall be rendered forthwith if the pleadings, depositions, answers to interrogatories, and admissions on file, together with the affidavits, if any, show that there *615 is no genuine issue as to any material fact and that the moving party is entitled to judgment as a matter of law.” Fed. R.Civ.P. 56(c). Summary judgment is appropriate if the moving party demonstrates that there is no genuine issue of material fact regarding the existence of an essential element of the nonmoving party’s case on which the nonmoving party would bear the burden of proof at trial. Celotex Corp. v. Catrett, 477 U.S. 317, 322, 106 S.Ct. 2548, 91 L.Ed.2d 265 (1986); Martin v. Ohio Turnpike Comm’n, 968 F.2d 606, 608 (6th Cir.1992).

In considering a motion for summary judgment, the Court must view the facts and draw all reasonable inferences in a light most favorable to the nonmoving party. 60 Ivy St. Corp. v. Alexander, 822 F.2d 1432, 1435 (6th Cir.1987). The Court is not required or permitted, however, to judge the evidence or make findings of fact. Id. at 1435-36. The moving party has the burden of showing conclusively that no genuine issue of material fact exists. Id. at 1435.

A fact is “material” for purposes of summary judgment if proof of that fact would have the effect of establishing or refuting an essential 'element of the cause of action or a defense advanced by the parties. Kendall v. Hoover Co., 751 F.2d 171, 174 (6th Cir.1984). A dispute over a material fact is genuine “if the evidence is such that a reasonable jury could return a verdict for the nonmoving party.” Anderson v. Liberty Lobby, Inc., 477 U.S. 242, 248, 106 S.Ct. 2505, 91 L.Ed.2d 202 (1986). Accordingly, when a reasonable jury could not find that the nonmoving party is entitled to a verdict, there is no genuine issue for trial and summary judgment is appropriate. Id.; Feliciano v. City of Cleveland, 988 F.2d 649, 654 (6th Cir.1993).

Once the moving party carries the initial burden of demonstrating that there are no genuine issues of material fact in dispute, the burden shifts to the nonmoving party to present specific facts to prove that there is a genuine issue for trial. To create a genuine issue of material fact, the nonmov-ing party must present more than just some evidence of a disputed issue. As the United States Supreme Court has stated, “there is no issue for trial unless there is sufficient evidence favoring the nonmoving party for a jury to return a verdict for that party. If the [nonmoving party’s] evidence is merely colorable, or is not significantly probative, summary judgment may be granted.” Anderson, 477 U.S. at 249-50, 106 S.Ct. 2505 (citations omitted); see Celotex, 477 U.S. at 322-23, 106 S.Ct. 2548; Matsushita Elec. Indus. Co., Ltd. v. Zenith Radio Corp., 475 U.S. 574, 586-87, 106 S.Ct. 1348, 89 L.Ed.2d 538 (1986).

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
375 F. Supp. 2d 612, 2005 U.S. Dist. LEXIS 13908, 2005 WL 1590656, Counsel Stack Legal Research, https://law.counselstack.com/opinion/hunt-construction-group-inc-v-construction-services-inc-mied-2005.