MidAmerica, Inc. v. Bierlein Companies, Inc.

CourtDistrict Court, W.D. Arkansas
DecidedOctober 9, 2020
Docket4:19-cv-04096
StatusUnknown

This text of MidAmerica, Inc. v. Bierlein Companies, Inc. (MidAmerica, Inc. v. Bierlein Companies, Inc.) is published on Counsel Stack Legal Research, covering District Court, W.D. Arkansas primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
MidAmerica, Inc. v. Bierlein Companies, Inc., (W.D. Ark. 2020).

Opinion

IN THE UNITED STATES DISTRICT COURT WESTERN DISTRICT OF ARKANSAS TEXARKANA DIVISION

MIDAMERICA, INC. PLAINTIFF

v. Case No. 4:19-cv-04096

BIERLEIN COMPANIES, INC. DEFENDANT

MEMORANDUM OPINION AND ORDER

Before the Court is Plaintiff MidAmerica, Inc.’s Motion for Partial Summary Judgment. ECF No. 34. Defendant Bierlein Companies, Inc. responded in opposition to the motion (ECF No. 43), and Plaintiff replied. ECF No. 50. Also before the Court is Defendant’s Motion for Summary Judgment. ECF No. 39. Plaintiff responded in opposition to that motion (ECF No. 48), and Defendant replied. ECF No. 49. The Court finds these matters ripe for consideration. BACKGROUND This action stems from a construction project involving the decommission, demolition, and decontamination of a retired power plant. Defendant served as the general contractor on the project. Plaintiff served as a subcontractor to provide various environmental remediation and waste disposal services. Plaintiff’s tasks under the subcontract included cleaning Fuel Oil from the plant’s pipelines and associated equipment and removing “Universal Waste.” ECF No. 2-1. Before the project began, Defendant asked Plaintiff to prepare a bid for its services based on certain plans and specifications. Plaintiff contends that those documents expressly stated that the material it would be cleaning was No. 2 Fuel Oil. Plaintiff states that it conducted an on-site inspection of the power plant prior to submitting its bid. Plaintiff further states that during the inspection, an agent of the plant’s owner, Entergy Arkansas, confirmed to Plaintiff that the material to be removed from the plant’s piping and associated equipment was No. 2 Fuel Oil. Plaintiff submitted a bid in the amount of $16,420.00 for the portion of the subcontract requiring the cleaning and disposal of Fuel Oil, and the parties subsequently executed a subcontract that incorporated the plant specifications originally provided by Defendant.1

Plaintiff states that after it commenced work on the project, it found that the material in the pipelines and associated equipment was No. 6 Fuel Oil instead of No. 2 Fuel Oil. There are six grades of Fuel Oil in the United States. The grades are referred to by number, ranging from No. 1 Fuel Oil to No. 6 Fuel Oil. As the number increases, so does the Fuel Oil’s boiling point, carbon chain length, and viscosity. Consequently, No. 6 Fuel Oil is the most physically robust and is significantly more difficult and expensive to remove from piping and equipment in comparison to No. 2 Fuel Oil. Plaintiff alleges that Defendant knew No. 6 Fuel Oil was present in the plant’s pipes from the onset of the project and that Defendant misrepresented what material it was contracting Plaintiff to clean up in the plans and specifications it submitted to Plaintiff. Plaintiff further alleges

that Defendant refused to allow Plaintiff to alter its bid after it discovered the No. 6 Fuel Oil, which would be significantly more costly to remove than No. 2 Fuel Oil. Ultimately, Plaintiff cleaned the No. 6 Fuel Oil under protest and at a cost that exceeded its bid price for the project. Plaintiff alleges that it incurred an additional $453,159.88 in costs to complete the work of removing the No. 6 Fuel Oil. Plaintiff also states that the elemental mercury it removed during the project did not fall under “Universal Waste” in the scope of the subcontract. Plaintiff contends that its scope of work

1 This amount, $16,420.00, only represents the amount Plaintiff bid to clean the plant’s pipelines and associated equipment. The subcontract also required Plaintiff to perform other clean up, demolition, and environmental remediation duties. The total amount of the subcontract was $746,341.00. did not include cleaning any mercury spills other than in a particular location on the project site. Plaintiff seeks $16,301.20 for the cost of this mercury removal it believes was outside the subcontract’s scope of work. Plaintiff commenced this action on August 20, 2019, seeking, in part, to recover the

increased costs associated with removing No. 6 Fuel Oil instead of No. 2 Fuel Oil and the removal of elemental mercury. To this end, Plaintiff brought claims for breach of contract and unjust enrichment, alleging that Defendant materially misrepresented the scope of work that Plaintiff was to perform under the subcontract. On July, 28, 2020, Plaintiff filed its Motion for Partial Summary Judgment, arguing that there is no genuine dispute that (1) the documents and specifications provided by Defendant to Plaintiff for bidding contained a material misrepresentation regarding the work to be completed; and (2) the misrepresentation caused Plaintiff to incur additional costs in completing its work. Accordingly, Plaintiff moves the Court to rule as a matter of law that Defendant breached the parties’ subcontract. That same day, Defendant filed its Motion for Summary Judgment, arguing that this action should be dismissed in its entirety because there is no

genuine dispute that all the work performed by Plaintiff was contemplated by the parties’ subcontract. LEGAL STANDARD I. Summary Judgment “Summary judgment is appropriate if the movant shows that there is no genuine dispute as to any material fact and the movant is entitled to judgment as a matter of law.” Hess v. Union Pac. R.R. Co., 898 F.3d 852, 856 (8th Cir. 2018) (citation omitted). Summary judgment is a “threshold inquiry of . . . whether there is a need for trial—whether, in other words, there are genuine factual issues that properly can be resolved only by a finder of fact because they reasonably may be resolved in favor of either party.” Anderson v. Liberty Lobby, Inc., 477 U.S. 242, 250 (1986). A fact is material only when its resolution affects the outcome of the case. Id. at 248. A dispute is genuine if the evidence is such that it could cause a reasonable jury to return a verdict for either party. Id. at 252.

In deciding a motion for summary judgment, the Court must consider all the evidence and all reasonable inferences that arise from the evidence in a light most favorable to the nonmoving party. Nitsche v. CEO of Osage Valley Elec. Co-Op, 446 F.3d 841, 845 (8th Cir. 2006). The moving party bears the burden of showing that there is no genuine issue of material fact and that it is entitled to judgment as a matter of law. See Enter. Bank v. Magna Bank, 92 F.3d 743, 747 (8th Cir. 1996). The nonmoving party must then demonstrate the existence of specific facts in the record that create a genuine issue for trial. Krenik v. Cnty. of LeSueur, 47 F.3d 953, 957 (8th Cir. 1995). However, a party opposing a properly supported summary judgment motion “may not rest upon mere allegations or denials . . . but must set forth specific facts showing that there is a genuine issue for trial.” Anderson, 477 U.S. at 256. The same standard applies where, as here, the parties have filed cross-motions for summary

judgment. Each motion should be reviewed on its own merits, with each side “entitled to the benefit of all inferences favorable to them which might reasonably be drawn from the record.” Wermager v. Cormorant Twp. Bd., 716 F.2d 1211, 1214 (8th Cir. 1983); see also Canada v. Union Elec. Co., 135 F.3d 1211, 1212-13 (8th Cir. 1998). II.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Anderson v. Liberty Lobby, Inc.
477 U.S. 242 (Supreme Court, 1986)
Donna Krenik v. County of Le Sueur
47 F.3d 953 (Eighth Circuit, 1995)
Enterprise Bank v. Magna Bank of Missouri
92 F.3d 743 (Eighth Circuit, 1996)
Lafayette Canada v. Union Electric Company
135 F.3d 1211 (Eighth Circuit, 1997)
Tkachik v. Mandeville
790 N.W.2d 260 (Michigan Supreme Court, 2010)
Cruz v. State Farm Mutual Automobile Insurance
648 N.W.2d 591 (Michigan Supreme Court, 2002)
Valentini v. City of Adrian
79 N.W.2d 885 (Michigan Supreme Court, 1956)
Goodwin, Inc v. Orson E Coe Pontiac, Inc
220 N.W.2d 664 (Michigan Supreme Court, 1974)
State v. Ochoa
244 N.W.2d 773 (Supreme Court of Iowa, 1976)
M & D ROBINSON CO. v. Dunitz
162 N.W.2d 318 (Michigan Court of Appeals, 1968)
Burkhardt v. City National Bank
226 N.W.2d 678 (Michigan Court of Appeals, 1975)
Holloway Construction Co. v. State
205 N.W.2d 575 (Michigan Court of Appeals, 1973)
Hammond v. United of Oakland, Inc
483 N.W.2d 652 (Michigan Court of Appeals, 1992)
Hunt Construction Group, Inc. v. Construction Services, Inc.
375 F. Supp. 2d 612 (E.D. Michigan, 2005)
Miller-Davis Co. v. Ahrens Construction, Inc.
848 N.W.2d 95 (Michigan Supreme Court, 2014)

Cite This Page — Counsel Stack

Bluebook (online)
MidAmerica, Inc. v. Bierlein Companies, Inc., Counsel Stack Legal Research, https://law.counselstack.com/opinion/midamerica-inc-v-bierlein-companies-inc-arwd-2020.